>> GOOD MORNING, EVERYONE. WELCOME TO
[Call to Order]
OUR COMMISSION WORKSHOP WHERE WE WILL DISCUSS THE DESIGN BILL FOR SABAL PALM PARK.CITY CLERK, PLEASE CALL THE ROLL.
>> [INAUDIBLE] DANIEL. IF EVERYONE PLEASE STAND AND OUR CITY MANAGER, ACTUALLY.
OUR NEWEST MEMBER OF THE TEAM.
STEPHEN, WILL YOU PLEASE LEAD US IN THE PLEDGE OF ALLEGIANCE AND WE HAVE A MOMENT OF SILENCE.
>> THANK YOU. PLEASE BE SEATED. FOR THE RECORD, [INAUDIBLE] DANIEL IS HERE. CITY MANAGER.
[1.a Design/Build for Sabal Palm Park Project (RFP No. 25-14R)]
I'M GOING TO TURN IT OVER TO OUR PERSON AND CONTRACTS MANAGER ADMINISTRATOR.
THIS IS FOR THE [INAUDIBLE] STATION THAT WE ISSUED RECENTLY FOR THE CONSTRUCTION OF SABAL PALM PARK.
WE HAVE PRESENTATIONS FROM VENDORS, SO WE'RE GOING TO DO TWO THIS MORNING AND TWO IN THE AFTERNOON.
BUT I'M GOING TO TURN IT OVER TO OUR PURSING AND CONTRACTS MANAGER.
MR. STEWART AND HE'S GOING TO PRY THE THE ROADMAP OR THE GUIDELINES.
>> YES. GOOD MORNING, EVERYONE.
MY NAME ONCE AGAIN IS STEVE STEWART, I'M THE PROCUREMENT AND CONTRACTS MANAGER WITH THE CITY.
JUST TO GIVE SOME PURPOSE AS TO WHY WE'RE HERE TODAY.
THE CITY RECENTLY ISSUED AN RFP FOR THE SABAL PALM PARK PROJECT.
WE ISSUED AN RFP TO GET A DESIGN BUILD IN WHICH WE PRESENTED THAT.
WE HAD THIS EIGHT ACRE LOT, AND WE WANTED CERTAIN THINGS ON THIS LOT, THINGS SUCH AS A SPLASH PAD, A DOG PARK, ON SITE PARKING, A MULTI PURPOSE FEEL FOR SOCCER FOOTBALL, ETC.
LANDSCAPING, WALK IN PATHS, ETC.
ESSENTIALLY JUST DICTATED FOR THIS EIGHT ACRE LOT THAT WE WANTED VARIOUS THINGS ON THE LOT, AND SO WE ISSUED THIS RP AND WE GOT A TOTAL OF FOUR PROPOSALS IN RESPONSE TO THE RP.
THE RP WERE REVIEWED AND SCORED BY A SELECTION COMMITTEE COMPRISED OF SEVEN CAPABLE EMPLOYEES.
THOSE EMPLOYEES SCORED ALL FOUR PROPOSALS AND IN GENERAL, THE SCORE OF FOUR FIRMS RANGE FROM 78-85 ON AVERAGE.
ESSENTIALLY, THERE WAS A BIT OF A SEVEN POINT DIFFERENTIAL BETWEEN ALL THE FIRMS THEY'RE PRETTY MUCH CLOSE, AND THE COSTS FOR EACH OF THE FOUR FIRMS RANGED FROM 8-14 MILL.
BIG DIFFERENCE IN THE PRICE THERE, BUT THE SCORES WERE ESSENTIALLY VERY CLOSE, WHICH DEMONSTRATED THAT ALL OF THE FIRMS ARE CAPABLE OF PROVIDING OR COMPLETE THIS PROJECT.
WHY ARE WE HERE TODAY? WE'RE HERE TO HAVE THESE FOUR FIRMS PRESENT THEIR PROPOSALS TO THE CITY COMMISSION IN ORDER FOR THE CITY COMMISSION JUST TO SEE WHAT IS BEING PROPOSED.
I THINK WE DID ASK YOU FIRM TO COME READY WITH ANY IMAGES, RENDERINGS, CONCEPTUAL, DESIGNS ETC TO HELP DEMONSTRATE WHAT YOU WOULD DO WITH THIS SPACE.
AS THESE PRESENTATIONS ARE PRESENTED TO THE PROPOSAL, WHAT WE'RE LOOKING FOR IS GUIDANCE FROM THE CITY COMMISSION ON THESE DIFFERENT PROPOSALS.
ANY INPUT IN GENERAL WILL HELP DICTATE, ESSENTIALLY, THE OUTCOME AND WHAT'S THE BETTER FIT? WHAT'S THE MOST ADVANTAGEOUS PROPOSAL TO THE CITY.
WITH THAT BEING SAID, NO FURTHER COMMENT FROM ME, I'M OPEN TO QUESTIONS BEFORE WE MOVE FORWARD TO PRESENTATIONS.
>> MR. STEWART, CAN YOU PROVIDE THE PRESENTERS THE TIMELINE IN THE ALLOCATION OF TIMES?
>> YES, DEFINITELY. WE'VE ESSENTIALLY JUST PENCILED A 45 MINUTE SLOT FOR EACH OF THE FOUR FIRMS. TO BREAK DOWN THAT 45 MINUTE SLOT, IT INCLUDES A 20 MINUTE PRESENTATION FROM EACH FIRM, FOLLOWED BY A 20 MINUTE Q&A SESSION FROM THE COMMISSION.
THEN WE HAVE AN EXTRA 5 MINUTES IN CASE WE RUN OVER, AS WELL AS JUST TIME, THAT TRANSITION TIME.
ONE FIRM GETS UP, ANOTHER FIRM NEEDS TO COME AND JUST GET THE POWERPOINT LOADED.
[00:05:05]
ESSENTIALLY 20 MINUTE PRESENTATION, 20 MINUTE Q&A, AND THEN WE HAVE A LITTLE FIVE MINUTE BUFFER IN BETWEEN.>> KEEPING TRACK OF THE TIME. WILL YOU BE KEEPING TRACK OF THE TIME?
>> NO TIME, SO WE'LL DO GOOD PHONE. I'LL PUT IT RIGHT HERE.
YOU'LL SEE EXACTLY THE TIME AS IT COUNTS DOWN, SO YOU'LL SEE EXACTLY HOW MUCH TIME YOU HAVE LEFT AND YOU'LL JUST KEEP AN EYE ON IT, AND I'LL GIVE A FIVE MINUTE WARMER.
WARNING AS WE GET DOWN WITHIN THAT FIVE MINUTE RANGE OF YOUR TIME RIGHT NOW.
>> YES. IN TOTAL FIVE, AND I GUESS THAT WOULD BE THE WAY TO ALLOCATE IT EVENLY, YES.
>> YOU'LL BE KEEPING TRACK OF THE MINUTES ON THAT.
>> THERE'S NO MANDATE YOU USE ALL THE 45 MINUTES IS UP TO YOU GUYS.
>> CORRECT. I JUST WANT TO MAKE SURE THAT EVERYBODY HAS AN EQUAL AMOUNT OF TIME ALLOTTED TO BE ABLE TO ASK QUESTIONS IF THEY HAVE THEM.
UNFORTUNATELY, MY LAPTOP IS NOT WORKING TOO GREAT RIGHT NOW, SO I'M GOING TO HAVE IT ON MY PHONE TO BE ABLE TO SEE WHEN COMMISSIONER WRIGHT WANTS TO SPEAK.
PLEASE FORGIVE ME FOR LOOKING UP AND DOWN ON THE PHONE.
>> THE FIRST FIRM WE HAVE TODAY IS THE DI POMPEO CONSTRUCTION CORP, SO YOU GUYS CAN STEP FORWARD AND GET READY TO PRESENT, AND I'LL START THE TIME AS YOU GET STARTED.
>> GOOD MORNING, I HAVE MY ENTIRE TEAM [INAUDIBLE].
I JUST WANT TO MAKE SURE THERE'S NO OTHER PROPOSALS HERE, CORRECT?
>> [INAUDIBLE] IN THE BACK TO THE PEOPLE THAT ARE COMING AFTER US CAN SEE OUR PRESENTATION.
>> IT IS A PUBLIC MEETING, AND TRUTHFULLY IN TERMS OF DISCLOSURE AND THAT THING OPEN AT THIS POINT.
>> THANK YOU SO MUCH FOR THE OPPORTUNITY.
I'M GOING TO GET QUICK TO THE POINT.
EVERYBODY ON THE FIRST SHEET, IF YOU LOOK AT IT AND SEE IF IT'S WORKING. IT'S NOT WORKING.
WE GOT TECHNICAL DIFFICULTIES. STOP THE CLOCK.
>> WE'LL GIVE YOU A COUPLE OF EXTRA SECONDS.
>> GOOD MORNING AGAIN. LIKE I SAID, I'M JOHN DI POMPEO.
WE HAVE THE PRIVILEGE OF BEING HERE FOR PROBABLY THE 10TH TIME IN THE PAST 30 YEARS.
ON THE SLIDE IN FRONT OF YOU AND IN YOUR HANDOUT, YOU CAN SEE THE OVERALL PARK DESIGN, AND ON THE BOTTOM IS ALL THE TEAM MEMBERS THAT WE HAVE SITTING BEHIND US, I SHOULD SAY, AND ARE LISTED ON THIS SHEET RIGHT HERE AS WELL.
AS YOU CAN SEE, OUR DESIGN BUILD TEAM HAS BEEN WORKING TOGETHER SINCE 1999, AND SINCE OUR FIRST DESIGN BILL JOB, WHICH WE DID FOR YOU GUYS IN 2008, WHICH WAS A PUBLIC WORKS FACILITY WHEN LEVENT WAS A YILMAZ IT MANAGER.
WE HAVE EXTENSIVE EXPERIENCE IN PARK AND RECREATIONAL FACILITY, AND WE HAVE A SUCCESSFUL HISTORY OF COMPLETING DESIGN BUILD PROJECTS.
WE'VE BEEN IN BUSINESS SINCE 1927.
WE STARTED IN FLORIDA IN 1992.
THE CHISHOLM FIRM HAS BEEN IN FLORIDA SINCE 1982.
AS YOU CAN SEE, MOST OF ALL THE PERSONNEL, ARCHITECTS, ENGINEERS THAT ARE NAMED ON THAT CHART ARE ALL SITTING BEHIND US, AND WE CAN TALK TO THEM IF YOU WISH LATER.
JUST TO GIVE YOU A LITTLE QUICK HISTORY, THIS SOLICITATION CAME OUT IN FEBRUARY OF 2024, AND IT WAS A TWO STEP PROCESS.
FIRST STEP WAS WHO YOU ARE, HOW GREAT YOU ARE, AND THEN YOU GET SHORTLISTED TO THE SECOND STEP THREE PEOPLE WERE PICKED.
WE WERE ONE OF THE THREE, MBR WAS ANOTHER ONE, AND WAYPOINT WAS ANOTHER ONE.
THERE'S ONLY ONE TEAM THAT SUBMITTED. OUR TEAM.
MBR AND WAYPOINT DID NOT SUBMIT.
IN MARCH OF 2025, WE HAD A MEETING WITH CITY STAFF, AND WE LOWERED OUR PRICE FROM 11,000,797-10,000,677, AS YOU CAN SEE ON THE SLIDE THERE.
BECAUSE WE HAD BASED UPON ALL THE YEARS OF WORKING WITH THE CITY, WE HAD THROW IN A BUNCH OF ENHANCEMENTS THAT WE FELT NECESSARY FOR THIS TYPE OF PROJECT.
HOWEVER, THE CITY SAID, JOHN, TAKE OUT ALL YOUR ENHANCEMENTS, GIVE US WHAT'S ON THE RFP, SO WE DROPPED OUR NUMBER TO 10,000,677.
THE CITY LATER THEN REJECTED OUR BID,
[00:10:03]
PUT IT OUT FOR RE ADVERTISEMENT.HOWEVER, THE NEXT SOLICITATION WAS NOT A TWO-STEP PRE-QUALIFICATION.
IT WAS DESIGNS, WHO YOU ARE, HOW GREAT YOU ARE, AND A PRICE ALL ON ONE PACKAGE.
UNFORTUNATELY, OUR PROPOSAL, OUR DESIGNS, OUR PRICING WAS ON THE STREET.
WHOEVER WANTED TO SUBMIT IT ON THE SECOND TIME, THEY SAW OUR DESIGNS AND THEY SAW OUR NUMBERS.
IT WAS DISENCHANTING FOR US THAT WE SPENT SEVEN MONTHS DESIGNING THIS PERFECT FACILITY ONLY TO HAVE OUR BID THROWN OUT, AND NOW OTHER PEOPLE CAME IN TO SEE OUR DESIGN AND SAW OUR PRICE.
IT IS WHAT IT IS. WELL WE MOVE ON.
ON THIS E MAIL IN MARCH 24, THIS WAS PREDICATED ON A MEETING WHERE WE HAD GIVEN THE CITY $900,000 WORTH OF ALLOWANCES TO DROP OUR NUMBER TO 106, WHICH WAS ORIGINALLY 11, AS I SAID BEFORE.
WE INCLUDED THE MILLION DOLLAR ALLOWANCE THAT THE CITY ASKED US TO INCLUDE BECAUSE AT THE BEGINNING OF THE RFP SOLICITATION, JOHN DOHERTY WANTED TO HAVE SOMEBODY MEANING YOURSELVES, THE CITY STAFF, WE'RE GOING TO DO ALL THE REMOVAL OF THE DIRTY SOIL AND THE ARSENIC AND GET RID OF IT SO THAT WAY A CONTRACTOR CAN START AFTER THAT.
HOWEVER, HE THEN SAID, NOPE, I'M NOT GOING TO DO IT.
I WANT THE CONTRACTORS TO DO IT, SO HE INCLUDED AN ALLOWANCE OF $1,026,000, WHICH EVERYBODY SHOULD HAVE.
AS YOU CAN SEE, IN PREVIOUS TRACK RECORD, THESE ARE FIVE JOBS WE'VE COMPLETED FOR THE CITY, ON TIME, ON BUDGET, AND MOST IMPORTANTLY, MAINLANDS PARK, WHICH WAS A ARSENIC, BAD SOIL, SAME IDENTICAL CONDITIONS OF THIS PROJECT THAT WE CONTENDED WITH ON THAT PROJECT AS WELL.
WE HAVE THE EXPERTISE AND WE KNOW HOW TO HANDLE TYPE OF FACILITIES THAT HAVE ARSENIC AND BAD SOIL CONTAMINATION.
AGAIN, MORE PARKS, RECREATION FACILITIES.
NOT THAT I WANT TO BORE YOU WITH THAT, BUT WE'VE BEEN DOING THIS FOR SO LONG AND OUR SPECIALTY IS MOSTLY CITY COUNTIES. THAT'S ALL WE DO.
I'LL LET MR. CHISHOLM'S RIGHT HAND MAN, MATT POLLOCK SPEAK ON HIS BEHALF. MATT, PLEASE.
>> GOOD MORNING. MY NAME IS MATT POLLOCK, PRESIDENT OF ARCHITECTURE CHISHOLM ARCHITECTS WITH ME IS MR. CHISHOLM AS WELL.
JUST VERY QUICKLY BECAUSE I KNOW WE'RE STRETCHED ON TIME.
WE'VE BEEN DOING WORK DI POMPEO FOR CLOSE TO OVER 25 YEARS, INCLUDING MANY DESIGN BUILD PROJECTS.
SOME OF THOSE SAMPLES ARE INCLUDED IN OUR RELATED EXPERIENCE.
THE FIRST SLIDE IS WORK THAT WE'VE DONE SEPARATE AND APART FROM MR. DI POMPEO, AND THEN OUR NEXT SLIDE ARE PROJECTS.
THE TAMARAC SPORTS COMPLEX, THE TAMARAC COMMUNITY CENTER, THE MALANS PARK ARE PROJECTS THAT WE ACTUALLY DID WITH MR. DI POMPEO, ALONG WITH THE HOMELESS ASSISTANCE CENTER AND A FEW OTHER PROJECTS.
WANT TO JUMP RIGHT INTO THE DESIGN.
WHAT YOU'RE SEEING HERE ARE FOUR AERIAL RENDERINGS OF THE SITE, EACH TAKEN FROM DIFFERENT PERSPECTIVES.
THE TOP LEFT PERSPECTIVE SHOWS THE VIEW LOOKING SOUTH FROM THE NORTHWEST.
WHAT YOU CAN SEE IS WE HAVE OUR ENTRY DRIVE.
OUR DOG PARK, THE DOG PARK IS ARTIFICIAL TURF DOG PARK, WHICH IS AN ENHANCEMENT.
WE ALSO ENLARGE THE SIZE OF THE DOG PARK SO IT COULD BE SEPARATED INTO BOTH LARGE AND SMALL DOGS, AND THEN IT HAS ALL THE REQUIREMENTS OF THE RFQ ARE ON THAT.
THAT'S A VIEW LOOKING SOUTHWEST, AND YOU CAN SEE THE WAY WE SITUATED THE KEY ELEMENTS OF THE FACILITY.
WE HAVE A PAVED PLAZA AREA WITH A WITH THE CONCESSIONS RESTROOM BUILDING, WHICH IS ALSO WE INCORPORATED IN THE MAINTENANCE ROOM AS WELL AS THE SPLASH PAD EQUIPMENT.
IN THAT BUILDING, I'LL TALK ABOUT A LITTLE A FEW MORE MINUTES WE ALSO GAVE A SEPARATE SET OF RESTROOMS THAT HAVE DIRECT ACCESS TO THE SPLASH PAD WITHOUT HAVING TO LEAVE THE FACILITY.
THEN JUST TO THE LEFT OF THAT, WE HAVE THE BASKETBALL COURT, WHICH CAN ALSO BE MODIFIED TO BE A PICKLEBALL COURT WITH TWO PICKLEBALL COURTS, AND THEN DIRECTLY TO THE SOUTH OF THAT IS THE ARTIFICIAL TURF PLAYFIELD.
THE IDEA WAS THAT PEOPLE WOULD ALL GATHER IN THAT AREA, AND THEN IN THE CONCESSIONS BUILDINGS BEING VERY NEARBY AND THAT CONCESSIONS BUILDING WOULD SERVE BOTH THE SPACES OF THE BASKETBALL COURT,
[00:15:01]
THE SOCCER FIELD, AND THEN THE SPLASH PAD HAS A SEPARATE WINDOW, SO YOU CAN PURCHASE AND BUY THINGS WITHOUT HAVING TO LEAVE THE SPLASH PAD AREA.THEN AS YOU CAN SEE, WHERE THE DOG PARK IS JUST TO THE LEFT OF THE DOG PARK IN THE UPPER RIGHT CORNER OF THE RENDERING ON THE LEFT, WE HAVE THE PLAYGROUND AREA.
THEN OUR VIEW ON THE BOTTOM RIGHT CORNER IS ACTUALLY A VIEW LOOKING NORTHEAST WHERE YOU SEE THE EXERCISE PAVILION LOOKING ACROSS THE FIELD THERE.
JUST TO REORIENT, EVERYONE IN THE PLAN HERE, SABAL PALM AVENUE IS TO THE NORTH AND YOU HAVE OUR ENTRY PARKING AREA.
WE TOOK ADVANTAGE OF THE PARKING AREA, WHICH WE'LL USE AS PART OF OUR SOIL MITIGATION, AND THEN WE WENT AHEAD AND PLACED AGAIN, THE DOG PARK TO THE LEFT OF THAT.
THEN, AS YOU CAN SEE, WE HAVE ALL OF OUR SAY, OUR CHILD RELATED ACTIVITIES, YOUR BASKETBALL COURT, YOUR SOCCER FIELD, YOUR SPLASH PAD, AND YOUR PLAYGROUND AREA.
WE LOCATED THE PLAYGROUND AREA ADJACENT TO THE SPLASH PAD THAT ALLOW PARENTS WHO MAY HAVE KIDS THAT MAY BE AT THE PLAYGROUND AND AT THE SPLASH PAD TO GIVE VISUAL CONTACT BETWEEN THE TWO, IF YOU HAVE KIDS DIFFERENT AGES DOING THAT.
THEN WE CREATED A WINDING PATHWAY AROUND THE ENTIRE PARK WITH EXERCISE AREAS AND PAVILIONS TO ENHANCE THE PARK AND THEN WITH THE FITNESS CENTER IN THE UPPER RIGHT CORNER, JUST OFF OF THE PARKING AREA IN A LANDSCAPED AREA.
THEN OBVIOUSLY, WE HAVE THE ARTIFICIAL TURF SOCCER FIELD WITH BLEACHERS ON BOTH SIDES OF THAT FACILITY.
WE ALSO DESIGN THIS SO THAT CENTRAL PLAZA AREA CAN RECEIVE A EMERGENCY VEHICLE, SO YOU HAVE ACCESS TO THE PARK OR AN EMERGENCY VEHICLE TO GET ALL THE WAY TO THE SOCCER FIELD AND INTO THE KEY AREAS, WHICH WOULD BE THE SPLASH PAD AND THE PLAYGROUND AREA AS WELL.
>> WE ALSO INCORPORATED EIGHT FOOT WIDE WALKWAYS AROUND THE ENTIRE WALKING PATH ALONG WITH THE EXERCISE AREAS, AND THEN CREATED THAT CENTRAL PLAZA, WHICH COULD BE USED FOR VENDORS AND FOOD TRUCKS FOR ANY ACTIVITIES YOU HAVE, ESPECIALLY IF YOU'RE HAVING LIKE BIG SOCCER GAMES.
>> I WANT TO MENTION THAT WE PUT IN YELLOW, ALL THE ENHANCED.
FROM PAST WORK, YOU WANT EIGHT-FOOT-WIDE WALKWAYS.
THAT'S THE YELLOW ITEMS THAT WE ALL THE EXPERIENCE WORKING WITH THE PARKS DEPARTMENT, WORKS DEPARTMENT AND, [INAUDIBLE] ETC.
WITH YELLOW ITEMS ARE THE ENHANCEMENT.
>>THIS IS A RENDERING OF THE SPLASH PAD AREA WITH THE CONCESSIONS AND RESTROOM BUILDING.
OUR BUILDING IS LARGER THAN THE DESIGN APPROACH BUILDING.
WE PROVIDED A PLUMBING CHASE THAT'S EASILY ACCESSIBLE FOR MAINTENANCE STAFF.
WE ALSO IN COMBINING THE PULL EQUIPMENT OR THE SPLASH PAD EQUIPMENT AREA IN THAT BUILDING AS WELL, CENTRALIZE THAT EQUIPMENT AND MAKES IT EASY TO BRING CHEMICALS AND SERVICE SERVICE A SPLASH PAD, AND THEN AS YOU CAN SEE, WE HAVE ON THE SPLASH PAD SIDE, THAT WINDOW IN THE RIGHT CORNER OF THE BUILDING IS FOR THE CONCESSIONS AREA, SO YOU CAN BUY CONCESSIONS FROM THE SPLASH PAD AREA.
IF YOU LOOK IN THE LOWER LEFT IMAGE THERE, THAT'S THE OTHER SERVICE WINDOW WHERE ANYBODY WHO'S NOT IN THE SPLASH PAD CAN ALSO PURCHASE CONCESSIONS AS WELL.
THEN THOSE ALL OVERLOOK THE CENTRAL PLAZA AREA THAT WE CREATED.
AGAIN, HERE IS THE LAYOUT OF OUR FLOOR PLAN THERE.
ONE OF THE FEATURES HERE THAT WE INCLUDED WAS TO ADD HIS AND HERS MEN'S AND WOMEN'S RESTROOM ON THE SPLASH PAD SIDE AGAIN, SO THAT YOU CAN ACCESS THE SPLASH PAD ALONG WITH WATER FOUNTAINS, AND THEN ALSO HAVE ADDITIONAL RESTROOMS THAT SERVE THE GENERAL PUBLIC, AND THEN WE HAVE THE STORAGE AND ALL THOSE OTHER ELEMENTS.
AGAIN, THIS IS JUST OUR RENDERING OF THE PLAYGROUND AREA, WHICH IS CATTY-CORNER TO THE SPLASH PAD.
IT'S COVERED, WHICH IS FOR THE REQUIREMENTS.
AGAIN, OUR PICKLEBALL COURTS JUST A LITTLE BIT ENHANCED RENDERING OF THAT.
THE DOG PARK AREA, WHICH I MENTIONED, WE SUBSTITUTED NATURAL GRASS WITH ARTIFICIAL TURF, WHICH WE THINK HOLDS UP BETTER FOR EVERYONE.
[00:20:02]
THEN THIS IS THE SPLASH PAD AREA BEING PROVIDED BY VORTEX.THE EXERCISE PAVILION THAT'S SEPARATE AND APART FROM THE PARK ALLOWS SOME PRIVACY FOR PEOPLE TO DO EXERCISES, BUT YET STILL CLOSE TO THE PARKING AREA AND HAS A LOT OF VISUAL CONTACT WITH THE REST OF THE PARK.
THE ARTIFICIAL TURF FIELD, AND WE LOCATED IT IN THE SOUTHEAST CORNER OF IT TO TAKE ADVANTAGE OF THE EXISTING GRADES AND ALSO TO ASSIST IN THE REMEDIATION OF THE SOILS.
>> THE LEAST AMOUNT OF ARSENIC EXIST.
THEN IMPUT THE FIELD WHERE THE MOST OF ARSENIC EXIST.
>> THEN I'M GOING TO LET JOHN TAKE OVER.
>> I'M NOT SURE THE MINUTE. AS FAR AS CIVIL ENGINEERING, LIKE I SAID, WE LOCATED THE FIELD IN THE LOCATION WHERE WE FELT WAS BEST TO REMOVE THE LEAST AMOUNT OF DIRT THAT IS BAD.
THE DOLLAR AMOUNT IN THE ALLOWANCE THAT WAS GIVEN TO US BY YOU GUYS IN THE CITY, WE HOPE AND WE THINK WE'RE GOING TO BE ABLE TO CUT THAT NUMBER IN HALF.
THAT'S THE GOOD NEWS. I'M NOT GOING TO TELL YOU RIGHT NOW, BUT THAT'S THE WAY WE DO IT WHEN WE SIT DOWN WITH YOUR STAFF.
WE'RE GOING TO COME UP WITH A LOWER NUMBER THAN THAT MILLION-DOLLAR ALLOWANCE.
AGAIN, THE DRAINAGE AND THE DIRT HAVE TO WORK HAND IN HAND BECAUSE YOU HAVE TO WORK WITH THE COUNTY.
DAVID VANDER LEDINGHAM IS THE GUY AT ENVIRONMENTAL PLANNING WHO WE'VE DEALT WITH BEFORE, ON MAINLANDS PARK AND OTHER ARSENIC FACILITIES.
WE HAVE A DEDICATED IRRIGATION PUMP AIRED FIRE HYDRANT, WHICH NO OTHER PROPOSERS HAVE.
WE'VE LOOKED AT ALL THE OTHER PROPOSALS THAT WE DID OUR DUE DILIGENCE AND RESEARCHED AS WELL.
REMEDIATION SES ENGINEERS UTX IS HERE WITH US.
HE'S BEEN DOING DIRT REMEDIATION, SO HE KNOWS THE STUFF.
AGAIN, IT'S NOT JUST US AND THE CITY.
WE HAVE TEAMS THAT WE HAVE TO DEAL WITH.
WE HAVE TO DEAL WITH THE CITY INSPECTORS, WE HAVE TO DEAL WITH DRC, THE BUILDING DEPARTMENT, ID DEPARTMENT, MR. TWIGER, BEHIND ME, PARKS DEPARTMENT, ENGINEERING, AND ALL THESE OTHER AGENCIES THAT WE HAVE TO GO THROUGH THAT WE'VE DONE SO MANY TIMES.
AGAIN DR. [INAUDIBLE], COST CONTROL SCHEDULING.
WE HAVE ALL THESE PROGRAMS THAT WE KEEP TRACK OF THE JOB.
WE ALWAYS FINISH ON TIME AND IN BUDGET.
JUST MORE DESIGN-BUILD PROJECTS, CITY PROJECTS WE'VE DONE RECENTLY FOR YOU GUYS, AND YOU CAN SEE ALL ON TIME, AHEAD OF SCHEDULE.
>> YOU HAVE TO HAVE FOUR MINUTE, AND I GIVE YOU [OVERLAPPING].
>> THANK YOU. PER THE RFP, IT SAYS THAT WE'RE SUPPOSED TO BE DONE IN 640 DAYS.
WE FEEL WE CAN BEAT THAT, BUT WE DID WHAT WAS IN THE RFP, BUT THE KEY IS THE PERMITTING.
THE PERMITTING COULD TAKE THREE MONTHS TO SIX MONTHS TO NINE MONTHS.
THAT'S THE VARIABLE, BUT WE WANT TO GIVE YOU WORST-CASE SCENARIO, AND THEN WE LOOK LIKE HEROES WHEN WE BEAT THE SCHEDULE.
OUR SCHEDULE IS BASED UPON THESE ITEMS, WHICH OBVIOUSLY THE BIG VARIABLE IS THE CONTAMINATED FILL.
AS I SAID IN THE BEGINNING, OUR PRICE RIGHT NOW IS 10,677,000, WHICH IRONICALLY, IF YOU LOOK AT THE SECOND BIDDER, IS RIGHT NEAR OUR NUMBER.
IT WAS PUBLIC RECORD, SO HE SAW OUR NUMBER.
TO HELP IN YOUR EVALUATION, WE MEET SPEC ON ALL THE LOW-VOLTAGE ITEMS. MOST SELLER PEOPLE'S PRICING.
ONE PERSON HAS A 199,000, WHICH THE TWO GENTLEMEN TO MY LEFT AND BEHIND ME KNOW, A $199,000 IS NOT GOING TO COVER THE AMOUNT OF IT EQUIPMENT NEEDED FOR THIS PROJECT.
THE FIRE STATION THAT WAS BUILT NEAR A PICCADILLY RESTAURANT, THAT WAS BY ANOTHER COMPETITOR, IT WAS $800,000 LESS THAN OURS BECAUSE HE LEFT OUT ALL THE IT.
THAT JOB WAS THREE YEARS LATE.
OUR ELECTRIC NUMBER IS DOUBLE AS WELL BECAUSE MUSCO IS YOUR SPECIFIED PRODUCT.
THEIR PRODUCT ALONE IS HALF OF THE BUDGET.
YOU JUST NEED TO LOOK AT SOME OF THESE GUYS' PROPOSALS.
YOU CAN'T PUT 10 POUNDS INTO A FIVE-POUND BUCKET.
THE TWO BIDDERS HAVE DESIGN FEES.
THE DESIGN FEES, FYI FOR FUTURE REFERENCE SHOULD BE 7-10% OF A PROJECT'S BUDGET.
TAKE THE NUMBER OF EVERYBODY'S BID AND JUST USE 10%.
YOU CAN'T DO TWO HUNDRED AND FIFTY THOUSAND DOLLARS FOR DESIGN AND ALL THE ENGINEERS.
TWO GENERAL CONTRACTORS LISTED THEY BUILT AND WERE NOT AWARDED EVEN THESE JOBS THAT THEY HAD EMPLOYEES THAT WORKED THERE, BUT THEY'RE TAKING CREDIT FOR THEIR EMPLOYEES THAT NOW WORK FOR THAT COMPANY, BUT THEY NEVER BUILT THOSE PROJECTS.
YOU NEED TO LOOK AT THOSE THINGS.
I'VE BEEN DOING THIS FOR A LONG TIME.
THE LITTLE BIDDER DOESN'T EVEN HAVE THE DOG PARK REQUIREMENTS.
THE SECOND LITTLE BIDDER DOESN'T HAVE ARTIFICIAL GRASS IN THE DOG PARK OR VEHICULAR ACCESS FOR THE FIRE TRUCKS.
THE HIGHEST BIDDER DOESN'T SHOW ANY LANDSCAPING IRRIGATION IN HIS BID, THAT'S FIVE HUNDRED THOUSAND DOLLARS.
THE LARGER CONCESSION BUILDING THESE ARE THE ADDED VALUES I WANTED TO TELL YOU ABOUT THAT WERE HIGHLIGHTED.
I JUST WANT TO GIVE YOU A LITTLE QUICK, REHEARSAL OF THE SAME ITEMS.
[00:25:02]
BIGGER RESTROOMS, BURGER ALARM SYSTEM, WHICH ISN'T IN THE RFP.WE INCLUDED THE PLUMBING CHASE THAT YOU GUYS LOVE TO HAVE BECAUSE IT'S EASY FOR MAINTENANCE, A LARGER DOG PARK, A BIGGER SPLASH PAD, MORE FITNESS STATIONS, VEHICULAR ACCESS, EIGHT FOOT WALKS, BIGGER GATHERING AREAS, SO YOU CAN HAVE FOOD TRUCKS COME OUT THERE ON THE WEEKENDS FOR GATHERING, GATE CONTROLLERS, MORE BLEACHERS, FIRE HYDRANTS, EVERYTHING THAT YOU SEE ON OUR PRICE IS MORE THAN OTHER PEOPLES BELOW US BECAUSE WE INCLUDED THINGS WE KNOW YOU'RE GOING TO WANT.
WE DESIGNED AND BUILD OTHER GOLF COURSES WITH SOLAR MEDIATION MITIGATION PROBLEMS, AS I SAID.
JOHN DOHERTY SAID WHEN WE HAD THE PRE-BID FOR THIS JOB, HE WANTED TO HAVE A PARTNER, SOMEBODY THAT KNEW WE HAD A PROBLEM WITH THIS PROJECT, WE NEED TO WORK TOGETHER, AND THAT'S WHY WE CAME TO THE TABLE TO HELP YOU GUYS.
THE WEIRD THING ABOUT THIS JOB, WHICH IN EVERY 35 YEARS IN MY EXISTENCE OF DOING GOVERNMENT WORK, THERE WAS NO BID BOND.
WHEN YOU SUBMIT A PROPOSAL TO THE MUNICIPALITY, YOU HAVE TO GIVE A BID BOND.
THAT WAY YOU CAN'T BACK OUT IF YOU GAVE A BAD NUMBER.
YOU MIGHT WANT TO ASK SOME OF THE BIDDERS, ARE YOU GOING TO DO YOUR JOB FOR THAT SMALL AMOUNT OF PRICE BECAUSE YOU'RE TWO MILLION DOLLARS LESS THAN EVERYBODY ELSE? WHEN YOU PUT A BID BOND ON THE TABLE, YOU PUT YOUR MONEY WHERE YOUR MOUTH IS, SO TO SPEAK.
WE HAVE THE 13 D FIRE SYSTEM, THAT'S NOT AN RFP, BUT WE KNOW YOU WANT IT BECAUSE WE BUILT OTHER FACILITIES FOR YOU.
FIFTEEN YEARS AGO, ONE PROPOSAL HAD AN ISSUE WITH THE CITY STAFF, HASN'T BID TO CITY OF TAMARAC WORK FOR A REASON.
NOW ALL OF A SUDDEN, HE'S BACK. HE'S BIDDING ON THIS PROPOSAL.
>> HEY, JOHN. SORRY TO CUT YOU OFF.
I'M GOING TO GIVE YOU AN EXTRA MINUTE, BUT JUST SOMETHING TO POINT OUT.
ALL TYPES OF BONDS WERE REQUIRED FOR THIS PROJECT.
RECORDS BECOME SUBJECT TO PUBLIC RELEASE.
IF YOU DON'T WANT IT TO BE SUBJECT TO PUBLIC RELEASE, SUBMITTED AS PROPRIETARY OR CONFIDENTIAL, AND ONCE AGAIN, YOU'RE DOWN TO YOUR LAST MINUTE.
>> FROM PAST HISTORY, THIS PROJECT THAT THE CITY HAS ALWAYS DONE HAS BEEN TWO STEP PROCESS, NOW THIS IS A ONE-STEP PROCESS.
USUALLY, YOU THROW OUT THE HIGH, YOU THROW OUT THE LOW, AND YOU TAKE THE AVERAGE OF THE MIDDLE.
WHEN YOU DO THAT TYPE OF PHILOSOPHY, YOU'RE BACK AT OUR NUMBER.
ALSO, THE DESIGNS AND MATERIALS WE KNOW THE IN CITY WANTS IS WHAT WE HAVE INCLUDED.
OTHER PEOPLE DON'T HAVE THESE THINGS IN THEIR PROPOSAL.
THE OLD SAYING GOES, YOU GET WHAT YOU PAID FOR.
IN SUMMARY, CITY OF TAMARAC IS IN THE PAST, IS OUR SOLE FOCUS.
I'M GOING TO BE YOUR NUMBER ONE GUY.
EVERYBODY BEHIND ME THAT HAS BEEN WORKING ON ALL OF YOUR PROJECTS FOR THE PAST 25 YEARS ARE GOING TO BE HERE AGAIN.
ALL THE PROJECTS ON TIME HAVE DESIGN-BUILD EXPERIENCE, WE KNOW THE PERMANENT REQUIREMENTS.
WE KNOW THE QUALITY CONTROL IT'S EXPECTED.
WE KNOW EVERYBODY IN THE CITY, THE INSPECTORS, THE BUILDING DEPARTMENT, ETC.
WE SELF-PERFORM A LOT OF WORK.
THAT MEANS WE CAN BEAT THE SCHEDULE AS WELL AS YOUR BUDGET.
WE'RE GOING TO IMPROVE ON THAT.
THE BIGGEST IMPORTANT THING, NO CHANGE ORDERS.
UNLESS YOU WANT TO CHANGE SOMETHING, THERE WILL BE NO CHANGES ON THIS PROJECT.
WE KNOW THAT WE CAN BEAT YOUR NUMBER IF YOU SIT DOWN WITH US. THANK SO MUCH.
>> PERFECT. YOU'RE OUT OF TIME. JUST SOMETHING I WANT TO CONFIRM.
A NUMBER I KEPT SEEING WAS 10,677,000, BUT YOUR PRICE IS ACTUALLY, AND MAYBE YOU EXCLUDED THE REMEDIATION MILLION, BUT IT'S 11,677,000?
>> CORRECT. THAT'S INCLUDING THE ENHANCEMENTS.
NOW, IF YOU TAKE THE ENHANCEMENT OUT, YOU'RE BACK DOWN ON A NUMBER OF 106.
BUT AS I SAID, WHEN WE ALL DID ALL THESE PROJECTS FOR THE CITY BEFORE, WE GIVE YOU BEST CASE SCENARIO, AND THEN WE WHITTLED IT DOWN TO WHAT YOU REALLY WANT.
OUR ELEVEN MILLION NUMBER HAS EVERYTHING MORE THAN WHAT'S IN THE RFP.
IF YOU WANT TO JUST GO BARE BONES MINIMUM OR AT THE TEN NUMBER.
>> PERFECT. THANK YOU. WE'RE GOING TO OPEN IT UP FOR THE COMMISSION.
VICE MAYOR? COMMISSIONER PATTERSON? COMMISSIONER WRIGHT?
>> I'M GOOD. NOTHING ON MY END.
>> WELL, I DO. THANK YOU FOR YOUR PRESENTATION, AND APPRECIATE THE INFORMATION.
I'M GOING TO ASK FIRST ABOUT THE PICKLEBALL VERSUS BASKETBALL AS A GENERAL COMMENT, AND EVERYBODY'S GOING TO HEAR THIS.
HOW FAR AWAY IS THIS PROPOSED BASKETBALL/PICKLEBALL? IF IT'S IN PICKLEBALL FOR NOW.
>> YOU WANT TO ANSWER MS. GOMEZ'S QUESTION, PLEASE?
>> I'M A LITTLE CONFUSED ON THE QUESTION.
>> LET ME PHRASE. HOW FAR AWAY FROM HOLMES IS THAT PICKLEBALL IF IT'S A PICKLEBALL?
>> ACTUALLY, A GOOD QUESTION, MICHELLE. THERE IS NO PICKLEBALL.
>> BUT YOU MENTIONED PICKLEBALL,
[00:30:02]
WHICH IS WHAT MY CONCERN.>> THE THING IS CAN IT? BECAUSE MANY COMMUNITIES THAT ARE PUTTING IN PICKLEBALL COURTS RIGHT NOW ARE GETTING SUED FOR THE HIGH SOUND OF THE PERCUSSION OF THE PADDLES AND THE QUICK PA PA PA.
I HAVE NOTHING AGAINST PICKLEBALL, BUT IT IS RECOMMENDED A THOUSAND FEET AWAY FROM A HOME, AND DEFINITELY NO LESS THAN FIVE HUNDRED.
LOOKING AT THE COMMUNITY SHOWS THAT THERE'S ONLY THREE HUNDRED FEET FROM THIS PARK TO A HOUSE. ONE OF THE CLOSEST HOUSE.
I CAN GIVE YOU A STREET OR AN ADDRESS IF YOU WANT.
BUT I PUT THAT OUT THERE FOR THE COMMUNITY.
I DON'T REMEMBER EVER HEARING FROM THE COMMUNITY THAT I WANTED PICKLEBALL IN ALL THE MEETINGS I WENT TO.
I DON'T KNOW IF THERE WAS A MEETING THAT WAS HAD THAT I WASN'T PRIVY TO, BUT I'VE NEVER HEARD THAT THIS COMMUNITY WANTED PICKLEBALL.
AGAIN, I'M NOT AGAINST PICKLEBALL.
I AM ONLY IF WE'RE GOING TO MAKE IT A SOUNDPROOF AREA, WHICH YOU REALLY CAN'T DO, FORCING THEM TO PLAY WITH A SOFT PADDLE.
PICKLEBALLERS WHO ARE PICKLEBALLERS AT HEART DO NOT LIKE THAT SOFT PADDLE.
THE GOOD NEWS IS IN THE PAST RECORD WHEN WE SIT WITH YOUR STAFF.
IF WE WANT TO CHANGE THAT BASKETBALL INTO A PICKLEBALL, NOT THAT YOU WANT TO, BUT IN CASE, THIS IS WHAT WE DO.
WE CAN MOVE THE BASKETBALL OVER TO THIS CORNER OVER NEAR THE TURNPIKE, WHICH IS EVEN FURTHER AWAY FROM THE RESIDENTIAL COMMUNITY, WHICH IS ON THE NORTH AND THE WEST SIDE.
>> UNDERSTOOD, BUT STILL MEASURE OUT MY CONCERN.
>> [OVERLAPPING] HOW YOU'RE GOING TO DO IT. THAT'S THE FURTHEST YOU'RE EVER GOING TO.
>> IT DOESN'T MATTER IF YOU'RE THE FURTHEST.
IF YOU'RE THE FURTHEST AND YOU'RE STILL THREE HUNDRED FEET AWAY FROM THAT HOME, CITY'S GETTING SUED, YOU'RE GETTING SUED, WE'RE ALL GETTING SUED, AND THE RESIDENTS ARE GOING TO BE HAPPY THEY'RE GOING TO MOVE OUT.
THAT'S A CONCERN BECAUSE THESE LAWSUITS ARE POPPING UP ALL OVER.
>> RESIDENT AND THAT'S RIGHT THERE AT THE UPPER CORNER.
THE REST OF IT IS A RETENTION AREA.
THE OTHER SIDE TO THE RIGHT OF THE PROPERTY OR TO THE NORTH IS LIFT STATION, AND THERE'S NO RESIDENTIAL.
I'M LOOKING AT THIS, SOUTH SIDE IS THE TURNPIKE, WATER, RESIDENCE ON THE LEFT.
>> MORE TUNPIKES ON THE BOTTOM.
>> NO RESIDENTS ON THE RIGHT SIDE.
>> IT'S PART OF THE TURNPIKE ENTRANCE THAT DOES A TURNAROUND AND A LIFT STATION.
RESIDENTS ARE WAY ON THE OTHER SIDE OF THAT.
THEN ACROSS THE STREET IS A BIG ROUTINEAGE AREA BEFORE IT EVEN GETS TO THE RESIDENTS, WHICH ONLY BACK UP TO THAT LARGE ROUTINEAGE AREA.
THERE'S ONLY ONE SET OF RESIDENTS THAT'S TO THE LEFT BEHIND THE-
>> I'M JUST SHARING MY RESEARCH AND LETTING YOU KNOW THAT THERE IS A HOME LESS THAN THREE HUNDRED FEET OF THIS PARK, AND I HAVE BIG CONCERNS ABOUT THAT IN GENERAL.
YOU CAN USE IT FOR EVER YOU WANT.
IF YOU DON'T WANT TO PICK IT, YOU DON'T HAVE.
>> BUT IF WE SAY WE'RE GOING TO DO SOMETHING, THEN ALL OF A SUDDEN, YOU HAVE TO DO SOMETHING, AND THEN YOU'RE NOT THEN FOLLOWING WHAT WE'VE ASKED FOR.
I AM TRYING TO MAKE SURE THAT WE BE CAREFUL FOR WHAT WE ASK FOR.
I DON'T KNOW IF THIS COMMUNITY ASKED FOR IT, BECAUSE AS I SAID, THE MEETINGS I'VE BEEN IN PART OF, NO ONE'S ASKED FOR A PICKLEBALL COURT. BASKETBALL IS DIFFERENT.
>> WE HAVE IT ABOUT THE OPPORTUNE POSITION RIGHT NOW.
IT'S ABOUT 300 OR 400 FEET AWAY FROM THE RESIDENT.
THE ONLY THING WE COULD SHIFT IT DOWN, ONLY THE SIZE OF THE COURT, WHICH IS ABOUT ANOTHER 150-200 FEET TO THE NORTH.
THAT'S ABOUT THE EXTENT OF YOUR PROPERTY.
>> I THINK WHAT WE WOULD DO IS WE WOULD DO A RADIUS, SET THE SET THE BASKETBALL PICKLEBALL COURT ON THE PLAN, DO A RADIUS, SEE IF WHERE 300 FEET IS, 500 FEET IS, A 1,000 FEET IS, IDENTIFY IF THERE'S ANY RESIDENCE IN THE WAY OF THAT, AND THEN WE CAN LOOK WHETHER WE WANT TO RELOCATE THE PICKLEBALL COURT AND BASKETBALL COURT OR JUST TO RELOCATE THE POTENTIAL PICKLEBALL EITHER.
BUT THAT'S LIKE JOHN SAID, THERE'S OPPORTUNITIES TO DO THAT EITHER BEHIND TO THE WEST OF THE SOCCER FIELD OR PERHAPS EVEN MOVING IT FOR A LITTLE BIT FURTHER EAST.
BUT WE CAN PUT IT PRETTY MUCH WHERE EVERYONE WANTS.
>> YOU GOT FOUR OPPORTUNITIES FOR FREE.
>> WE'RE ALMOST A TIME THERE, MAYOR.
>> WELL, AT THE SAME TOKEN, EVERYBODY SAID THEY DIDN'T WANT TO GO.
NOW THAT I'M SPEAKING, PEOPLE WANT TO GO, IT MAKES IT A LITTLE BIT HARD FOR YOU TO TAKE TIME.
FINE, BUT I'M GOING TO ASK THIS QUESTION.
[00:35:02]
THE DOG PARK, EVERYBODY KNOWS I'M A BIG PET PERSON.VERY EXCITED WITH HAVING THE DOG PARK, HAVING IT SPLIT INTO TWO, FINE.
IS THERE A WATER FEATURE FOR THE PUPS IN THE DOG PARK AREA?
>> YES. WE HAVE THE WATER FOUNTAINS FOR BOTH THE DOG WATER STATION.
WE ALSO HAVE A DOG WASHING STATION.
>> MADAM MAYOR, IF I MAY PLEASE PROCEED WITH THE QUESTIONS, BUT THESE ARE PART OF THE ELEMENTS OR THE CONVERSATIONS THAT TO BE HAD WITH THE SUCCESSFUL PROVIDER AT THE TIME OF THE DESIGN PROCESS.
WHAT YOU SEE HERE ARE COMPLETELY CONCEPTUAL.
THESE ARE RECOMMENDATIONS OF THE CONTRACTOR, DEVELOPER TO SATISFY THE RP REQUIREMENTS.
BUT THE LOCATIONS, THE AMENITIES ARE COMPLETELY CONCEPTUAL AT THIS POINT, AND THIS IS NOT THE PLACE FOR US TO [OVERLAPPING].
>> WELL THEN, IF WE WIND UP PICKING SOMEBODY AND THEN THEY CAN'T MOVE IT TO SOMETHING WE WANT.
THIS IS DESIGN-BUILD PROJECTS.
WE SAID WE WANT TO PARK WITH THESE ELEMENTS.
THEY RESPONDED WITH A DESIGN, BUT THERE'S GOING TO BE A NEGOTIATION PROCESS THAT'S GOING TO REALLY FINALIZE OR REVISE WHAT THEY PROPOSE.
HERE'S A PART. HERE'S THE THINGS YOU ASKED FOR, BUT THERE'S GOING TO BE SOME INTERACTION AND NEGOTIATIONS TO TWEAK THINGS, MOVE THINGS AROUND, MAKE SOME ADJUSTMENTS, AND THAT WILL DICTATE THE FINAL OUTCOME.
>> UNDERSTOOD, BUT THEY WON'T INCLUDE US.
>> BEFORE THE PERMITTING THERE WILL BE A CONCLUDED DESIGN PROCESS AND THEN THEY CAN COME BACK TO COMMISSION.
>> BUT WHEN YOU FINISH PERMITTING, THEN YOU'VE WASTED MULTIPLE TIMES.
>> NOT FINISHED PERMITTING BEFORE PERMITTING.
IT SEEMS LIKE AN INEFFICIENT USE OF A PROCESS.
IF YOU ASK US HERE TO MAKE SOME DECISIONS AND MAKE INQUIRY, THEN WE SHOULD BE ALLOWED TO MAKE THESE INQUIRIES.
IF THEY ARE ACCEPTED, ANYONE IS ACCEPTED, THEY KNOW THAT THERE MIGHT BE THESE THINGS THAT THEY WOULD HAVE TO ADJUST THEIR PLAN FOR.
WHY ELSE HAVE US HERE TO DISCUSS THIS?
>> THE PURPOSE OF THIS MEETING IS FOR YOU TO PROVIDE SOME FEEDBACK AND PUT IN THE QUALITY AND FITNESS OF THESE PROPOSALS, BECAUSE AS PART OF THE DESIGN BILL PROCESS, THAT STEP IS A LITTLE FURTHER DOWN THE ROAD AND SO NOT TODAY.
>> BUT WE ARE NOT IN PART OF THAT DESIGN-BUILD PROCESS UNLESS WE'RE GOING TO CHANGE OUR PROCESS YET AGAIN AND PUT US IN IT.
>> I THINK YOUR INPUT THAT YOU'RE PROVIDING TODAY IS BEING CAPTURED AND SO AS WE NEGOTIATE A CONTRACT, I THINK THESE SOME ELEMENTS OR THE INPUT WILL BE TAKEN INTO ACCOUNT FOR THE FINAL DESIGN.
I THINK THAT FINAL DESIGN CAN COME BACK TO THE COMMISSION BEFORE IT PROCEEDS TO MOVE FORWARD.
>> PART OF THE REASON I'M SAYING THIS IS THAT THE DIPOMPEO MAY NOT BE THE SUCCESSFUL BIDDER.
>> I AM GOING TO ASK FOR ALL THIS BIDDER.
>> I KNOW, BUT FOR THE SAKE OF TIME AND PURPOSE OF THIS MEETING, I THINK IT'S BEST FOR US TO LEAVE THAT TO THE FURTHER STEPS OF THE CONVERSATION.
>> I MEAN, IF I MAY JUST GIVE YOU [OVERLAPPING].
ALL THE DESIGN BILLS WE'VE DONE FOR YOU GUYS.
IF YOU GUYS AFTER THIS MEETING AT THE NEXT COMMISSION MEETING, YOU COME UP WITH OTHER IDEAS, WE WILL MAKE THE CHANGES NO CHARGE.
JUST LIKE WE MOVED THE PUBLIC WORKS FACILITY, IT WAS ON NOB HILL.
NOW IT'S 500 FEET OFF OF NOB HILL.
WE'VE CHANGED ALL OUR DESIGNS FROM OUR INITIAL PRESENTATION BASED UPON YOUR GUYS' INPUT, STAFF'S INPUT, COMMISSION'S INPUT, AND NO CHARGE.
THERE'S NO EXTRA CHARGE IF YOU WANT TO MOVE PHASE AROUND, DELETE THINGS, ADD THINGS, THAT'S PART OF OUR FEE.
>> I STILL HAVE NOBODY. COMMISSIONER PATTERSON.
>> THANK YOU, MAYOR. I JUST HAVE ONE QUICK QUESTION.
CAN YOU CLARIFY THE ENHANCEMENTS THAT YOU SPOKE TO BECAUSE I'M LOOKING AT THE COST SHEET.
YOU MENTIONED OR I UNDERSTOOD THAT THERE IS $1 MILLION DIFFERENTIAL.
I SEE IT AT 500,000, BUT WHAT ACCOUNTS FOR THE ADDITIONAL 500?
>> IT IS NOT NECESSARILY AN ENHANCEMENT.
IT WAS MORE OR LESS THEY POINT OUT SOMETHING THAT YOU MIGHT WANT TO BE KNOWLEDGEABLE OF.
WHEN YOU LOOK AT THE OTHER PROPOSALS LIKE WE DID, YOU CAN'T DO THE AMOUNT OF IT THAT MR. TWIGGER AND LEVENT WANT FOR THE AMOUNT OF MONEY THAT THE GUYS HAVE IN THEIR PROPOSAL.
OTHER PEOPLE HAVE $100,000 AND $200,000.
AS FAR AS THE ENHANCEMENTS, WE MADE THE BUILDING BIGGER, WE PUT ARTIFICIAL TURF, WE MADE EIGHT-FOOT SIDEWALKS, WHICH WERE NOT IN THE RFP.
ALL OF THOSE EXTRA ENHANCEMENTS THAT WE'VE LEARNED THROUGH THE LAST 25 YEARS OF WORKING FOR THE CITY,
[00:40:02]
WE'VE INCLUDED ALL THAT, EVEN THOUGH IT WAS NOT IN THE RFP.>> UNDERSTOOD. I GUESS MY DIRECT QUESTION IS, YOUR PROJECT CAME IN AT 116?
>> ARE WE SAYING THAT THE ENHANCEMENTS FOR THE ADDITIONAL MILLION DOLLAR ARE SPECIFIC TO IT?
>> IT'S LIKE I WAS SAYING, IT'S A BUNCH OF ITEMS. LIKE ALL THESE YELLOW ITEMS, WE'VE TRIED TO DELINEATE THOSE FOR YOU.
>> CAN YOU SPECIFY? CAN YOU GIVE ME SOME CLEAR SPECIFICS ON THAT MILLION [OVERLAPPING]
>> I'LL GIVE YOU A ONE BIG NUMBER, FOR EXAMPLE, THE WALKS.
THE RFP DOES NOT REQUIRE EIGHT-FOOT WALKS, THAT WE KNOW YOUR EMERGENCY VEHICLES AND YOUR PUBLIC WORKS VEHICLES AND YOUR PARKS WRECK VEHICLES, THEY WANT TO DRIVE ON THE PARK.
THAT'S $150,000 THAT WE'VE INCLUDED IN OUR NUMBER.
IF I MAY, GO BACK TO THE FIRST E-MAIL WE HAD FROM OUR MEETING.
WE HAD GIVEN YOU A LIST OF ITEMS AS IT SHOWS THERE, 10,000,006, BECAUSE THEY HAD SAID TO US, JOHN, TAKE OUT ALL OF THE GINGERBREAD AND THE ENHANCEMENTS, IF YOU WILL.
EVEN THOUGH WE KNOW YOU'RE GOING TO WANT IT, BASED UPON OUR EXPERIENCE WITH YOU GUYS, WE TOOK IT OUT AND WE'RE AT A 10 6 NUMBER.
TO MEET RFP BARE BONES [OVERLAPPING]
>> YOU GUYS HAVE NEVER HAD ANY EXPERIENCE WITH ME.
I DON'T KNOW WHAT EXPERIENCE YOU GUYS HAVE HAD IN THE PAST WITH THE [OVERLAPPING].
>> LIKE THE PUBLIC WORKS, THE PARKS DEPARTMENT, OTHER STAFF LIKE THAT.
>> SURE. I THINK THAT'S WHY WE'RE HERE BECAUSE WE'VE GOT NEW STAFF. WE'VE GOT NEW COMMISION.
>> I THINK IT'S IMPORTANT TO BE ABLE TO SPEAK TO WHERE THE CITY IS TODAY AND THAT'S WHY I'M TRYING TO GAIN SOME CLARITY BECAUSE PERHAPS WHERE WE WERE THEN IS NOT WHERE WE ARE NOW.
BUT I APPRECIATE YOUR RESPONSE [OVERLAPPING].
>> THERE'S ANOTHER ONE IF MAY COMMISSIONERS, THAT WORKING WITH YOUR CITY STAFF, IE, PARKS DEPARTMENT, YOU ONLY HAVE A CERTAIN TYPE OF IRRIGATION HEADS.
WE HAVE THOSE IRRIGATION HEADS.
THE OTHER VENDORS HAVE PICKED A CHEAPER IRRIGATION HEAD BECAUSE YOU STOCK CERTAIN MATERIALS WHEN YOU MAINTAIN YOUR FACILITIES, IE, PLUMBING CHASES.
THEY WANT TO HAVE DEDICATED PLUMBING CHASES IN THEIR BUILDING BECAUSE OVER THE YEARS, THEY KNOW THEY'RE GOING TO HAVE PROBLEMS. WE PUT AN EXTRA THREE-FOOT PLUMBING CHASE, WHICH IS NOT IN THE RFP, BUT WE KNEW FROM PUBLIC WORKS THAT THEY WANT THAT.
THOSE LITTLE ENHANCEMENTS FROM ALL THESE YEARS OF WORKING WITH ALL THE DEPARTMENTS, NOT NECESSARILY THAT COMMISSION OR THIS COMMISSION, BUT YOUR STAFF IN THE CITY IN GENERAL.
>> ANY OTHER COMMENTS OR QUESTIONS? THANK YOU VERY MUCH.
>> I THINK THEY HAVE TO COME AND GET SET UP HERE.
>> DO WE WANT TO BE IN A FIVE-MINUTE RECESS WHILE THEY DO?
>> WE CAN WHILE THEY GET SET UP.
>> THIS WAY, NOT EVERYTHING'S BEING TAPED.
I'M GOING TO JUST SAY IT'S 11:46.
WE'RE GOING INTO A FOUR-MINUTE RECESS.
WE'LL BE BACK ONLINE AT 11:50. THANK YOU.
[00:48:02]
NOW WE GET BACK ON THE RECORD, FOR THE CLERK HAS TO SIT.THANK YOU, EVERYONE. WE ARE NOW BACK.
IT IS 11:50, AND WE ARE GOING TO PROCEED WITH OUR SECOND PRESENTATION. MR. STEWART.
>> YES. THANK YOU GUYS AND WELCOME.
AS DISCLOSED IN THE LETTER YOU RECEIVED, YOU'RE GOING TO HAVE 20 MINUTES TO PRESENT YOUR PROPOSAL, AFTER WHICH THE COMMISSION MAY HAVE SOME QUESTIONS FOR YOU, AND THEN WE'LL WRAP UP.
THAT WILL BEING SAID. GO AHEAD AND START.
>> GOOD MORNING, EVERYONE. THANK YOU FOR GIVING US THIS OPPORTUNITY TO COME IN HERE AND PRESENT TO YOU GUYS THE PROJECT FOR SABAL PARK.
WE'RE VERY EXCITED TO BE HERE.
I WANT TO START OFF BY INTRODUCING THE PROJECT TEAM.
WE HAVE WAYPOINT CONTRACTING AS A DESIGN BUILDER, AND WE'RE GOING TO GET INTO TEACH FIRM AND THEIR RESPECTIVE PLAYERS IN THIS PROGRAM.
MEC IS GOING TO BE DOING THE ENVIRONMENTAL CONSULTANT.
SALZ MICHELSON IS GOING TO BE THE ARCHITECT OF RECORD.
MILLER LEGG IS GOING TO BE DOING THE CIVIL AND LANDSCAPE ARCHITECTURE, AND WE'RE GOING TO HAVE AQUATIC DESIGN & ENGINEERING AND VORTEX DOING THE AQUATIC STRUCTURE.
WAYPOINT CONTRACTING. TO THE LEFT, YOU HAVE THE MEMBERS OF THE TEAM THAT ARE GOING TO BE INVOLVED IN THIS PROJECT, MYSELF AS A PROJECT EXECUTIVE, LIMREAL BLANK FOR PRE-CONSTRUCTION, AND YOUR YASID AND CESAR ARE GOING TO BE DOING PROJECT MANAGEMENT AND FIELD COORDINATION RESPECTIVELY.
OUR CORE FOCUS IS TO ELEVATE THE CUSTOMER AND VENDOR EXPERIENCE BY DELIVERING FIRST-IN-CLASS CONSTRUCTION SERVICES THAT CATER TO OUR CLIENTS' NEEDS AND MAINTAIN COST EFFECTIVENESS AND DRIVE INNOVATIVE EXECUTION.
THE CORE VALUES THAT WE LIVE BY EVERY DAY ARE INTEGRITY, ACCOUNTABILITY, PERSISTENCE, AND COLLABORATION.
WE'RE A PROUD MEMBER OF ABC AND HAVE WON
[00:50:01]
NUMEROUS EXCELLENCE IN CONSTRUCTION AWARDS OVER THE PAST SEVERAL YEARS AND MOST RECENTLY, WE GOT BEST PLACES TO WORK AT BY THE SOUTH FLORIDA BUSINESS JOURNAL, WHICH WE'RE VERY PROUD OF.SOME OF THE PROJECTS THAT HAVE SIMILAR FEATURES TO SABAL, DORAL WHITE COURSE ON THE TOP LEFT.
THAT'S A THREE-ACRE DEVELOPMENT, GROUND-UP CONSTRUCTION THAT WE RECENTLY PERFORMED, CAPE CORAL AT THE CENTER, THAT'S TWO SEPARATE PARKS, CULTURAL PARK, AND GATOR CIRCLE PARK, BOTH WITH SIMILAR AMENITIES TO SABAL.
THE FORT LAUDERDALE FIRE STATION PARKING LOT ON THE TOP RIGHT.
THAT WAS A COMPLETE NEW PARKING LOT FOR THE STATE OF FORT LAUDERDALE ON THE BEACH, BAY HARBOR DOG PARK ON THE BOTTOM LEFT, WHICH IS A PARK THAT WE DID AS A DESIGN-BUILD WITH MILLER LEGG AND VILLAGE OF ROYAL PALM BEACH, CRESTWOOD NORTH PARK.
THAT'S A PRODUCT THAT WE JUST FINISHED LAST YEAR AS WELL, NEW GROUND OF CONSTRUCTION.
TO THE RIGHT IS A SPLASH PAD THAT WE ALSO JUST FINISHED FOR THE CITY OF HOMESTEAD.
I'LL TURN IT OVER TO MIKE FROM MILLER.
>> GOOD MORNING. I'M MIKE KROLL WITH MILLER LEGG.
AGAIN, PLEASED TO BE ON THE WAYPOINT TEAM AND PRESENTING TO YOU FOR SABAL PALM PARK.
WE'LL BE HANDLING ALL THE SITE DESIGN, LANDSCAPE ARCHITECTURE, CIVIL ENGINEERING, COORDINATING WITH CHARLES AND HIS ARCHITECTURAL STAFF, AS WELL AS THE WAYPOINT STAFF, AND ALL THE ENVIRONMENTAL ASPECTS THAT WE'RE GOING TO BE DEALING WITH.
WE HAVE OVER 250 PARKS PROJECTS HERE IN SOUTH FLORIDA ALONE, AND THAT INCLUDES EVERYTHING FROM MASTER PLANNING DOWN TO DETAILED DESIGN.
SOME OF THE EXPERIENCE THAT WE'VE JUST SEEN HERE IS HIGHLIGHTED.
OBVIOUSLY, ONE OF THE THINGS THAT WE'RE WORKING ON RIGHT NOW WITH TAMARAC IS THE CAPORELLA PARK, YOUR OVERFLOW PARKING THERE.
WE DID COLLABORATE WITH WAYPOINT ON BAY HARBOR, THEIR DOG PARK, THEIR MOST RECENT DOG PARK.
IN BOCA, WE ARE DOING NORTH PARK, THAT'S OVER 200 ACRES, AND THAT'S AN OLD GOLF COURSE THAT WE'RE TURNING INTO A PASSIVE PARK.
VERY SIMILAR TO WHAT WE'RE DOING HERE.
MANY OF THE SAME TYPE OF ELEMENTS ARE INCORPORATED IN THAT PROJECT AND SAME ENVIRONMENTAL CONCERNS, AND THEN ROLLING OAKS REGIONAL PARK, ALSO.
>> GOOD MORNING. THANK YOU FOR INVITING US HERE.
I'M CHARLES MICHELSON, PRESIDENT OF SALTZ MICHELSON ARCHITECTS, AND WE'RE A LEGACY BROWARD COUNTY FIRM.
NEXT YEAR, WE'LL BE CELEBRATING 50 YEARS HERE IN BROWARD COUNTY WITH 33 PEOPLE STRONG WITH 10 REGISTERED ARCHITECTS.
NOW, OBVIOUSLY OVER THAT TIME, WE HAVE EXTENSIVE EXPERIENCE WORKING ON A WIDE VARIETY OF PARKS AND RECREATION FACILITIES, JUST A SAMPLING ARE SHOWN ON THE SCREEN.
SOME PROJECTS THAT YOU MIGHT BE FAMILIAR WITH THAT ARE VERY RECENT FOR THE CITY OF SUNRISE.
WE RENOVATED THEIR SPORTS ATHLETIC FACILITY ON SUNRISE BOULEVARD, HEADING WEST, AND THE CITY PARK IN SUNSET STRIP, ON THE EAST, HAVING MANY OF THE SAME ELEMENTS IN THOSE FACILITIES THAT YOU HAVE IN YOURS.
FOR EXAMPLE, YOU START TO SEE HERE SOME OF THE SPLASH PADS AND RESTROOM BUILDINGS, CONCESSION BUILDINGS, ETC.
ANYWAY, WE'VE WORKED WITH EVERYBODY ON THIS TEAM BEFORE.
WE'RE VERY COMFORTABLE IN A WELL OILED TEAM PUTTING THESE PROJECTS TOGETHER FOR YOU.
>> THANK YOU, CHARLES. NEXT, WE HAVE JEFF FROM MEC ENGINEERING.
>> GOOD MORNING, JEFF THOMPSON, MEC ENGINEERING, PRESIDENT OF MEC ENGINEERING.
WE'RE ENVIRONMENTAL AND CIVIL ENGINEERING FIRM, BUT FOCUSING ON ENVIRONMENTAL FOR THIS PROJECT SPECIFICALLY.
WE HAVE QUITE A BIT OF EXPERIENCE IN THE REDEVELOPMENT OF CONTAMINATED SITES, INCLUDING SOIL BLENDING ON PARKS, MOST RECENTLY COMPLETING PHASE 2 OF THE UNDERLYING LINEAR PARK, ABOUT TWO-AND-A-HALF MILES IN MIAMI-DADE.
ALSO DID A REMEDIATION OF A PARK ABOUT THIS SIZE, EIGHT ACRES OF OLINDA PARK, ARSENIC CONTAMINATION SIMILAR TO THE SITE.
NUMEROUS PROJECTS THROUGHOUT MIAMI-DADE AND SOUTH FLORIDA ON THE REDEVELOPMENT OF CONTAMINATED SITES, INCLUDING TWO RECENTLY HERE IN BROWARD AT THE PORT EVERGLADES BYPASS BRIDGE AND FORT LAUDERDALE TERMINAL 5 EXPANSION FOR JETBLUE.
>> THANK YOU, JEFF. JUST TO GIVE YOU A HIGH LEVEL PROJECT SCHEDULE, THE CONTRACT OBVIOUSLY ALLOWS FOR 640 DAYS.
PHASE 1 IS GOING TO BE THE DESIGN PORTION.
THAT'S GOING TO INCLUDE THE SITE INVESTIGATION AND THE ENVIRONMENTAL REMEDIATION.
JUST SOME OF THE HIGH LEVEL DELIVERABLES DURING THAT PHASE, OBVIOUSLY CONTRACT NEGOTIATION, WHICH WILL THEN ALLOW US TO GO INTO PRECONSTRUCTION SERVICES AND DEVELOP THE DESIGN.
WE'RE GOING TO PROPOSE A 30,60, 90%, AND 100% DESIGN DELIVERABLES BEFORE WE GO INTO PERMITTING.
THEN PHASE 2 WILL OBVIOUSLY BE THE CONSTRUCTION OF THE PROJECT.
I'M GOING TO TURN IT OVER TO JEFF JUST TO TALK A LITTLE BIT MORE ABOUT THE SITE REMEDIATION EFFORT.
>> SURE, AS ONE OF THE FIRST STEPS WOULD BE THE SITE REMEDIATION OF ARSENIC IMPACTED CONTAMINATED SOILS, WHICH THERE'S BEEN QUITE A BIT OF ASSESSMENT ON THE SITE ALREADY.
[00:55:02]
WE MAY DO ADDITIONAL SITE ASSESSMENT FOR SOIL SAMPLING TO REFINE A SOIL MANAGEMENT PLAN.BUT THE SOIL MANAGEMENT PLAN AND REMEDIAL ACTION PLAN WILL BUILD ON THE CURRENT ASSESSMENT AND REMEDIATION CONCEPT, INCLUDING SOME SOURCE REMOVAL, SOIL BLENDING AND PROVIDING A TWO FOOT CLEAN SOIL CAP FOLLOWING THE REMEDIATION, THE ASSESSMENT THAT'S REQUIRED AS OUTLINED TO COLLECT ABOUT 80 SOIL BORINGS, VERIFYING THE TOP TWO FEET, MEET THE ALTERNATIVE CLEANUP TARGET LEVEL FOR PARKS AS SPECIFIED.
COMPLETING THAT, WE'LL HAVE ENGINEERING CONTROL SOIL MANAGEMENT PLAN IMPLEMENTATION.
THE ENGINEERING CONTROL AS BUILT WILL DELINEATE THE PARK FEATURES THAT WILL ACT AS THE ENGINEERING CONTROL, WHETHER IT BE TWO FEET A CAP OR IMPERVIOUS SURFACES.
CLOSING OUT THESE PROJECTS WITH AN ENVIRONMENTAL SITE CLOSURE, I THINK IS A VERY IMPORTANT PART AS YOU CAN GET STUCK WHEN YOU ARE TRYING TO COMPLETE THE CLOSE OUT ON THE ENVIRONMENTAL BEFORE YOU CAN USE THE PARK AND THIS IS SOMETHING THAT WE'RE VERY FAMILIAR WITH. THAT WOULD BE OUR PLAN.
>> THANK YOU, JEFF. THIS PROJECT FROM A HIGH LEVEL TO SHARE WITH YOU, WHAT WE'RE PROPOSING IS GOING TO HAVE A ONE STORY STRUCTURE RESTROOM WITH CONCESSION, STORAGE ROOMS AND UTILITY AREAS, A COVERED SPLASH PAD AND A COVERED PLATE GROUND, A MULTI-USE TRAIL, A COVERED FITNESS AREA, PRE-ENGINEER PICNIC SHELTERS, MULTI-PURPOSE, BASKETBALL, AND PICKLEBALL COURTS, AND MULTI-PURPOSE, ARTIFICIAL TURF FIELD, A DOG PARK AND A NEW PARKING LOT.
I'M GOING TO ALLOW CHARLES TO SPEAK A LITTLE BIT ABOUT THE ARCHITECTURE ON THE RESTROOM BUILDING.
>> THE TRUE ARCHITECTURE OF THIS PROJECT HAS TO DO WITH THE LANDSCAPE ARCHITECTURE AND THE DESIGN OF THE SITE.
THE BUILDINGS ITSELF ARE VERY UTILITARIAN AND HAVE TO BE RESPECTFUL OF THE BUDGET FOR THE MONEY THAT YOU HAVE AVAILABLE TO DO THIS.
HERE'S A PARK RESTROOM FACILITY THAT'S VERY STRAIGHTFORWARD, VERY EFFICIENT, ALONG WITH CONCESSION.
ALSO VERY IMPORTANT FOR ANY PARK FACILITY IS HAVE THE APPROPRIATE STORAGE, THE ABILITY TO GET INTO THE BUILDING THROUGH OVERHEAD DOORS AND SIDE DOORS.
ALSO HAVE AREAS WHERE THEY ANTICIPATE WATER TO COME IN AND DRAIN FROM THE FACILITY VERY STRAIGHTFORWARD.
IT'S JUST A VERY STRAIGHTFORWARD UTILITARIAN BUILDING THAT CAN BE VERY ATTRACTIVE.
AGAIN, SLIDE WE END UP WITH A METAL ROOF ON THE BUILDING, SOME SCORED STUCCO.
WHAT WE LIKE TO DO IS MEET WITH THE CITY AND EVEN MEMBERS OF THE COMMUNITY TO TALK ABOUT THE COLORS AND THE STYLE OF ARCHITECTURE.
BECAUSE WHEN THERE'S BUY IN FROM THE COMMUNITY, PARKS ARE MUCH BETTER RECEIVED.
INSTEAD OF COMING IN WITH FINISHED RENDERINGS, WHAT WE'D LIKE TO DO IS HAVE A LITTLE HARE, EVEN A HALF HOURS WORTH OF TIME GOES A LONG WAY TO BUYING ACCEPTANCE IN THE COMMUNITY.
>> THANK YOU, CHARLES. THIS NEXT SLIDE IS SOME RENDERINGS OF THE PROPOSED SPLASH PAD BY VORTEX.
MIKE, YOU WANT TO SPEAK A LITTLE BIT ABOUT THAT ON THE PLAYGROUND THAT'S NEXT.
>> SURE. AGAIN, WHAT'S IMPORTANT IS THAT THESE AMENITIES ADDRESS NOT ONLY A SMALL GROUP OF PEOPLE, BUT AS WIDE AND DIVERSE AGE GROUPS AS POSSIBLE.
AGAIN, WE DON'T SHOW THE CANOPY ON TOP OF THIS BECAUSE OF JUST FOR GRAPHIC PURPOSES, BUT THERE WOULD BE A COVERED CANOPY OVER THE TOP OF THE SPLASH PAD.
AGAIN, ACCESSIBILITY IS CRITICAL.
OUR SPLASH PAD WILL BE ACCESSIBLE FOR ALL USERS.
THERE WILL BE ACTUALLY DIFFERENT LEVELS OF INTERACTION WITH DISPLAY AND SPRAY EQUIPMENT FOR PEOPLE IN WHEELCHAIRS OR MOBILE FOLKS ALSO.
ALSO WOULD BE DIFFERENT LEVELS OF CONTROLS SO THAT THE SMALLER KIDS CAN USE THEM AS WELL AS THE BIGGER KIDS AND DIFFERENT TYPES OF ACTIVITIES.
SURFACE WISE, IT'LL BE FLUSH WITH THE ADJACENT SIDEWALKS, SO THERE WILL BE OBVIOUSLY ACCESSIBILITY FOR THAT.
NEXT. SAME TYPE OF THING WITH THE PLAYGROUND AND THE PLAYGROUND THAT WE HAVE SHOWN HERE IS FROM LANDSCAPE STRUCTURES.
IT WILL BE A COVERED PLAYGROUND, AGAIN, COVER IS NOT SHOWN ON THIS FOR ILLUSTRATIVE PURPOSES.
BUT WE'LL ADDRESS BOTH ACCESSIBILITY AND INCLUSIVENESS IN THIS PLAYGROUND.
NOT ONLY WILL THE CHILDREN BE ABLE TO ACCESS IT, BUT THE PEOPLE, THE CHILDREN WILL BE ABLE TO ACTUALLY BE ENGAGED IN THAT PLAY FACILITIES.
THEY'LL BE MODIFIED AND DESIGNED IN SUCH A WAY THAT WILL ACCOMMODATE CHILDREN FROM TWO TO 12 YEARS-OLD, 13-YEARS-OLD IS A STANDARD.
HOW WE'VE DONE THAT IS THAT CENTRALIZED PLAY EQUIPMENT IS REALLY FOR FIVE TO 12, AND THE TWO TO FIVE YEAR OLDS BECAUSE YOU DON'T WANT TO MIX THOSE KIDS, THE BIGGER KIDS, AND THE SMALLER KIDS.
THOSE WILL BE A LITTLE BIT MORE INDEPENDENT FEATURES, STANDALONE FEATURES WHERE THE PARENTS COULD
[01:00:03]
SUPERVISE ALL THE STUDENT OR CHILDREN WHEREVER THEY ARE, BUT STILL BE IN THE SAME PLAYGROUND.ARTIFICIAL TURF IS WHAT WE'RE PROPOSING TO UTILIZE AS THE SURFACE THERE ON THIS.
AGAIN, THAT'S REALLY IMPORTANT BECAUSE THAT ALLOWS FOR UNINHIBITED ACCESSIBILITY AND INCLUSIVITY INTO THIS PLAYGROUND.
>> NEXT WE HAVE A RENDERING OF THE COVERED FITNESS AREA JUST SO YOU COULD HAVE AN IDEA WHAT THAT'S GOING TO LOOK LIKE.
MIKE I DON'T KNOW IF YOU HAVE ANYTHING TO ADD ON THAT ONE.
>> SURE. AGAIN, THE FOCUS IS VERY SIMILAR.
NOW, THIS IS A PLAYGROUND FOR OLDER FOLKS.
THIS IS NOT JUST WHERE YOU GO EXERCISE, BUT THIS IS TRULY WHERE SOMEONE WHO IS 13 OR 83 CAN COME AND ENJOY THIS AREA.
ALSO, SOMEONE WHO IS MOBILE OR NOT MOBILE.
MAYBE HAVE ACCESSIBILITY NEEDS.
AGAIN, THIS EQUIPMENT IS FROM GREENFIELDS, AND THEY ARE EXPERTS AND THEIR FOCUS IS BEING ABLE TO MAKE SURE THAT FOLKS OF ALL CAPABILITIES CAN USE THIS EQUIPMENT.
THERE'S MULTIPLE STATIONS, ADEQUATE SPACING.
AGAIN, THIS IS REALLY THE WAY THAT FITNESS IS BEING APPROACHED NOWADAYS WITH CONSOLIDATED SPACES RATHER THAN THOSE FITNESS AREAS ALONG A MULTI-PURPOSE TRAIL BECAUSE THIS BECOMES A DESTINATION WHERE IT CAN ACTUALLY BE USED WHERE THE PARENTS ARE USING THIS AND THEY'RE OBSERVING THEIR CHILDREN IN OTHER AREAS OF THE PARK.
>> NEXT SLIDE, IS JUST A RENDERING OF THE COVERED PICNIC SHELTERS.
AGAIN, JUST TO GIVE YOU A VISUAL IDEA OF HOW THAT WOULD LOOK.
THEN WE WANTED TO TAKE A MINUTE TO SPEAK A LITTLE BIT ABOUT THE DOG PARK, CURRENT FLOOR PLAN THAT YOU HAVE IN FRONT OF YOU JUST SHOWS A GENERAL LAYOUT BUT WE WANTED TO TALK ABOUT SOME OF THE FEATURES THAT WOULD GET INCORPORATED INTO THE DESIGN, AND I'LL LET MIKE SPEAK ABOUT THAT.
>> WE TALKED ABOUT RECREATION FOR PEOPLE.
IN THIS PARK, WE'RE ALSO GOING TO RECREATE FOR THE DOGS.
I REALLY BECOMES A SOCIAL NODE AT THE END OF THE DAY.
IT'S NOT ONLY WHERE THE DOGS GO BUT WHERE PEOPLE GO ALSO.
WE HAVE TO THINK ABOUT THAT INTERACTION.
SOME OF THE THINGS THAT WE DEAL WITH, ESPECIALLY FOR THE DOGS AND SAFETY AND SUCH IS WE SEGREGATE SMALLER DOGS AND LARGER DOGS.
THEY HAVE A SEPARATE ENTRANCE AND ACCESS INTO THE PARK.
THERE'S REALLY NO SHARP CORNERS IN THE DESIGN OF OUR DOG PARKS.
WHY THAT IS IS BECAUSE WHEN YOU HAVE AN ACUTE ANGLE IN A DOG PARK, THAT CAN BE AN AREA WHERE A DOG CAN BE TRAPPED BY OTHER DOGS AND BE ATTACKED.
THAT'S SOMETHING THAT WE ALWAYS LOOK AT IN THE DESIGN OF OUR DOG PARKS IS TO MINIMIZE OR REDUCE OR TAKE OUT ANY OF THOSE SHARP CORNERS.
A SIX FOOT HIGH FENCE IS GOING TO BE WHAT WE WOULD PROPOSE TO HAVE ON THE EXTERIOR OF THAT DOG PARK.
AGAIN, FROM A SAFETY PERSPECTIVE, OF DOGS GETTING OUT OR CHILDREN GETTING IN.
THAT'S SOMETHING THAT'S VERY IMPORTANT.
THEN A DOG WASH STATION AS WELL AS A WATERING STATION IS SOMETHING ELSE THAT WE'RE INCLUDING INTO THE DOG PARK.
THEN BENCHES, BECAUSE AGAIN, WE'RE TALKING THAT THIS IS NOT JUST A SOCIAL NODE FOR DOGS, BUT THAT'S WHERE THE OWNERS ALSO SOCIALIZE ALSO.
WE INCORPORATE THAT IN THE DESIGN.
>> THANK YOU, MIKE. WE TALKED A LOT ABOUT A DESIGN.
I WANT TO TALK A LITTLE BIT ABOUT THE CONSTRUCTION PROCESS AS OBVIOUSLY, THAT'S THE MOST INVASIVE PROCESS IN THIS ENTIRE PROJECT.
SOME OF THE ITEMS THAT WE DEPLOY DURING THE CONSTRUCTION TO MAKE SURE THAT WE MINIMIZE THE IMPACT TO THE COMMUNITY AND THE NEARBY RESIDENTS IS MAKING SURE THAT WE FENCE OFF OUR CONSTRUCTION SITE, WINDSCREEN THE ENTIRE SITE, TO MAKE SURE WE CONTROL DUST TO THE NEIGHBORING RESIDENTS.
ALL OF OUR CONSTRUCTION SITES ARE GOING TO HAVE A ROCK CONSTRUCTION ENTRANCE WITH A WASHED DOWN STATION TO MAKE SURE THAT ALL THE VEHICLES LEAVING THE PARK ARE PROPERLY RINSED OFF AND WASHED DOWN OF ANY SEDIMENT AND CONTAMINANTS BEFORE THEY LEAVE.
NOTIFICATION TO THE RESIDENTS IS SOMETHING THAT WE'RE GOING TO DO.
WE KNOW THAT IT'S A CITY REQUIREMENT.
WE'RE GOING TO MAKE SURE WE COMMUNICATE TO THEM PRIOR TO THE BEGINNING OF CONSTRUCTION AND WHAT TO EXPECT DURING THE PROCESS.
WORK HOURS, MONDAY THROUGH FRIDAY, 8:00-5:00 PM.
AGAIN, PER CITY CODE, MY UNDERSTANDING, MAKING SURE AGAIN THAT WE KEEP EVERYONE SAFE AND OUTSIDE OF THE PERIMETER OF THE CONSTRUCTION.
>> YOU HAVE 4.5 MINUTES, GEORGE.
>> THANK YOU. I JUST WANTED TO HIGHLIGHT SOME FEATURES THAT WE MAKE SURE WE IMPLEMENT INTO EVERY ONE OF OUR PROJECTS THAT WE HAVE FOUND ALLOW US TO PROVIDE A SUCCESSFUL PROJECT TO BOTH THE CLIENT AND THE END USER DURING THE CONSTRUCTION PROCESS.
NUMBER 1 IS WE WANT TO MAKE SURE THAT WE FOSTER A STRONG PARTNERSHIP WITH THE CITY, THE COMMUNITY, AND THE DESIGN BUILD TEAM.
TWO, ENSURING THAT THE DESIGN PROGRESS ALIGNS WITH THE BUDGET AND THE SCOPE THROUGHOUT THE ENTIRE PROJECT.
THREE IS DEVELOP AND TRACK A REALISTIC PROJECT TIMELINE, AND FOR THAT, WE USE MICROSOFT PROJECT AND A NASA STAT TOOL THAT MAKE SURE THAT WE HAVE A HEALTHY AND RELIABLE PROJECT SCHEDULE THROUGHOUT THE ENTIRE CONSTRUCTION PROJECT.
ADDITIONALLY, WE DEVELOP LOOK AHEAD SCHEDULES THAT CAN LOOK OUT ANYWHERE TWO TO THREE WEEKS.
WE PROVIDE THAT TO THE PROJECT TEAM AND THE CLIENT ON A WEEKLY BASIS TO MAKE SURE THAT THEY'RE UP TO SPEED WITH THE DETAILS OF CONSTRUCTION AS THEY HAPPEN.
[01:05:03]
FOR MAKING SURE THAT WE LEVERAGE OUR ESTABLISHED RELATIONSHIPS WITH THE KEY VENDORS AND SUPPLIERS FOR DESIGN INPUT, BUDGETING, AND VALUE ENGINEERING.AGAIN, FIVE, SOMETHING THAT WE JUST SPOKE ABOUT, MAKING SURE THAT WE KEEP THE RESIDENTS INFORMED.
THEY'RE THE BIGGEST CRITICS OF THIS PROJECT, AND WE WANT TO MAKE SURE THAT WE PARTNER WITH THEM AND KEEP THEM INFORMED OF ALL THE ACTIVITIES THAT ARE GOING ON DURING THE PROJECT, FOR DUST AND NOISE CONTROL, AND FOR TRAFFIC INTERRUPTIONS.
SIX, MAKING SURE THAT WE UTILIZE OUR EXPERIENCE IN DOING GOVERNMENT WORK TO MAKE SURE THAT WE ADHERE WITH ALL THE REQUIREMENTS THAT THE CITY HAS FOR THIS PROJECT.
PRICING PROPOSAL FOR SABAL PALM.
JUST TO GIVE YOU A QUICK BREAKDOWN HERE, THE CLEARING AND ENVIRONMENTAL.
THAT'S $2,074,000, AND THE DESIGN BUILDING CONSTRUCTION WAS $8.3 MILLION FOR A SUBTOTAL OF 10.4.
THAT'S OUR PRESENTATION. THANK YOU VERY MUCH FOR YOUR TIME.
>> THANK YOU GUYS SO MUCH. OPEN.
>> SEEING NO QUESTIONS FROM MY COLLEAGUES, WELL, I HAVE ONE QUESTION THAT YOU JUST HAD.
IT SAYS SUBTOTAL CONTRACT AMOUNT.
WHY IS IT A SUB TOTAL OR NOT THE TOTAL?
>> THAT SHOULD BE TOTAL, SORRY.
>> JUST CHECK. I WILL JUST MAKE COMMENTS BECAUSE I WAS TOLD THAT I'M NOT ALLOWED TO ASK CERTAIN THINGS AT THIS POINT IN TIME.
I'M JUST GOING TO SHARE WITH YOU MY OPINION FOR THE DOG PARK, NEEDS TO HAVE A LITTLE DOGGY POOL TO JUST AS MUCH AS A PET PARENT.
WE KNOW THE DOGS LOVE TO PLAY IN THE WATER TO AND JUST GIVING THEM A BATH ON THE LITTLE SHOWER THING NOT ENOUGH.
AS FAR AS THE PICKLEBALL, I'VE EXPRESSED MY CONCERNS.
I KNOW PEOPLE LOVE PICKLEBALL.
BUT ESPECIALLY WHERE I SEE THAT IT IS HOUSED ON YOUR SITE PLAN FOR RIGHT NOW, IT IS WAY TOO CLOSE TO HOMES AND WILL ONLY CAUSE EVERYBODY A LOT OF DURESS UNLESS YOU PLAN ON ENCLOSING IT AND MAKING IT SOUND PROOF.
THOSE ARE MY COMMENTS THAT WILL BE DISCUSSED OR SHARE WITH EVERYBODY, JUST TO LET YOU KNOW.
NOW, COMMISSIONER BOLTON HAS A QUESTION.
>> I NOTICED THAT YOU USE SOME PICTURES HERE, SOME RENDERINGS.
WHERE DID YOU GET THAT FROM? IS IT JUST ONLINE?
>> YEAH. I DO BELIEVE THOSE WERE GENERAL RENDERINGS THAT WE PULLED FROM OTHER PRODUCTS.
>> BECAUSE I SAW SOME OF THE SAME PHOTOS IN THE DEPRIMO PRESENTATION.
>> MOST LIKELY THAT'S FROM GREENFIELD, THE MANUFACTURER WHERE WE PULLED THOSE FROM.
THEY HAVE GENERAL PICTURES OF ALL THEIR EQUIPMENT AND PRODUCTS THAT THEY'VE USED BEFORE.
>> YOU'D BE PARTNERING WITH GREENFIELD OUTDOOR FITNESS AS WELL?
>> THAT'S THE MANUFACTURER, WE INTEND TO USE FOR THAT, YES.
>> THANK YOU, AND THEN COMMISSIONER WRIGHT IS ON THE SKY.
>> ON MY END, THE PRICING MOVED REAL FAST, IF YOU CAN SHOW THAT ON THE SCREEN AGAIN, SO I CAN JUST WRITE THAT DOWN TO MAKE MY NOTES.
>> YEAH. I'M JUST PUTTING THE NUMBERS NO FAST.
>> THANK YOU. SEEING THERE ARE NO OTHER QUESTIONS.
THANK YOU VERY MUCH FOR YOUR PRESENTATION.
>> LADIES AND GENTLEMEN, IT IS 12:11.
WE WILL BE RECONVENING AT 1:15.
IS THAT WHEN THE SCHEDULE IS? 01:15. WE WILL SEE YOU BACK HERE AT 1:15.
>> THANK YOU. HAVE A GOOD DAY EVERYONE.
>> THANK YOU VERY MUCH FOR YOUR PATIENCE.
WE'RE APOLOGIZING FOR BEING LATE.
CITY CLERK, DO WE NEED TO DO ANYTHING WITH ROLL OR WE'RE GOOD?
>> GOOD AFTERNOON. RECREATIONAL DESIGN CONTRACTING.
AS EXPLAINED IN THE LETTER YOU RECEIVED, YOU GUYS ARE GOING TO BE PROVIDING A 20 MINUTE PRESENTATION TO THE CITY COMMISSION.
YOU'LL SEE THE COUNTER RIGHT HERE IN TERMS OF YOUR TIME AFTER WHICH POINT THE COMMISSION MAY HAVE SOME QUESTIONS FOR YOU.
WITH THAT BEING SAID, GO AHEAD AND GET INTO IT. [INAUDIBLE]
>> DO YOU HAVE ANY PRESENTATION MATERIAL HANDOUTS OR ANY? JUST A SCREEN?
>> THAT'S OKAY. I'M MONITORING IT ON THE SCREEN.
I SEE IT OVER HERE. WE HAVE THE TWO SCREENS. THANK YOU.
>> THANK YOU. GOOD AFTERNOON, AND THANK YOU FOR THE OPPORTUNITY.
MY NAME IS JOE RON, PRESIDENT OF RECREATIONAL DESIGN OF CONSTRUCTION
[01:10:01]
AND I'D LIKE TO INTRODUCE OUR DESIGN TEAM.I DON'T WANT TO WASTE TOO MUCH TIME.
MY WE'LL DO IT WHILE WE'RE INTO IT.
HOW DO I MOVE THE SLIDES? THE BUTTON.
THANK YOU. RDC IS AN ESTABLISHED DESIGN BUILD TEAM.
SOME OF THE RELATIONSHIPS BETWEEN THESE FIRMS GO BACK 30 YEARS.
STAN TECH AND RDC, AQUI DYNAMICS HAVE BEEN WORKING TOGETHER FOR 30 YEARS.
WE'VE COMPLETED 500 DESIGN BUILD PROJECTS, 27 SYNTHETIC TURF FIELD, 125 PLAYGROUNDS, 72 RESTROOM CONCESSION BUILDINGS, FOUR PROJECTS FOR THE CITY OF TAMARAC, FITNESS AREAS, MULTIPURPOSE TRAILS, PAVILIONS, SPLASH PADS, DOG PARKS, AND 25 SITE REMEDIATIONS.
THE PARK HAS EVERYTHING THAT YOU ASKED FOR.
THIS IS OUR VERSION OF YOUR PROJECT.
WE PLACE THE MULTI PURPOSE FIELD, THE BASKETBALL COURT, THE PICNIC SHELTERS AND STRATEGIC LOCATIONS.
THE SPLASH PAD IS AWAY FROM THE BUILDING SO THAT IF THEY'RE HAVING TWO EVENTS AT THE SAME TIME, THE BUILDING ISN'T JAM PACKED TOGETHER.
THE RESTROOM CONCESSION, ALL THE FACILITIES ARE VERY WELL THOUGHT OUT AND WHAT YOU ASKED FOR AND OUR PROJECT APPROACH IS VERY SIMPLE.
WE BRING THE DESIGN TEAM TOGETHER WITH THE CITY OF TAMARAC AND THE STAKEHOLDERS AND WE MAKE SURE THAT OUR PROGRAM MATCHES YOURS.
WE PREPARE THE DOCUMENTS FOR PUBLIC REVIEW, PERMITTING AND APPROVAL THROUGH ALL REGULATORY AGENCIES, AND WE KNOW THAT SOME OF THESE REGULATORY AGENCIES DO TAKE A VERY LONG TIME.
WE MANAGE THE PROCUREMENT LOG.
EVERYTHING HAPPENS THROUGH THE PROCUREMENT LOG AND THE SCHEDULE.
THE PROCUREMENT LOG, IF THERE'S A LONG LEAD ITEM, WE WANT TO KNOW WHEN IT'S SUPPOSED TO ARRIVE AND WHEN IT WILL ARRIVE AND WHEN IT GETS IMPLEMENTED IN.
WE MANAGE THE TRADES, OFFSITE PARKING, ONSITE PARKING, ACCESS TO THE SITE, SITE LOGISTICS AND SAFETY AND WE HAVE AN ESTABLISHED QUALITY CONTROL PROGRAM THAT ENSURES TIMELY PROJECT COMPLETION AND WE'RE GOING TO TALK ABOUT SITE REMEDIATION.
>> THIS ONE, I DON'T HAVE ANY SLIDE.
THIS IS MY ONLY SLIDE. I DON'T HAVE TO WORRY ABOUT THIS.
WE'RE LOCATED IN FORT LAUDERDALE.
FOR THE SITE REMEDIATION, I THINK EVERYBODY KNOWS THAT THIS SITE USED TO HAVE A HISTORY BEHIND IT WITH ARSENIC CONTAMINATED SOILS.
THE PREVIOUS CONSULTANT DID A VERY GOOD JOB OF DOING THESE THE ASSESSMENT OF WHERE THE ARSENIC CONTAMINATED SOIL IS AT AND THE DEPTH AND WHATNOT.
OUR TASK WILL BE TO WRITE THE REMEDIAL ACTION PLAN AND WHAT'S CALLED THE SOIL MANAGEMENT PLAN.
BOTH OF THESE TOGETHER WILL DICTATE HOW WE'RE GOING TO APPROACH THE CONSTRUCTION SIDE OF THE PARK.
THESE DOCUMENTS, THE REMEDIAL ACTION PLAN AND RAP AND SOIL MANAGEMENT PLAN WILL BE CONDUCTED CONCURRENTLY.
WE WORK WITH BROWARD COUNTY ALL THE TIME VERY FREQUENTLY.
WE'LL GET THEM ON BOARD RIGHT AWAY AS TO WHAT WE WANT TO DO AND WHAT THE GOAL OF THE REMEDIATION IS, WHICH IS NOT TO HAVE A CLEAN, PRISTINE ARSENIC FREE SITE.
IT WILL BE TO PROTECT THE HEALTH AND SAFETY OF THE PARK USERS WHEN IT'S ALL SAID AND DONE.
THERE WILL BE WHAT WE CALL ENGINEERING CONTROLS PLACED UPON THE SITE.
SAFETY IS GOING TO BE OF UTMOST CONCERN TO FIRST, THE CONSTRUCTION WORKERS BECAUSE THEY HAVE TO KNOW THAT THEY'RE GOING TO BE DEALING WITH ARSENIC IMPACTED SOIL.
WE'LL PUT IN OUR SOIL MANAGEMENT PLAN, WE'LL HAVE SAFETY GUIDELINES AND WE'LL GO AND WE'LL TEACH EVERYBODY WHO'S ON SITE HOW TO HANDLE ANY ARSENIC CONTAMINATED DIRT TO PROHIBIT INGESTION, DERMAL CONTACT, AND INHALATION.
SECOND WILL BE THE RESIDENTS OF THE COMMUNITY AND THE SURROUNDING AREA WHERE WE TYPICALLY WILL DO WIND PARTICULATE MONITORING OF THE NEIGHBORHOODS AROUND THE AREA TO MAKE SURE THAT DUST IS IN CONTROL, AND THERE'S NO ARSENIC CONTAMINATED SEDIMENTS THAT LEAVE THE SITE.
THEN THIRDLY, THE PARK USERS, WHEN IT'S ALL SAID AND DONE, WILL HAVE ENGINEERING CONTROLS IN PLACE THAT WILL HOPEFULLY PUT THE RISK TOLERANCE OF ZERO TO ANY PARK USER FOR DERMAL CONTACT.
THAT WILL BE ESSENTIALLY WHAT THE ENGINEERING CONTROLS WILL DO.
WE'LL DO THAT THROUGH A COMBINATION OF ARTIFICIAL TURF AND ET CETERA.
OUR MAIN GOAL IS TO PRESERVE AS MANY TREES AS WE CAN.
I KNOW THE TREES ARE IMPORTANT HERE.
WHEN WE DESIGN IT, WE'LL KEEP THE TREES ALL THE TREES THAT WE CAN,
[01:15:01]
AND THEN ALSO TO INTEGRATE DRAINAGE AND UTILITY CONSTRUCTION INTO THE REMEDIAL ACTION PLAN SO THAT WE CAN MINIMIZE THE AMOUNT OF SOIL THAT WE ACTUALLY TAKE OFF SITE.WE'RE GOING TO BE USING A COMBINATION OF SOIL EXCAVATION, VERY MINIMAL AND SOIL BLENDING TO REACH THE TARGET GOAL OF 5.5 MILLIGRAMS/KILOGRAM FOR THE SITE AND BEFORE WE PUT OUR ENGINEERING CONTROL IN CAP.
WITH THAT, I'LL TURN IT OVER TO THE DRAINAGE EXPERTS.
I'M THE CIVIL ENGINEER, SO I GET TO TALK ABOUT SOME OF THE MORE BORING STUFF, BUT THE IMPORTANT THINGS THAT ALLOW THIS PARK TO FUNCTION.
WE'VE EVALUATED THE SITE SIGNIFICANTLY IN THIS PROCESS.
TYPICALLY, THIS WOULD BE A FAIRLY SIMPLE PROJECT.
IT'S COMPLICATED BY THE MITIGATION REQUIREMENTS.
WE'VE GONE WITH AN APPROACH THAT IS ALL DRAINING AT THIS POINT IN TIME WITH OPEN RETENTION AREAS THAT WILL COLLECT AND HOLD THE SURFACE RUNOFF WATER UNTIL WHICH TIME IT CAN DRAIN INTO THE SOIL.
THAT'S LARGELY TO AVOID ANY UNDERGROUND PASSAGE OF WATER THAT WILL MOVE THE CONTAMINATION AND SO THIS IS SOMETHING THAT WE WILL WORK WITH BROWARD COUNTY AND JEFF ON AS PART OF THE REMEDIATION PLAN TO ENSURE THAT WE ARE NOT MAKING THE CONTAMINATION ISSUES WORSE.
WE'LL BE COORDINATING CLOSELY WITH THE ENVIRONMENTAL MITIGATION PLAN, AND THE ELEVATIONS THAT WE USE AS PART OF THIS PROCESS, WE WILL ADAPT THEM AS WE GO TO MINIMIZE THE AMOUNT OF SOIL CONTAMINATION THAT'S MOVING OFF SITE AS WELL AS THE AMOUNT OF FILL THAT WOULD BE NEEDED TO BRING IN TO THE SITE.
WE'LL BE DOING A CUT FILL BALANCE AS WE GO TO OPTIMIZE THAT SOLUTION.
WITH THE SITE UTILITIES, WE HAVE UTILITIES ALONG THE FRONTAGE OF THE PARK SO WE DIDN'T NEED TO DO A LOT OF EXPANSION.
WE HAVE WATER SERVICE BEING BROUGHT INTO THE PARK FOR BOTH A NEW FIRE HYDRANT AT THE PARKING LOT AND THE FIRE SERVICE ALL THE WAY UP TO THE RESTROOM CONCESSION BUILDING AND A SEPARATE TWO INCH DOMESTIC SERVICE TO COME UP TO THE BUILDING.
THE SANITARY SERVICE, THERE IS CURRENTLY A MANHOLE WITH A STUB THAT REACHES OUT TOWARDS THE PARK PROPERTY, SO WE'RE ABLE TO CONNECT TO THAT.
THE SANITARY MAIN IN THIS AREA IS VERY VERY DEEP, SO TO AVOID DISRUPTION TO THE EXISTING ROAD, WE'RE GOING TO USE THAT STUB BECAUSE IT'S AT A SHOWER ELEVATION AND DOESN'T REQUIRE CONSTRUCTION OUT INTO THE ROADWAY.
THEN WE'LL CONNECT TO THAT, BRING A SANITARY MAIN INTO THE SITE, CONNECT BOTH THE BUILDING AND THE DISCHARGE FROM THE AQUATICS FACILITY INTO IT.
MORE EXCITING THAN THAT, I WANT TO TALK A LITTLE BIT ABOUT THE MULTIPURPOSE FIELDS.
THIS IS SOMETHING THAT WE HAVE SOME EXPERTISE IN.
WE'VE WORKED WITH PRDC AS JOE SAYS FOR OVER 30 YEARS.
MUCH OF IT IN THE ARTIFICIAL TURF SPACE WE'VE DONE PROBABLY OVER 30 FIELDS PERSONALLY.
THESE ARE A MODERN MIRACLE WHEN IT COMES TO GETTING THE MAXIMUM USE OUT OF THE SPACE THAT YOU HAVE.
THEY LOOK SIMPLE FROM THE SURFACE, BUT THEY DO HAVE SOME COMPLEXITIES UNDERGROUND, INCLUDING THE BUILD UP OF THE VARIOUS LAYERS OF BOTH THE INFILL AND UNDERGROUND ROCK DRAINAGE LAYERS SO THAT THEY FUNCTION IN A RAIN CONDITION, BUT ALSO SAFELY FOR YOUR KIDS TO PLAY ON.
LIKE I SAID, WE'VE DONE DOZENS OF THESE OVER THE YEARS AND I CONSULT WITH OTHER CITIES TO SELECT AND AND SPECIFY THESE FIELDS AS WELL.
JUST TO GIVE YOU AN IDEA OF WHAT IT LOOKS LIKE GOING INTO THE GROUND, THESE ARE PICTURES.
IF YOU LOOK CLOSELY THESE PICTURES FROM 2006, IT'S HOW LONG WE'VE BEEN INVOLVED IN THIS SPACE.
THIS IS ACTUALLY IS THE STADIUM AT FIU, WHICH WE REDID THE FIELD BACK IN 2006 THERE WITH JOE HERE AT RDC.
BUT YOU CAN SEE THERE'S A LOT OF CONSTRUCTION HAPPENING UNDERGROUND WITH PIPING, ROCKS, SOME FLAT DRAINS THAT GO UNDER.
I WOULD ADD THAT WE ALSO DID YOUR FIELD NUMBER FOUR AT SPORTS PLEX, IS ALSO A FIELD TURF LIKE THIS. IT IS A COMPLEXITY.
THERE ARE VERY FEW ENGINEERS AROUND THAT KNOW HOW TO DO IT.
I WOULD VENTURE TO SAY A FEW THAT HAVE DONE AS MANY AS WE HAVE.
WITH THAT, I'D LIKE TO TURN IT OVER.
>> HELLO, LUKE SARON, PROJECT ARCHITECT.
THE CONCESSION STAND AND ALL THE FEATURES THAT ARE DONE WITHIN THIS BUILDING ARE SET IN RELATION TO THE DIFFERENT FEATURES IN THE PARK, NOT QUITE IN THE CENTER, BUT IN ITS PRACTICAL USE FROM ONE PIECE TO THE NEXT.
HERE IS MY BEST INTERPRETATION OF EVERYTHING THAT WAS LISTED IN THE DESIGN CRITERIA PACKAGE, ALL IN ONE BUILDING, GIVING YOU EVERYTHING THAT YOU COULD POSSIBLY NEED.
HERE'S A DIAGRAM THAT DEPICTS THE SITE ITS PROXIMITY TO THE SPECIFIC FEATURES IN THE PARK.
[01:20:03]
ONE IN RELATIONS TO THE RESTROOMS, TO THE PLAYGROUNDS AND SPLASH DECK.BUT AS WELL, THE CONCESSION IN VIEWS TO THE FIELDS AND FITNESS AREAS.
THE COLOR WAS A LITTLE DIFFERENT.
I HAD SOMETHING ELSE ON MY MIND THAT DAY, BUT IT'S TO BE DECIDED BY THE CITY OF TAMARAC.
WHO'S NEXT? IS ANYONE FOR THIS? YES.
>> THANK YOU, WHEN IT COMES TO SPLASH DECK.
WE HAVE DONE IN EXCESS OF 20 SPLASH DE X.
THIS IS A VERY NICE LARGE SPLASH DECK.
RDC IS A DESIGN BUILD CONTRACTOR LED DESIGN BUILDER, BUT WE'RE ALSO A LICENSED COMMERCIAL POOL CONTRACTOR.
WE BUILD THE ACTUAL FACILITIES.
WE BUILT 20 OF THESE OURSELVES WITH OUR OWN FORCES.
WE USE AQUI DYNAMICS AS OUR AQUATIC ENGINEER, AND COMPACT FILTRATION IS THE EQUIPMENT MANUFACTURER, AND THESE ARE ACTUALLY THE PICTURES ARE FACILITIES THAT WE HAVE BUILT.
JUST TO SHOW YOU THAT THIS IS NOT SOMETHING THAT YOU WANT TO LEARN ON, THOSE ARE THE TWO EQUIPMENT VAULTS THAT BELONG TO THE SPLASH PAD.
THESE ARE THESE ARE WIFI ENABLED.
THEY ARE VERY COMPLEX, AND THIS IS NOT SOMETHING THAT YOU WANT TO HAVE SOMEBODY LEARN ON. BRIAN?
>> GOOD AFTERNOON. NAME IS BRIAN WELL, ARCHITECTURAL ALLENS LANDSCAPE.
WE'RE WORKING WITH RDC ON THIS PROJECT.
AS YOU KNOW, THE PARK CALLS FOR MULTIPLE USES THROUGHOUT.
ONE OF THE ONES THAT SPLASH PAD, BASKETBALL COURT, SLASH PICKLEBALL COURT, FITNESS AREA, MULTI CONCRETE PATH, THE CONCESSION STAND, SOME PICNIC AREAS, THE TURF PURPOSE FIELD, AND ALL THE LANDSCAPE AND NEGATION IN SIT LIGHTING.
FIRST, ONE THAT WE WANTED TO TOUCH BASE ON WAS THE PLAYGROUND, AND IT'S GOING TO BE SHADED.
WE ALSO ARE ANTICIPATING SPLITTING IT IN TWO THAT WAY YOU HAVE THE DIFFERENT AGE GROUPS ON EACH SIDE AND THEN IT GIVES, THEN BECOMES A COLORFUL AND VIBRANT AREA TO HELP PROMOTE INTERACTIVE PLAY THAT IS CHALLENGING, AND EXCITING FOR ALL THE AGE GROUPS TO USE.
WE ALSO HAVE A COVERED FITNESS EQUIPMENT CENTER.
IT'S OFF THE LOOP WALKING PATH AND WE ALLOW OPPORTUNITY FOR WELLNESS WITH STATIONS FOR STRENGTH, FLEXIBILITY, CARDIO, INVITES EVERYONE TO USE IT TEENS AND SENIORS TO STAY ACTIVE IN A FRESH AIR ENVIRONMENT.
WE ALSO HAVE PICNIC SHELTER, WHICH IS ALSO ON THE LOOPED WALKING TRAIL AND THIS PROVIDES SHADED SPACE FAMILIES TO GATHER AND HAVE PICNICS.
THEN ALSO GIVING A WAY THAT YOU COULD ALSO POSSIBLY GET OUT AND RENT A SPACE THAT YOU COULD COME AND RENT THE SPACE OUT FOR EVENTS, BIRTHDAYS, THINGS LIKE THAT.
THE PARKS MULTI PURPOSE TRAILS EIGHT FOOT WIDE.
IT'S LOOPS AROUND THE ENTIRE PARK.
WE ALSO HAVE RESPITE STATIONS THROUGHOUT WITH BENCHES, SHADED AREAS AS WELL.
THIS LOOP BIKE PATH ALSO GIVES ACCESS TO ALL THE VARIOUS AMENITIES WITHIN THE PARK, THE DOLL PARKS, THE SLASH PAD, THE FITNESS, THE PLAYGROUND, AND THE MULTIPURPOSE FIELDS AS WELL.
WE'LL HAVE LIGHTED PATH WITH LED COLOR CHANGING LIGHTS THAT ARE WIFI ENABLED.
THE NEXT IS GOING TO THE LANDSCAPE.
DESIGNED FLORIDA FRIENDLY LANDSCAPING, USE NATIVE AND CLIMATE APPROPRIATE PLANT MATERIALS THAT REQUIRE LESS WATER.
THESE PLANTS WILL BE ARRANGED IN THOUGHTFUL GROUPINGS, CREATE MICROCLIMATES, AND SPECIALIZED HABITATS, INVITING LIKE BIRDS, BUTTERFLIES, POLLINATORS, AND JUST OFFERING UP UNIQUE AREAS AND INTERESTS THROUGHOUT THE PARK.
ALSO TO ENSURE LONG TERM HEALTH OF THE PLANTS WE'VE TALKED ABOUT THE SOIL REMEDIATION AND AMENDMENT TO IT, THUS GIVING YOU AN INVESTMENT INTO THE LANDSCAPE TO HELP PROMOTE LONG TERM GROWTH.
THE LAST THING I WANT TO TALK ABOUT WAS WOULD BE THE IRRIGATION SYSTEM WE'RE PROPOSING WOULD BE A HIGH EFFICIENT, LOW TRAJECTORY IRRIGATION HEADS, HELP WITH WATER USAGE AND SAVE.
[01:25:01]
AS MOST ENVIRONMENTS, USING MORE AND MORE WATER, WE'RE GOING TO TRY TO USE LESS WATER AND WITH THE NATIVE PLANT MATERIAL, SHOULD BE ABLE TO DO THAT, ESPECIALLY WITH THE HIGH EFFICIENCY LANDSCAPE IRRIGATION HEADS.>> YOU GUYS HAVE ABOUT 4.5 MINUTES.
>> THANK YOU. THIS SCHEDULE READS AS 640 DAYS TO COMPLETION, 600 TO SUBSTANTIAL COMPLETION.
WE KNOW HOW LONG IT'S GOING TO TAKE TO GET THROUGH BROWARD COUNTY, THE ENVIRONMENTAL ISSUES, SO WE'RE NOT GOING TO SAY THAT WE CAN GET IT DONE EARLY BECAUSE WE KNOW THAT IT CAN'T HAPPEN.
WE HAVE AN AGGRESSIVE SCHEDULE, BUT IT'S A SCHEDULE THAT CAN BE MET AND WILL BE MET.
WE KNOW THAT THE PROJECT IS SIGNIFICANTLY OVER BUDGET.
WE DIDN'T CHANGE OUT ANYTHING.
WE DIDN'T GIVE YOU AN ALTERNATIVE MATERIAL.
WE GAVE YOU EXACTLY WHAT YOU ASKED FOR.
BUT WITH THAT BEING SAID, THERE ARE SAVINGS VE OPTIONS, AND WE ARE CERTAINLY WILLING TO NEGOTIATE WITH THE CITY TO MAKE THIS PROJECT HAPPEN.
THIS IS A VERY NICE PARK RIGHT AROUND THE CORNER FROM OUR OFFICE, WE WOULD LOVE THE OPPORTUNITY TO WORK WITH THE CITY.
WHY SELECT RDC? WE ARE A LOCAL PROVEN DESIGN BUILD FIRM WITH EXTENSIVE EXPERIENCE.
WE HAVE A RICH HISTORY WORKING WITH THIS DESIGN BUILD TEAM.
WE ARE A FISCALLY CONSERVATIVE FIRM.
TOP MANAGEMENT WILL BE INVOLVED THROUGHOUT THE PROJECT, MEETING MYSELF, AND AN EXCEPTIONAL VALUE.
WE COMPLETE ALL OUR PROJECTS WITH OUR OWNERSHIP VERY HAPPY.
WE HAVE THE CAPACITY, THE EXPERIENCE, AND THE EXPERTISE TO BRING THIS PROJECT TO COMPLETION FOR YOU.
THANK YOU. IF THERE'S ANY QUESTIONS AND WE'RE EARLY.
>> COMMISSIONER BOLTON? NO. YOU THINGS TURNED OVER.
>> NO. COMMISSIONER WRIGHT? NO?
>> [OVERLAPPING] DID I MISS THE PRICING? DID I MISS IT?
>> CAN YOU GO BACK? WHAT I EXPLAINED WAS THAT WE KNOW THAT THE PROJECT IS OVER BUDGET, BUT THIS IS A COMPLETE PROPOSAL.
WE DIDN'T CHANGE YOUR SPECIFICATIONS.
WE GAVE YOU EXACTLY WHAT YOU ASKED FOR.
BUT WE'RE ALSO SAYING THAT THERE ARE SAVINGS, THERE ARE VE OPTIONS, AND WE WOULD LIKE THE OPPORTUNITY TO NEGOTIATE WITH THE CITY FOR THE PROJECT TO TRY TO BRING IT CLOSE TO YOUR COST.
>> THANKS. I SEE IT. I GOT IT. THANKS.
>> ONE WOULD BE A DEFINITION OF VE.
>> WELL, VALUE ENGINEERING, EVERYBODY PRETTY MUCH KNOWS WHAT THAT IS.
BUT MAYBE NOT VALUE ENGINEERING, BUT IS THERE SAVINGS THAT CAN BE HAD? IS THERE SOMETHING THAT WE CAN OFFER TO YOU THROUGH A NEGOTIATION, THROUGH DISCUSSION THAT SAY, I DIDN'T UNDERSTAND THAT WAS WHAT YOU MEANT, AND WE CAN SAVE MONEY THAT WAY.
VALUE ENGINEERING, THANKS, I POINTED OUT.
WE DID INDICTATE, SPLASH PADS AND DIFFERENT THINGS IN THE PART, BUT WE DIDN'T DISCLOSE THE TYPE OF MATERIAL, ETC.
I THINK THERE'D BE A LOT OF GROUND TO NEGOTIATE THOSE ELEMENTS.
>> THANK YOU. I DO HAVE A FEW COMMENTS BECAUSE I WAS TOLD I'M NOT ALLOWED TO ASK YOU A CERTAIN THINGS.
CONCERNED IF YOU TURN BASKETBALL INTO PICKLEBALL COURTS FOR THE DISTANCE BETWEEN THE HOMES, BECAUSE THE DECIBEL IS 0-140 AND AT 80% AND 60% DECIBEL, YOU CAN REALLY DO SOME DAMAGE.
THERE ARE SOME HOMES THAT ARE WITHIN 300 SOMETHING FEET.
JUST KEEPING THAT IN MIND IF THERE SHOULD BE ANY DISCUSSION AND CHANGE BECAUSE MY UNDERSTANDING IS WE WON'T BE A PART OF THAT UNTIL MAYBE THE END.
THE DOG PARK, I DON'T KNOW THE FEATURES, BUT A DOGGIE POOL.
THEN WHEN YOU TALKED ABOUT REMEDIATION, YOU GAVE US NUMBERS.
IT'S UP TO 5.5 OR WHATEVER THE COUNTY WANTS, PERSONALLY, I THINK IT WOULD BE BETTER TO NOT GO TO THE LOWEST THAT YOU'RE ALLOWED TO OR THE HIGHEST THAT YOU'RE ALLOWED TO GO DOWN.
I WANT AT LEAST A PERCENTAGE POINT DOWN IF FEASIBLE BECAUSE THIS WAY, WE KNOW IT'S TAKEN CARE OF.
OUT OF THE SHADE STRUCTURES FOR THE PARK, I'M HOPING THAT THEY ARE OF HIGH QUALITY AND NOT HAVE TO HAVE ANY WORRIES ABOUT MAINTENANCE THAT WE'VE HAD WITH ONE OF OUR OTHER PARKS.
THEN WHILE I THINK THE LIGHTS AND WIFI ARE NICE AT NIGHT, IF WE'RE NOT OPENING OUR PARKS AT NIGHT, MAYBE WE NEED TO KEEP SOME OF OUR PARKS OPEN A LITTLE BIT LATER.
[01:30:02]
THAT'S JUST A COMMENT. I'M IN MY FOUR MINUTES, AND YOU GUYS ARE ALL DONE.THANK YOU VERY MUCH. CITY MANAGER.
>> I HAVE A GENERIC QUESTION RELATED TO WHAT YOU WERE SAYING TOO.
WE TALK ABOUT THESE SPLASH PADS AND YOU'RE SAYING IT'S COMPLICATED. THEY ARE.
WHY ARE WE HAVING SO MUCH PROBLEMS WITH OUR SPLASH PADS? WHAT MAKES THIS SPLASH PAD BETTER THAN THE OTHER? WHAT ARE SOME OF THE ELEMENTS THAT WE SHOULD BE LOOKING FOR? THAT'S GOING TO MAKE A LITTLE BIT MORE LONGER LASTING RATHER THAN.
>> WELL, FIRST HIRE US TO BUILD IT FOR YOU.
>> YOU WALKED INTO THAT ONE. [LAUGHTER]
>> THANK YOU VERY MUCH FOR THAT, SOFTBALL.
IT'S A LOT OF IT'S IN THE DESIGN, A LOT OF IT'S IN THE MANUFACTURING, THE EQUIPMENT THAT YOU'RE USING, AND QUITE HONESTLY.
>> WHAT IS THE EQUIPMENT? IS IT THE PUMP? IS IT THE VALVE?
I WISH I HAD A PICTURE OF WHAT IT LOOKS LIKE WHEN THERE'S NO DIRT OVER ALL THE PIPES.
IT IS LITERALLY MILES OF PIPING.
EACH FEATURE, LET ME SEE IF I CAN GO BACK.
>> ALL THOSE NOZZLES. [OVERLAPPING]
>> ALL THOSE NOZZLES GO BACK TO A VALVE AND THAT VALVE HAS TO BE ACTUATED SO THAT IT TURNS ON AND OFF AT A CERTAIN TIME.
ALL OF THAT, THOSE ARE NOT THE SAME, THOSE ARE TWO DIFFERENT TANKS, AND THERE'S A THIRD TANK THAT HAS THE WATER IN IT.
THERE'S REALLY THREE TANKS AND THEY'RE BIG BECAUSE THERE'S A LOT OF VOLUME OF WATER THAT HAS TO MOVE FROM THE TANK TO THE FEATURE AND THEN IT'S INTRANSIT AS WELL.
THERE'S FILTERS BECAUSE THIS IS DRINKING QUALITY WATER.
IF A CHILD WAS TO OPEN HIS MOUTH AND STICK HIS HEAD UP, THAT WATER IS GOING TO GO DOWN HIS THROAT AND HE'S GOING TO DRINK IT.
THAT WATER HAS BEEN FILTERED, ALTERNATED.
>> ON THAT NOTE, CAN I ASK A QUESTION?
>> OUR COMPETITION WE PERFORM ALL THE AQUATIC WITH OUR OWN MECHANICS WHO ARE ON OUR PAYROLL 12 MONTHS A YEAR.
>> IS THERE A DIFFERENCE BETWEEN A SPLASH PAD THAT HAS THE THING THAT GOES OVER AND DUMPS ON, BIG KIDS BECAUSE SOME OF US REALLY LIKE THE SPLASH PADS OR THE ONE THAT JUST HAVE THE LITTLE SHOOT UPS AND THEN GO BOUNCING AROUND AND PEOPLE RUN THROUGH IT.
IS THERE A DIFFERENCE IN PUTTING IT TOGETHER?
>> THIS ONE HAS IT, OR YOU CAN LOOK ON YOUR SCREEN.
IT HAS OCTOPUSES THAT SQUARE IT UP, BUT IT DOES HAVE A BUCKET THE TIPS.
IT'S GOT A BUNCH OF DIFFERENT FEATURES.
THE BUCKET WILL FILL, AND AT A CERTAIN TIME IT TIPS, GOES ON A ROOF OR SOME SORT, AND THEN IT SPRAYS EVERYBODY.
THAT IS A FEATURE THAT WE ADDED.
>> I UNDERSTAND BUT IS THERE A DIFFERENCE IN PUTTING IT ALL TOGETHER BY HAVING SOMETHING THAT BUCKETS AND FILLS OR ONE THAT JUST, ATLANTA WHEN THEY HAD THE OLYMPICS THERE, AND JUST SHOOTS UP WATER AND YOU JUST JUMP BETWEEN IT. [OVERLAPPING] IS THERE A DIFFERENCE?
>> MUCH DEEPER TO DO IT THAT WAY.
THIS IS NOT AN INEXPENSIVE THING.
>> THANK YOU VERY MUCH. APPRECIATE YOUR TIME.
WE WE'LL RECESS UNTIL 1:50 PM WHILE WE EXCHANGE PARTICIPANTS OR APPLICANTS. THANK YOU.
>> LADIES AND GENTLEMEN, WELCOME BACK AT THIS 2:00 PM, AND WE ARE ON OUR FOURTH PRESENTER, MR. STEWART.
>> GOOD AFTERNOON, AND WELCOME.
AS IT WAS DISCLOSED TO YOU IN A NOTIFICATION YOU RECEIVED.
YOU GUYS BE GIVEN 20 MINUTES TO PRESENT YOUR PROPOSAL TO THE CITY COMMISSION, AFTER WHICH POINT THE COMMISSION WILL HAVE 20 MINUTES ASK SOME QUESTIONS.
THEN WE'LL GO AHEAD AND JUST WRAP THINGS UP AFTER THAT.
WITH THAT BEING SAID, 20 MINUTES, THE COUNT WILL BE RIGHT HERE. GO AHEAD AND BEGIN.
>> MADAM MAYOR, COMMISSIONERS, MR. MANAGER. I JUST WANT TO SAY THANK YOU VERY MUCH FOR ALLOWING US TO PRESENT TODAY.
THIS IS A REAL PRIVILEGE TO DO THIS.
I WAS JUST LOOKING AT YOUR WEBSITE AND YOUR MISSION SAYS, "THE CITY OF TAMARAC MISSION IS TO FOSTER AN ENVIRONMENT OF EXCELLENCE BY WORKING AS A TEAM, ACHIEVING RESULTS, MAKING A DIFFERENCE AND CREATING AND INNOVATING AND RESPONDING TO THE CUSTOMER.
AT FRANJO WE COULDN'T SAY IT ANY BETTER.
WE FEEL THAT OUR CULTURE MATCHES PERFECTLY WITH THE CITY OF TAMARAC, AND WE'D LOVE TO WORK WITH YOU. NEXT SLIDE.
WE'RE GOING TO WALK RIGHT THROUGH THIS AGENDA, WHY THE FRANJO TEAM, OUR TEAM QUALIFICATIONS, OUR PROJECT UNDERSTANDING AND APPROACH, OUR BUDGET AND SCHEDULE REVIEW, AND THEN WE'LL CIRCLE BACK TO WHY THE FRANJO TEAM.
[01:35:01]
OF ALL THE TEAMS THAT HAVE PRESENTED TO YOU, WE FEEL THAT WE HAVE THE BEST VALUE OF ALL THE TEAMS. THAT'S NOT JUST PRICE WISE.BRINGING BACK TO THIS COMMUNITY EXACTLY WHAT IT DESERVES IN THIS PROJECT.
WE BELIEVE IN COMMUNITY ENGAGEMENT ON THE DESIGN AND THROUGHOUT CONSTRUCTION.
WE BELIEVE THAT IT'S AN INTERACTIVE PROCESS.
FRANJO'S DESIGN PROCESS ENSURES THE CITY GETS EXACTLY WHAT IT DESERVES AND WHAT IT WANTS.
WE BELIEVE THAT WE HAVE THE BEST ABATEMENT PLAN AND THE BEST ABATEMENT PROFESSIONALS ON THE TEAM.
SOME OF THE MUNICIPALITIES THAT OUR TEAM MEMBERS HAVE WORKED WITH.
THERE'S OVER 30 OF THEM LISTED HERE, FROM HALLANDALE BEACH TO DORAL, HOLLYWOOD, DORAL, MIRAMAR.
WE HAVE PARK PROJECTS THROUGHOUT SOUTH FLORIDA, AND WE'LL BE TALKING ABOUT THOSE HERE.
WHAT YOU SEE UP HERE IN THE LEFT HAND CORNER.
I'VE WORKED WITH JAMES BEFORE.
I'VE WORKED WITH ALEX FENECH HDG ON THESE PROJECTS HERE ALONG WITH CLIFFORD MOORE.
TOM, OUR SUPERINTENDENT, RIGHT BACK HERE, HAS WORKED WITH JAMES AND HE'S WORKED WITH OTHERS ON A TEAM, RON FOR MANY YEARS.
OUR TEAM IS NOT A GROUP OF AMATEURS, WE'RE VETERAN PARK BUILDERS.
WHAT YOU SEE HERE IS THE EXTENSIVE TEAM WE'VE BROUGHT.
NOW, JUST BECAUSE IT'S BIG DOESN'T MEAN IT'S EXPENSIVE AS WE SHOWED WITH OUR VALUE PROPOSITION.
WHAT WE HAVE HERE IS EXPERTS WHO WILL INTERJECT THEIR EXPERTISE AT EXACTLY THE RIGHT MOMENT ON THE PROJECT.
WE ARE THE LEAD FRANJO BUILDERS, ALEXANDER & JOHNSON ARE OUR GENERAL CONTRACTOR PARTNERS.
WE'VE ALREADY ENGAGED THEM AS OUR PARTNER ON SITE CIVIL.
HITCHCOCK DESIGN IS OUR LANDSCAPE ARCHITECT.
NETA ARCHITECTS IS OUR VERTICAL ARCHITECT.
UES IS OUR ENVIRONMENTAL & GEOTECH ENGINEERING ABATEMENT, CONEMCO STRUCTURAL, FLYNN, JOURNEY C&D GROUP IS ON OUR PLAYGROUND EQUIPMENT, AND ALSO SOME OUTREACH.
THEN WE HAVE OUR COMMUNITY DEVELOPMENT AND BENEFITS PROGRAM. TURN IT OVER TO WYATT.
I'D LIKE TO GO THROUGH THE CHART A LITTLE BIT TO SHOW YOU HOW THIS IS ALL PUT TOGETHER WITH THE TEAM BEHIND.
I'M OVERSEEING THE WHOLE TEAM FROM THE BACKGROUND, BUT THE TEAM WE PUT TOGETHER IS GOING TO MAKE THAT VERY EASY FOR ME.
ON THE CONSTRUCTION SUPPORT SIDE, WE HAVE JIM AULD, WHO WE'VE MET, WHO'S LEADING THAT WITH DARLENE, ESTIMATOR WHO HELPED PUT TOGETHER THE NUMBERS FOR YOU.
GEORGE, AND CLIFFORD, AND JAMES ARE GOING TO WORK ON THAT CONSTRUCTION SUPPORT AS WELL.
RON HASKO, OUR PROJECT EXECUTIVE WILL BE LEADING THE TEAM FROM THE CONSTRUCTION STANDPOINT.
WELL AS TOM FOWLER, OUR GENERAL SUPERINTENDENT WHO WILL OVERSEE OUR ONSITE PROJECT TEAM BUILDING IT.
THEY WILL ALSO BE DOING THE COORDINATION WITH ALEX FENECH AND HIS TEAM FROM HITCHCOCK DESIGN GROUP, WHO WILL OWN THE DESIGN TEAM UNDERNEATH THEM TO HELP BRIDGE THAT GAP BETWEEN DESIGN AND MEANS AND METHODS TO GET THIS PERMITTED CORRECTLY AND BUILT TO FINALIZED DESIGN.
AT FRANJO WE BELIEVE IN CREATING OPPORTUNITIES IN THE COMMUNITY.
WE'VE BROUGHT ON SOME LOCAL CONTRACTORS AND WE INTEND TO BRING ON MORE LOCAL CONTRACTORS THROUGHOUT THE PROCESS.
WE HAVE THE BEST ENVIRONMENTAL CONSULTING SERVICES GROUP, AND CONEMCO ENGINEERING IS ALSO A SMALL LOCAL FIRM.
NEXT. SOME OF OUR DESIGN EXPERIENCE, ALEX?
>> YES. AS JIM MENTIONED, MY NAME IS ALEX FENECH.
I'M THE MANAGING PRINCIPLE OF HITCHCOCK DESIGN GROUP, THE TEAMS LANDSCAPE ARCHITECT AND LEAD DESIGNER.
THANK YOU FOR YOUR FLEXIBILITY IN ALLOWING ME TO ZOOM IN REMOTELY.
I HAD SOME PREVIOUSLY SCHEDULED TRAVEL THAT I COULDN'T AVOID.
AS JIM AND WITTY MENTIONED, WE ARE BASED IN CORAL SPRINGS, AND WE HAVE A NATIONALLY RECOGNIZED TRACK RECORD OF AWARD WINNING PARKS AND RECREATION EXPERIENCE THAT WE'VE SUCCESSFULLY BUILT AROUND THE COUNTRY.
THESE PROJECTS RANGE IN SCALE AND SIZE AND COMPLEXITY FROM SMALL PASSIVE PARKS TO LARGE REGIONAL RECREATION AND ATHLETIC COMPLEXES AND EVERYTHING IN BETWEEN, AND SO AS YOU CAN SEE ON THE SCREEN, WE'VE GOT SMALL PASSIVE PARKS, WE'VE GOT THEMED PLAYGROUNDS, SLASH PADS, AND ALL THE THINGS THAT THE COMMUNITIES THAT WE WORK WITH ARE REQUIRING, WE'RE ABLE TO WORK WITH.
IF YOU GO TO THE NEXT SLIDE. LOCALLY, WE'RE WORKING ON SEVERAL PROJECTS HERE IN SOUTH FLORIDA.
I WANT TO TALK SPECIFICALLY ABOUT EL PRADO PARK, WHICH IS IN LAUDERDALE-BY-THE-SEA.
WE'RE USING OUR NATIONAL EXPERIENCE TO MAKE AN IMPACT LOCALLY THROUGH A VERY PURPOSEFUL AND STANDARDIZED COMMUNITY ENGAGEMENT PROCESS.
WE'VE DEVELOPED THIS PROJECT, WORKING WITH THE COMMISSIONERS, WORKING WITH THE STAFF, AND WORKING WITH THE RESIDENTS THROUGH A VERY PURPOSE DRIVEN DESIGN ENGAGEMENT PROCESS TO MAKE IT, SO THIS PARK IS COMING FROM THE COMMUNITY RATHER THAN COMING FROM US.
IT'S BEEN A REALLY FUN PROCESS AND SOMETHING THAT WE FELT A LOT OF VALUE IN TO DOING RATHER THAN JUST CREATING SOMETHING IN A VACUUM.
WE'VE EXECUTED THIS PROCESS SUCCESSFULLY ON MULTIPLE PROJECTS, AND WE'RE EXCITED TO WORK WITH YOU HERE AT STABLE HOME PARK. NEXT SLIDE.
THIS MAY BE ONE THAT YOU'RE FAMILIAR WITH,
[01:40:01]
BUT WE'RE ALSO WORKING WITH THE CITY OF FORT LAUDERDALE AND INTER MIAMI ON THE FORT LAUDERDALE COMMUNITY PARK.CHANGED HANDS SEVERAL TIMES, BUT WE'RE HAPPY TO SAY THAT WE ARE THE LANDSCAPE ARCHITECT THAT'S GOING TO BE HELPING MOVE THAT PROJECT FORWARD.
ALSO AT BIG CYPRESS RECREATION CENTER, A PROJECT OUT IN BIG CYPRESS SEMINOLE INDIAN TRIBE.
HERE'S JUST A SAMPLE OF SOME OF THE OTHER PROJECTS THAT ARE NOTABLE THAT WE FELT RELEVANT TO SHARE WITH YOU THAT WE'VE WORKED ON WITH SIMILAR EITHER SIZE OR BUDGET OR PROGRAM, AND THINGS THAT WE CAN BRING TO THE TABLE AGAIN WITH THAT LOCAL INFLUENCE THAT WE'RE EXCITED TO BE A PART.
>> WHAT YOU SEE HERE IS ONE OF OUR CURRENT PROJECTS AT FRANJO.
IT'S OVER $30 MILLION, BUT THE SITE WORK PACKAGE IS VERY SIMILAR TO WHAT WE HAVE TO DEAL WITH AT SABAL PALM PARK.
THERE'S ENVIRONMENTAL CONCERNS.
IT'S A LARGE SITE PROJECT, AND SIGNIFICANT CIVIL WORK THE SAME WAY AS WE'VE DEALT WITH THIS PROJECT, WE'LL DEAL WITH SABAL PALM.
>> GOOD AFTERNOON. MY NAME IS JAMES ALEXANDER.
I'M THE GENERAL CONTRACTOR AND SITE CIVIL CONTRACTOR BY ALEXANDER AND THE OWNER OF ALEXANDER & JOHNSON.
MY FIRM BRINGS ABOUT 20 YEARS OF EXPERIENCE IN BUILDING PARKS DEVELOPMENT.
SITES AND MITIGATING SOLES PRIOR TO CONSTRUCTION.
WE SUCCESSFULLY COMPLETED MULTIPLE MUNICIPALITIES AND PARKS, UNDER BUDGET AND AHEAD OF SCHEDULE.
I PERSONALLY LED THE CONSTRUCTION OF SEVERAL PARKS AND I WILL BE HAPPY TO SHARE MY KNOWLEDGE AND EXPERIENCE TO SUPPORT YOUR PROJECT WITH FRANJO BUILDERS.
>> JAMES AND I, WE WERE IN HALLANDALE BEACH IN 2012 WHEN WE BUILT BF JAMES PARK, JOSEPH SCAVO, SOUTH CITY BEACH PARK, AND OB JOHNSON.
THESE ARE ALL PARKS THAT WE'VE WORKED TOGETHER FOR YEARS.
WE'RE NOT JUST THROWING TOGETHER A TEAM HERE.
AS I SAID BEFORE, WYATT IS 22 YEAR VETERAN OF THE INDUSTRY.
HE'S LET OUR OFFICE. HE'S OUR SENIOR VICE PRESIDENT OF THE FLORIDA REGION, AND HE BRINGS A WEALTH OF EXPERIENCE.
I'VE ALREADY INTRODUCED MYSELF, RON, AGAIN, 26 YEAR VETERAN, AND TOM FOWLER TURNED 62 DAYS AFTER I DID.
I CALL HIM JUNIOR. OUR OFFICE IS JUST 14 MILES FROM YOU.
WE'RE VERY HAPPY TO BE THAT CLOSE, AND WE'RE GOING TO BE ON SCENE AND WE'RE GOING TO BE VERY VISIBLE IN THE CITY. CLIFF.
>> THANKS, JIM. WE TALKED ABOUT THE COMMUNITY ENGAGEMENT, AND SO JIM TALKED ABOUT HOW WE BUILT PARKS IN HALLANDALE.
IT REMINDS ME OF A STORY OF A SUBCONTRACTOR, HIS NAME WAS PAUL A. JACKSON.
IT WAS A PLUMBING COMPANY. IT WAS HIS FIRST TIME BEING ON A COMMERCIAL PROJECT.
PAUL SHOWED UP IN MY OFFICE WITH A LAPTOP UNOPENED, SO WE UNBOXED IT AND WE SAT DOWN AND I GAVE HIM G702, G703, HIS PAY APPLICATIONS, HIS GENERAL CONDITIONS FOR HIM.
WHEN WE TALK ABOUT ENGAGING WITH THE COMMUNITY AND OUR LOCAL AND SMALL BUSINESSES, WE BELIEVE IN BEING THERE FOR THEM BECAUSE THEIR SUCCESS IS OUR SUCCESS.
>> CLIFF IS ANOTHER PARTNER I'VE WORKED WITH FOR OVER 15 YEARS.
I WANT TO POINT OUT THE FRANJO FOUNDATION.
THE FRANJO FOUNDATION IS AN ORGANIZATION WITHIN OUR COMPANY, WHEREBY WE GIVE BACK TO THE COMMUNITIES IN WHICH WE DO BUSINESS.
IT'S OUR INTENTION, IT'S HOW WE DO IT.
LOOKING BACK, WE SEE IN PRIOR TIMES THAT THOSE WHO HAVE DONE WORK WITH THE CITY HAVE GIVEN BACK AND THAT FITS PERFECTLY WITH WHAT WE DO AS WELL. ALEX.
>> I'M ACTUALLY A RESIDENT OF TAMARAC, AND SO WHEN I GOT THE OPPORTUNITY A CALL FROM JIM TO GET A CHANCE TO WORK ON THIS PROJECT. I WAS REALLY EXCITED.
I'VE BEEN TRACKING THIS PROJECT FOR SEVERAL YEARS, AND I UNDERSTAND, A FEW YEARS AGO THAT THERE WAS A GRANT THAT WAS AWARDED TO THE CITY FOR THIS PROJECT.
DURING THAT PROCESS SEVERAL ITERATIONS OF ST PALM PARK WERE CREATED THAT ARE SHOWN ON THE SCREEN AND WHAT WE WANT TO JUST CONTINUE TO REITERATE IS THAT THROUGHOUT THE RFQ PROCESS, THERE WERE SOME SUGGESTIONS THAT SOME DESIGNS WERE BROUGHT FORWARD.
WHILE WE DID GO THROUGH THAT PROCESS AND WE DID PUT A DESIGN FORWARD.
WE FEEL LIKE FOR WHAT WORKED FOR THE CITY AND WHAT WORKED FOR THAT PARK AND WHAT WORKED FOR THE STAKEHOLDERS THREE YEARS AGO HAS MORE THAN LIKELY CHANGED, AND SO WE WANT TO JUST CONTINUE TO FOCUS ON THE PROCESS THAT WE'RE EXCITED TO BRING FORWARD FOR YOU.
THERE WERE INHERENT VARIANCES IN THE AESTHETIC FUNCTION AND PROGRAMMING OF SOME OF THE PARK DESIGNS THAT WERE SUGGESTED PREVIOUSLY, AND I'M SURE THAT HAVE BEEN SUGGESTED BY SOME OF THE OTHER TEAMS, BUT WE ARE VERY ADAMANT ABOUT WORKING THROUGH THIS PROCESS TOGETHER FROM THE VERY BEGINNING. NEXT SLIDE.
WE UNDERSTAND THE REQUIREMENTS THAT ARE BEING ASKED.
WE KNOW THAT THERE IS A SIGNIFICANT ENVIRONMENTAL CONCERN HERE, AND SO WE PUT TOGETHER A WORLD CLASS ABATEMENT TEAM TO HELP REALIZE THAT CHALLENGE.
THE RECREATIONAL AND ATHLETIC FACILITIES, OBVIOUSLY, CERTAIN COMMUNITY, THINGS THAT ARE ALIGNMENT WITH THE PARKS AND RECREATION MASTER PLAN.
WE WANT TO OVERLAY TO MAKE SURE THAT WE'RE
[01:45:01]
PROVIDING SOME OF THE AMENITIES AND PROGRAMMATIC ELEMENTS THAT THIS PARK FROM THE GEOGRAPHIC LOCATION ARE SITUATED IN.OTHER COMMUNITY AMENITIES AND OBVIOUSLY, THE INFRASTRUCTURE, PARKING, LANDSCAPING, ENVIRONMENTAL PROTECTION THINGS THAT WE WOULD THINK ARE STANDARD IN MOST PARKS ARE SOMETHING THAT WE'RE AWARE OF THAT WE'RE UP TO THE CHALLENGE TO WORK WITH YOU.
AS I MENTIONED, WE DID PUT TOGETHER A CONCEPTUAL DESIGN PROCESS THROUGH THIS RQ RESPONSE AND SOME RENDERINGS AND THINGS LIKE THAT.
BUT THESE ARE REALLY JUST AN INITIAL TAKE ON WHAT IT COULD BE.
WE CERTAINLY ARE EXCITED TO DIVE INTO THE DETAIL TO UNDERSTAND WHAT THE ADJACENT NEIGHBORS TRULY NEED, WHAT THE COMMUNITY TRULY NEEDS, AND WHAT YOU ALL ON THE COMMISSION HAVE IN MIND FOR THIS PART.
THROUGH THAT DESIGN CENTERED PROCESS, WE KNOW THAT THIS IS A REALLY TIGHT SCHEDULE.
I KNOW THAT THAT'S PROBABLY SOMETHING THAT WE'RE ALL TRACKING, BUT WE THINK THAT WE COULD STILL DO THIS THE RIGHT WAY THROUGH COMMUNITY ENGAGEMENT. WE NEED TO LISTEN.
WE NEED TO UNDERSTAND WHAT SOME OF THE NEEDS ARE.
THIS CAN BE THROUGH STRATEGIC COMMUNITY MEETINGS OR IT COULD BE A POP UP EVENTS THAT THE CITY ALREADY HAS SCHEDULED.
WE CAN SHOW UP AND GO THROUGH SOME QUICK ENGAGEMENT EXERCISES.
BUT WORKING TOGETHER WITH THE STAFF AND ALL OF YOU ENGAGING IN SOCIAL MEDIA WEBSITE THINGS ARE ALL THINGS THAT WE CAN DO TO QUICKLY GET A PULSE ON WHAT THE NEEDS TRULY ARE FOR THIS PARK.
ONCE WE GET THAT INPUT AND FEEDBACK, WE WILL WEAVE IT THROUGH A SERIES OF COMMUNICATIONS AND OBVIOUSLY THE DESIGN PROCESS BECAUSE WE WANT TO CREATE A PARK THAT'S NOT JUST SERVING THE NEEDS OF TODAY, BUT THAT IT'S FUTURE FOCUSED THAT GIVES EVERYONE THE NEEDS THAT RESPONDS TO THE NEEDS OF THE PARK.
JIM MENTIONED EARLIER ON THE CITY MISSION AND SOME OF THE GOALS.
THOSE ARE THINGS THAT WE ALWAYS WANT TO OVERLAY IN OUR PROJECTS TO MAKE SURE THAT THAT STABLE PALM PARK WILL BE ADVANCING SOME OF THOSE GOALS, BUT ALSO SPEAKING TO THE MISSION.
THE TYING INTO THE PARKS AND RECREATION MASTER PLAN IS GOING TO BE IMPORTANT THAT WE TAKE THE PROPER STEPS TO DO THAT.
>> GOOD AFTERNOON, EVERYONE. MY NAME IS JONATHAN BULLEY, AND I'M WITH UES, AND I'M THE ENVIRONMENTAL MANAGER FOR BROWARD COUNTY AND MEADE COUNTY REGION.
UES AND MYSELF, WE'RE VERY EXCITED TO BE A PART OF THIS TEAM.
I BELIEVE YOU HAVE AMONGST YOU, A VERY STRONG TEAM TO HELP YOU DEVELOP YOUR PROJECT.
UES IS A NATIONAL PREMIUM ENVIRONMENTAL CONSULTANT FIRM.
WE HAVE OFFICES ACROSS THE COUNTRY.
IN FLORIDA, WE HAVE 15 OFFICES.
WE'VE COMPLETED SEVERAL ENVIRONMENTAL ASSESSMENT AND REMEDIATION PROJECTS IN PARTNERSHIP WITH PUBLIC AND PRIVATE SECTOR PARTNERSHIPS.
WE HAVE REVIEWED CAREFULLY THE SET ASSESSMENT REPORTS AND AGENDA AND GROUND MONITORING REPORTS THAT HAVE BEEN PREPARED FOR THE SITE.
WE DO UNDERSTAND THAT THE SITE IS IMPACTED WITH ARSENIC IN THE SOIL AND THE GROUNDWATER, AND THAT CAME AS A RESULT OF THE HISTORICAL USE OF THE PROPERTY FOR AGRICULTURE AND SUBSEQUENT GOLF COURSE USAGE.
WE WILL USE THE INFORMATION FROM THE SET ASSESSMENT REPORTS AND THE AGENDA TO DEVELOP A REMEDIAL ACTION PLAN AND THE SOIL MANAGEMENT PLAN.
THAT WILL EVALUATE REMEDIAL ALTERNATIVES, AND WE WILL COME UP WITH A COST EFFECTIVE REMEDIAL OPTION IN COLLABORATION WITH THE CITY AND ALSO WITH THE REGULATORY AGENCIES TO MAKE SURE THAT WHATEVER PLAN WE COME UP WITH IS, DOESN'T GET HUNG UP AND DELAYED A PROCESS THAT IT GETS APPROVED TIMELY.
WE WILL COME UP WITH, AS I MENTIONED EARLIER ON, A COST EFFECTIVE REMEDIAL OPTION TO ENSURE THAT WE GIVE THE CITY THE BENEFITS IN TERMS OF THE COST.
SOME OF THE ALTERNATIVES WOULD INCLUDE A COMBINATION OF REMOVING A HEAVILY IMPACTED, SO OUTSIDE DISPOSED A LANDFILL.
IT COULD ALSO INCLUDE THE BLENDING OF THE LESS IMPACTED SAWS WITH OFF CYCLING SAW TO BRING THE CONCENTRATIONS DOWN TO REMEDIAL OBJECTIVE, AS WE UNDERSTAND IT IS TO GET THE SITE CLOSURE WITH ALTERNATIVE [INAUDIBLE] LEVELS OF 5.5 MILLIGRAMS/KILOGRAM.
WE WOULD ALSO CONSIDER THE RELOCATION OF SOME OF THE HEAVILY IMPACTED SAW AND TO AREAS THAT ARE PROPOSED TO HAVE IMPERVIOUS SURFACES, SO THAT THOSE CAN SERVE AS ENGINEERING CONTROLS TO PROTECT THE HUMAN HEALTH AND THE ENVIRONMENT.
TO ADDRESS THE GROUNDWATER IMPACT, WE WILL MONITOR THE GROUNDWATER QUALITY ON A QUARTERLY BASIS.
[01:50:01]
WE WOULD EVALUATE THE TRENDS.THE GOAL IS TO DOCUMENT THE STABILITY OF THE PLUME AND ALSO, ENSURE THAT IT'S NOT LEAVING THE SITE, ENSURE THAT PUBLIC HEALTH AND HUMAN ENVIRONMENT IS ENSURED.
ONCE WE COMPLETE AS PART OF THE REMEDIATION, WE WILL ALSO DO POST CONFORMATION SAMPLING TO MAKE SURE WE GET THE PROPER CLOSURE TIMELY.
SUBSEQUENT TO THE CLOSURE WOULD DEVELOP THE DEED RESTRICTIONS AND GET THE SITE TO CLOSURE. THANK YOU.
>> GOOD AFTERNOON. MY NAME IS RON HASKO, PROJECT EXECUTIVE FOR FRANJO BUILDERS.
I BRING EXTENSIVE EXPERIENCE IN COORDINATING PARKS, INCLUDING CIVIL, STRUCTURAL AND OUTDOOR AMENITIES.
MY TEAM AND MYSELF WILL BE ENSURING THAT WE MAINTAIN FULL ACCESS FOR THE RESIDENTS DURING CONSTRUCTION, WORK WITHIN THE CITY NOISE ORDINANCE, COORDINATE AND IMPLEMENT THE APPROPRIATE AND APPROVED MOT, AND COORDINATE WITH THE CITY WHEN REQUIRED.
I'M TOM FOWLER, GENERAL SUPERINTENDENT.
FRANJO'S FIELD DIVISION FOCUSES ON SITE SAFETY, SECURITY, IN ADDITION TO MAINTAINING YOUR SCHEDULE AND PROVIDING QUALITY FINISHED PRODUCT. THANK YOU.
>> THE HIGH LEVEL SCHEDULE WE PUT TOGETHER BASED ON THE REQUIREMENTS THAT RFP AND DURATIONS, AND THINGS LIKE THAT.
ESSENTIALLY FROM THE NOTICE TO PROCEED, WE GO THROUGH THAT PRE-CONSTRUCTION DESIGN PROCESS TO GET TO THE PERMITTING, AND THEN RUN THROUGH CONSTRUCTION, CRITICAL PATH BEING GETTING TO THAT SITE AND THAT ARSENIC REMEDIATION UPFRONT.
THIS BASICALLY SHOWS THE FULL DURATION IT WAS GIVEN.
WE BELIEVE THERE ARE STILL OPPORTUNITIES TO REDUCE THAT BASED ON POTENTIALLY SOME PHASE PERMITTING TO GET US TO THAT ARSENIC REMEDIATION AND SITE FIRST, AS WELL AS SOME POTENTIAL OPTIONS IN OUR ENGINEERED CONTROLS FOR THAT REMEDIATION.
>> WHAT YOU SEE HERE IS THE BUDGET THAT WE PREPARED.
JUST REPRESENTS, WE'RE HAPPY TO ANSWER ANY QUESTIONS ABOUT IT AFTERWARD.
I WANT TO MOVE INTO THE WRAP UP NOW.
I WANT TO FIRST OF ALL, GO BACK TO JONATHAN FOR A SECOND.
I'VE WORKED WITH UES OVER 35 YEARS NOW, AND THERE IS BAR NONE, NO FINER ABATEMENT CONTRACTOR ENGINEERING COMPANY IN THE WORLD.
WE WERE FORTUNATE ENOUGH TO GET JONATHAN AND HIS TEAM ON BOARD HERE.
WE BRING THE BEST VALUE TO THE PROJECT.
WE BELIEVE THAT THE BEST VALUE IS ACHIEVED THROUGH TEAMWORK WITH YOU AND YOUR STAFF.
WE BELIEVE THAT COMMUNITY ENGAGEMENT IS CRITICAL ON A PARK.
EVERY PARK THAT WE'VE EVER BEEN A PART OF HAS BEEN A COLLABORATIVE PROCESS WHERE WE DON'T JUST GO OFF INTO A ROOM AND COME UP WITH OUR OWN IDEAS.
WE BELIEVE THAT IT'S NECESSARY TO SIT WITH YOU AND WORK THROUGH THE DESIGN.
THAT'S WHAT OUR INTENTION IS TO DO.
THAT'S WHAT WE'RE SELLING YOU TODAY IS A PROCESS.
WITH THAT PROCESS COMES THE BEST PRICE, AND IT COMES WITH THE ABSOLUTE FINEST PROFESSIONALS WORKING FOR YOU, NOT ONLY RENOWNED AROUND THE STATE, BUT AROUND THE COUNTRY.
OUR PROCESS ENSURES THE CITY GETS EXACTLY WHAT IT DESERVES, AND WE HAVE A WORLD CLASS ABATEMENT TEAM WHERE THERE'S NOT GOING TO BE ANY QUESTIONS FROM ANYONE LEFT AT THE END OF THE DAY ABOUT HOW THIS SITE IS HANDLED.
WE TREMENDOUSLY RESPECT THE CITY.
WE VALUE THE OPPORTUNITY TO BE WITH YOU TODAY, AND WE RESPECTFULLY REQUEST THAT YOU AWARD US THE PROJECT.
NOW, I'LL BE HAPPY TO FIELD THE QUESTIONS IF YOU'LL ALLOW ME, I'LL FIELD IT TO THE RIGHT PEOPLE UNLESS YOU WANT TO DIRECT YOUR QUESTIONS DIRECTLY.
>> FROM THE COMMISSION HERE, COMMISSIONER WRIGHT.
>> I NOTICED THAT YOU HAVE A TAMARAC RESIDENT ON YOUR TEAM.
BUT I KNOW A LOT OF RESIDENTS. I DON'T KNOW HIM.
>> ALEX FINCH WAS THE ARCHITECT THAT WAS SPEAKING?
>> YES, HE IS. HE'S A RESIDENT HERE.
>> YEAH. ALEX, DO YOU WANT TO RESPOND TO THAT? WHERE DO YOU LIVE?
I SEE MAT HAD THE PRIVILEGE OF MEETING A FEW OF YOU AT SOME OF THE GROOVE ON THE GRASS EVENTS AND THINGS.
MY WIFE AND I LIVE IN THE WOODMONT COMMUNITY.
WE MOVED INTO TAMARAC IN 2022, AND ABSOLUTELY LOVE BEING A TAMARAC RESIDENT, AND I APOLOGIZE THAT I HAVEN'T HAD THE PRIVILEGE OF MEETING YOU YET.
SO I'M LOOKING FORWARD TO [OVERLAPPING].
>> I'VE MET HIM. PLEASURE. NO OTHER QUESTIONS.
[01:55:05]
I'M GOING TO ASK THIS, IF YOU WOULD [OVERLAPPING].I NOTICED THAT YOUR SLIDE HAD THE PRICE, BUT IN THE PRESENTATION, IT DOESN'T HAVE THE PRICE.
>> YEAH. WE JUST GOT THAT INSERTED AFTER WE HAD JUST PRINTED.
WE WANT TO MAKE SURE WE HAD IT UP HERE, BUT IT'S ALREADY DELIVERED TO YOU.
>> I WAS GOING TO ASK FOR THAT BECAUSE I KNOW COMMISSIONER WRIGHT HAS ASKED FOR ALL FOUR OF THEM JUST TO MAKE SURE I WAS UP THERE, COMMISSIONER WRIGHT.
>> THANK YOU. I'M JUST GOING TO TELL YOU, I'M NOT ALLOWED TO ASK YOU, SO I'M JUST GOING TO SHARE WITH YOU MY ISSUES THAT I HAVE IN GENERAL.
WITH OUR PROPOSAL, WHAT WE'VE ASKED FOR PICKLEBALL.
IF IT'S GOING TO BE PUT IN, IT HAS TO HAVE SOUND DISTANCE, IT HAS TO BE SUFFICIENT ENOUGH THAT FOLLOWS ALL THE REQUIREMENTS BECAUSE WE'RE NOT GOING TO HAVE RESIDENTS COMING AFTER US BECAUSE THEY'RE GOING DEAF OVER THE BANG BANK, THE POP POP POPS, AND THEN NOT BEING ABLE TO ENJOY THEIR HOME.
IF PICKLEBALL DOESN'T MAKE THIS PROJECT, BECAUSE OF DISTANCE, THEN IT DOESN'T MAKE IT.
DOG SPLASH AREA BECAUSE I DON'T SEE IN YOUR PROPOSAL, AT LEAST WHAT WE HAVE HERE.
I DON'T REALLY SEE A FULL DESIGN.
>> BECAUSE I DON'T SEE THAT, I'M JUST GOING TO SHARE.
I ALSO WOULD LIKE TO SEE SOMETHING FOR THE DOGS, LIKE A DOG POOL AREA.
I DON'T EVEN SEE IT IN HERE AS A CONCEPT THAT HAS BEEN DISCUSSED IN YOUR THOUGHTS.
BASICALLY, I ALSO DO SEE THAT YOU HAVE FOR THE WATER FEATURE, IT'S MORE THE SPRAY UP VERSUS A SPLASH PAD TYPE THING.
WE'VE LEARNED THAT THAT'S A LITTLE BIT ON THE PER SIDE, NOT SAYING THAT'S A BAD THING.
JUST SAYING IT'S THE ONLY THING I REALLY NOTICED OUT OF THE PROJECT THAT GOES ALONG WITH EVERYTHING ELSE.
I THINK WE'RE GOOD WITH OUR QUESTIONS, AND PLEASE DON'T TAKE THE WRONG WAY. NOBODY'S ASK QUESTIONS.
I'VE ONLY COMMENTED. LADIES AND GENTLEMEN, BECAUSE I DO SEE YOU HAVE LADIES ON YOUR TEAM.
THANK YOU VERY MUCH FOR BEING HERE.
>> NICE AND SIMPLE. WE DON'T BITE.
>> THAT'S IT? VALUE YOUR COMMENTS.
VALUE YOUR COMMENTS. THANK YOU.
WE WOULD ABSOLUTELY TAKE THOSE INTO ACCOUNT IN THE DESIGN. THAT'S WHAT WE WANT TO DO.
>> FIVE MINUTE BREAK? IS THAT WHAT'S BEING REQUESTED? IS THAT WHAT YOU'RE REQUESTING? DID YOU REQUEST A FIVE MINUTE BREAK OR NO? WE GOOD TO GO.
>> GOOD TO GO. DID YOU HAVE SOMETHING YOU WISH TO SAY CITY ATTORNEY?
>> NO. THE PROCESS. BACK TO YOU, MR. STEWART.
>> THANK YOU GUYS SO MUCH FOR YOUR TIME.
YOU GUYS HAVE HAD A CHANCE TO SEE ALL FOUR PROPOSALS.
IN THE AGENDA PACKET 4, THIS WAS SOME GOOD SUMMARIZED INFORMATION THAT SHOWED ALL THE PRICES THAT YOU GUYS MAY HAVE HEARD OR SEEN TODAY.
IT REALLY HAS A SIDE BY SIDE COMPARISON LINE ITEM FOR THE DIFFERENT COMPONENTS, THE REMEDIATION, THE ACTUAL DESIGN AND BUILD, ETC., AS WELL AS THE SCORE SHEETS FROM THE EVALUATION COMMITTEE HAD SCORED.
SO WITH THAT BEING SAID, WE'RE REALLY JUST OPEN TO FEEDBACK FROM THE COMMISSION ON WHAT YOU'VE SEEN AND HEARD TODAY.
ANY FEEDBACK IN THAT REGARD WILL BE VERY MUCH APPRECIATED AND HELPFUL.
>> I NOTICED THAT IN SOME OF THE PRESENTATIONS, THEY HAD RENDERINGS AND PICTURES AND THAT SORT OF STUFF, AND SOME PEOPLE DID NOT.
WAS THAT A REQUIREMENT FOR THEM TO SHOW RENDERINGS?
MATTER OF FACT, WHEN WE ISSUED THE RFP, WE ACTUALLY HAD A CONCEPTUAL RENDERING JUST TO POSITION THE DIFFERENT THINGS WE WANTED.
IT WASN'T A REQUIREMENT, BUT IT'S [OVERLAPPING].
>> WE'LL LET MUSTAFA SPEAK ON THAT.
>> FOR THE RECORD, MUSTAFA [INAUDIBLE] SERVICE DIRECTOR.
IT IS A REQUIREMENT, COMMISSIONER, TO PROVIDE CONCEPTUAL DRAWINGS AND RENDERINGS, AND THAT WAS PART OF THE EVALUATION CRITERIA AS WE HAVE ESTABLISHED IT WITH THE CITY MANAGER OFFICE.
[02:00:01]
SO SOME OF THE FIRMS DID NOT PROVIDE THOSE RENDERINGS, AND THAT REFLECTED IN THEIR SCORES THAT YOU HAVE IN FRONT OF YOU FROM THE COMMITTEE.>> MR. BOLTON, ARE YOU STILL THINKING OF QUESTIONS OR ARE YOU DONE?
>> I'M JUST LOOKING AT THE SCORES.. ALL RIGHT.
WHY DO YOU THINK THAT THE HIGHEST ONE IS 14 MILLION AND THE LOWEST IS EIGHT MILLION?
>> IN GENERAL, WE SHARE THAT, WE HAVE THIS EIGHT ACRE LOCK, WE WANTED THESE DIFFERENT THINGS ON THERE.
THE REASON I THINK THE PRICE IS DIFFERENT BECAUSE WE ESSENTIALLY ASKED THEM TO PICTURE US A DESIGN.
WE TOLD WHAT WE WANTED, SPLASH PAD, PLAYGROUND.
BUT I THINK THEY PROPOSE DIFFERENT THINGS OR DIFFERENT LAYOUTS WITH DIFFERENT MATERIALS.
FOR EXAMPLE, ONE'S USING A CERTAIN TYPE OF TURF MATERIAL, THAT'S OF HIGHER QUALITY, OBVIOUSLY, THEIR PRICE WOULD BE HIGHER IF THEY'RE PROPOSING A BETTER MATERIAL, AS WELL AS LAYOUT IN DIFFERENT WAYS TO GO ABOUT THINGS.
ESSENTIALLY IT'S DESIGN BUILD.
WE SAID WE WANT THESE THINGS, BUT WE DIDN'T SAY YOU NEED TO USE THIS TYPE OF MATERIAL OR SPECIFY ALL THE DETAILS OF EVERYTHING.
WE WANTED THEM TO SUGGEST THE DESIGN TO US.
I THINK THAT DICTATED THE PRICE BASED ON WHAT DESIGNS THEY OFFERED AND SOME OFFERED A LITTLE BIT MORE OR LIKE I SAID, BETTER MATERIAL OR A LITTLE EXTRA.
I THINK THOSE THINGS DICTATED THE DIFFERENCE IN PRICE.
BUT IN GENERAL, WE ASKED FOR SOMETHING, THEY PROPOSE SOMETHING, AND THAT TENDS TO LEAD TO NEGOTIATIONS TO GO BACK AND FORTH AND HAVE DISCUSSIONS TO COME AT A FINAL PRODUCT.
>> BASED ON WHAT YOU ASKED FOR.
ALL FOUR OF THESE PROVIDED WHAT CHECKED THE BOXES FOR EACH OF THE THINGS YOU ASKED FOR?
>> CORRECT. WE HAD A LIST OF CERTAIN THINGS, AND YOU HEARD HIM GO OVER THE SPLASH PAD.
YOU'VE SEEN THAT QUITE A BIT, THE DOG PARK, YOU'VE HEARD A COUPLE OF TIMES TODAY, THE PLAYGROUND.
WE HAD THESE ITEMS, AND THAT'S REALLY WHAT THEY HAD TO MAKE SURE WAS INCORPORATED IN THEIR DESIGN, BUT IT WAS UP TO THEM IN TERMS OF THE LAYOUT AND OTHER THINGS, AS LONG AS IT INCLUDED THOSE THINGS.
>> IF YOU MAY ALLOW ME TO INTERJECT HERE, COMMISSIONER, JUST TO CLARIFY A COUPLE OF POINTS AND TO ECHO ON YOUR QUESTIONS.
WE HAVE PUT OUT A REQUIREMENT OF WHAT WE WANT TO PUT IN THE PARK AS FAR AS FIELD AND WHAT HAVE YOU.
THERE ARE MATERIALS THAT WHAT WE, THE CITY, EXPERIENCE-WISE, WHAT WE'D LIKE TO HAVE, AND THAT'S MENTIONED IN RFP.
FOR EXAMPLE, THE FIELD TURF, WHAT FIELD TURF WE WANT? UNFORTUNATELY, NOT ALL PROPOSERS HAD GIVEN US WHAT WE ARE ASKING.
SO THAT'S WHERE THE PRICE DIFFERENT COMES IN A ROLE.
>> WHAT DOES THAT MEAN, THEY DIDN'T GIVE YOU ALL THE THINGS THAT YOU ASKED?
>> FOR EXAMPLE, ONE OF THE PROPOSERS DID NOT GIVE US THE FIELD TURF.
THE FIELD TURF IS THE MERCEDES PRODUCT OF THE TURF.
THE FIELD TURF IS THE MANUFACTURER THAT MANUFACTURES A SYNTHETIC TURF FIELD.
SOME OF THE BIDDERS DID NOT MENTION WHAT TURF THEY'RE USING.
AND OTHERS GAVE AN ALTERNATE, THAT'S WHERE PRICE PLAYS A BIG ROLE IN A BIG DIFFERENCE HERE, BECAUSE PRODUCTS ARE NOT EQUALLY OR APPROVED EQUALLY IN THAT SENSE WHEN HE COMPARES IT TO EACH OTHER.
THAT'S WHERE THE PRICE PLAYS A BIG ROLE OR BIG DIFFERENCE HERE.
WHAT WE HAVE SEEN, AND YOU COULD SEE IN THE SCORES THERE, THE HIGHEST BIDDER THERE HAVE GIVEN THE MATERIALS THAT WAS REQUESTED IN RFP.
SO THE HIGHEST ONE MET ALL THE PRODUCTS THAT WE'RE ASKING IN RFP.
OTHERS DID NOT GIVE US ALL WHAT WE HAD ASKED IN THERE.
THEY CHANGED DIFFERENT PRODUCTS.
THEY MIGHT NOT BE EQUALLY AS WHAT WE HAD ASKED FOR.
FURTHER EVALUATION NEEDS TO BE DONE TO MAKE SURE THAT THIS IS AN EQUAL PRODUCT.
>> IS THAT SOMETHING YOU COULD NEGOTIATE MOVING FORWARD ONCE WE CHOOSE?
>> NOT MAY, CAN YOU? AND THE ANSWER IS YES OR NO.
>> WELL, WE CAN, BUT THE PRICE WILL GO UP.
>> THERE'S A QUESTION AND THAT WOULD HAVE BEEN MY NEXT QUESTION.
[02:05:01]
>> RIGHT, SO IT'S A YES OR NO.
>> THAT'S PROCUREMENT. WHAT [INAUDIBLE]
>> SO THE PRICE WOULD PROBABLY GO UP AS HIGH AS THE HIGHEST BIDDER OR NOT? GO AHEAD, CITY ATTORNEY.
>> IT DEPENDS ON WHAT THE MANAGER INDICATED EARLIER, THIS IS A DESIGN BILL.
AND DEPENDS ON THE SCOPE OF DESIGN AND SOME OF THE AMENITIES THAT THIS COMMISSION, THE MAYOR SAY PICKET BALL IS SOMETHING THAT MAY NOT WANT AT THAT PARK, SO THAT MAY BE ELIMINATED.
SO THE MANAGER AFTER GETS CONCEPTUAL DESIGN AND GETTING THE PRICE CROWD, IF THESE AMENITIES MEET AT LEAST HIS LIKING, HE HAS TO AT LEAST GET YOU GUYS TO AGREE WITH IT.
AND THEN HE CAN GIVE YOU A GOOD PRICE.
>> SO THEN IT MAKES SENSE TO GO LOWER AND THEN GO HIGH?
>> MANAGER YOU WANTED TO SAY SOMETHING.
>> I JUST WANT TO POINT OUT THAT THESE PROPOSALS IF THEY'RE BEFORE YOU, THAT MEANS THAT THEY PROVIDE A VIABLE PRODUCT AND THAT RFP REQUIREMENTS SAY THIS OR ALIKE OR THIS OR EQUAL.
AND WE DO REALIZE THAT ONE TYPE OF MATERIAL IS BETTER THAN THE OTHER, WE WOULD EITHER ACCEPT IT OR NOT ACCEPT IT.
BUT CLEARLY, I DON'T THINK WE ELIMINATED ANYBODY'S RESPONSE OUT OF THESE QUESTIONNAIRES BECAUSE THEY DON'T MEET ANY OF THE SPECIFICATIONS.
THEY DO. AND THAT'S WHY OUR [OVERLAPPING]
>> I CAN SPEAK TO THAT. ON ANY SOLICITATION PROCESS, YOU WANT ALL THE BITS TO BE RESPONSIVE AND RESPONSIBLE.
RESPONSIVE, THEY PROVIDED ALL THE FORMS, EVERYTHING THAT'S NEEDED, RESPONSIBLE, THEY HAVE THE RESOURCES, CAPACITY, ET CETERA.
THEY DON'T GET TO THE EVALUATION STAGE UNTIL THEY CHECK ALL THE BOXES THAT THEY PROVIDED EVERYTHING THAT NEED TO BE SUBMITTED.
>> SO EVERYBODY HAS PROVIDED EVERYTHING.
>> EVERYBODY HAS QUALITY PRODUCT THAT WE'RE ASKING FOR.
>> YES. AND ONCE AGAIN, THE SCORES OF 78-84 AND CHANGE, CALL IT 85, SEVEN SEVEN-POINT DIFFERENTIAL, REALLY ALSO SHOWS IN TERMS OF SCORE, AND THIS IS THE AVERAGE SCORE AMONG SEVEN PEOPLE THAT THEY WERE ALL ESSENTIALLY WITHIN THE SAME RANGE.
SO THEY ALL DEMONSTRATED THE CAPACITY AND ABILITY, QUALITY-WISE, TO PROVIDE OR COMPLETE THIS PROJECT.
>> THIS IS JUST LIKE OVER THE WEEKEND, I NOTICED THAT MY PHONE WALLET IS COMING APART.
SO I WENT ON AMAZON TO LOOK FOR THE SAME PHONE CASE, AND IT WAS ABOUT $30.
MY FRIEND HAS THE SAME PHONE CASE, EXACT SAME PHONE CASE, AND HE BOUGHT IT ON SHEIN FOR $3.
>> SO YOU'RE BUYING A NEW PHONE ON SHEIN, A NEW CASE ON SHEIN, AND YOU'RE TELLING US.
>> MAYBE SOMETIMES IT'S NOT THE PRODUCT, BUT IT'S THE SUPPLIER OR YOUR RELATIONSHIPS AS THE SUPPLIER, I DON'T KNOW.
>> I THINK IT'S A COMBINATION OF ALL OF THOSE THINGS.
I THINK WE SAW SOME FOLKS WHO WAS SHOWING I GUESS A PLAYGROUND, I GUESS THE INFRASTRUCTURE WORK, 20 YEARS AGO, ET CETERA.
ALL OF THESE DIFFERENT THINGS AFFECT THE PRICE IN TERMS OF SOME ARE GOING TO DO A BIT MORE, BETTER MATERIAL, THE STRUCTURE OF IT, THAT SORT OF THING.
ALL THESE DETAILS IS WHAT DICTATE THE RANGE OR HOW HIGHER LOADED PRICES.
>> IF I MAY, THE MORAL OF THE STORY IS THAT YOU HAVE FOUR QUALIFIED VENDORS THAT THEY CHECKED ALL THE BOXES THAT WE IDENTIFIED, ALL OUR REQUIREMENTS AND SO YOU'VE SEEN THEIR PRESENTATIONS, YOU'VE SEEN THEIR APPROACH TO THE PROJECT, YOU'VE SEEN THEIR PROJECT TEAMS AND WHAT THEY BRING TO THE PROJECT, HOW THEY GO ABOUT IT, AND THEIR TIMELINE AND THEIR EXPERIENCE.
THOSE ARE THE ELEMENTS THAT WE CAN DISCUSS.
>> VICE MAYOR. ARE WE VOTING NOW OR WE STILL?
>> YOU STILL TALKING? [OVERLAPPING] YOU NEED CONSENSUS OR NOT?
>> MY SUGGESTIONS GIVE TO CITY MANAGER YOUR PREFERENCE, IF YOU HAVE ANY.
>> I WOULD SAY MY PREFERENCE IS INSTEAD OF MAKING IT LONG BECAUSE WE JUST SAW EVERYTHING.
I KNOW ONE OF OUR CONCERN IS THAT WATERPAD.
THE GUY SAID, LET HIM BUILD IT, BUT WHATEVER YOU'RE LIKE THE HIGHEST.
I WAS WITH THE MATTER, THE PRICE.
I THINK WE GO WITH THE CHEAPEST AND WE NEGOTIATE FOR THE BETTER QUALITY.
NOW, WHAT THE BETTER QUALITY IS, I HAVE NO IDEA.
>> CAN YOU DO ME FAVOR SINCE YOU LOOK [OVERLAPPING]
[02:10:07]
>> YEAH, BECAUSE IT'S 8 MILLION AND WE COULD NEGOTIATE FOR THE PRODUCTS WE THINK WE KNOW ARE THE BETTER PRODUCTS.
ESPECIALLY FOR THE WATER, BECAUSE THAT BREAKS DOWN A LOT?
>> SPLASHBACK. AND FOR THE TURF, YOU SAID TURF, YOU WANT TURF.
EVEN THOUGH THAT TURF YOU NEED TO TALK ABOUT THE TURF [OVERLAPPING] IS MESSING UP.
>> DO YOU WANT TO GIVE A SECOND AND THIRD OR YOU ONLY WANT TO GIVE FIRST.
>> AND THEN I GUESS THE SECOND WOULD BE THE HIGHEST ONE BECAUSE HE HAS ALL THE [OVERLAPPING] NO, IT WOULD BE RDC.
AND THEN MY THIRD WOULD BE THE GUIDE THAT SAID HE CAN BUILD THE WATER SPLASHBACK..
>> NOW, KEEP IN MIND, RDC WAS THE MOST EXPENSIVE.
>> RIGHT. BUT THEY SAID ON REASON I'LL PUT.
I JUST WANT THE ONE WITH THE LOWEST PRICE.
>> BUT HE SAID THAT THEY HAVE MET ALL THE QUALIFICATIONS THAT WE ASKED FOR, BUT THEY'RE JUST EXTREMELY EXPENSIVE.
THEY'RE LIKE DOUBLE THE PRICE.
>> COMMISSIONER BOLTON, DO YOU WISH TO GIVE ME YOURS BEFORE I GO TO COMMISSIONER PATTERSON? [BACKGROUND] COMMISSIONER PATTERSON.
>> THANK YOU, MAYOR. JUST FOR CLARITY, WE'RE GIVING CONSENSUS IN THIS SETTING.
>> OR YOU HAVE QUESTIONS TOO RIGHT NOW. CAN YOU ASK YOUR QUESTIONS?
>> I DON'T NECESSARILY HAVE ANY QUESTIONS.
I GUESS IF I WERE TO HAVE ANY QUESTIONS, IT WOULD BE RELATED TO JUST OUR PROCESS AND HOW WE FOUND OURSELF.
THE FIRST GENTLEMAN HAD A LOT OF CONCERNS ABOUT OUR PROCESS.
OBVIOUSLY, THAT RAISED SOME QUESTIONS FOR ME, BUT I GUESS WE CAN HAVE THAT CONVERSATION IN A SEPARATE SETTING.
>> MISS PATTERSON, I THINK THEY RELATE TO THE PREVIOUS PROCESS.
I THINK I CAN EXPLAIN TO YOU OFF THE RECORD.
>> THAT'S WHAT I'M SAYING. I MEAN, I'M FINE WITH HAVING THAT CONVERSATION SEPARATELY.
BUT REGARDING WHERE WE ARE IN TERMS OF REVIEWING AND EVALUATING THE PROJECTS AS PRESENTED.
IN TERMS OF THE EXPERTS, I THINK THAT THE BUILDERS ARE THE EXPERTS.
I THINK WHAT WE SAW MET THE CRITERIA, ALTHOUGH I DON'T KNOW WHAT THE CRITERIA WAS AS PRESENTED TO THE PUBLIC.
I DON'T KNOW WHAT WE ASKED FOR.
BUT IF THE STAFF IS SAYING THAT THEY MET THE REQUESTS OF THE CITY IN TERMS OF DELIVERING A PROJECT AND A PRODUCT, I'M COMFORTABLE WITH THAT.
I THINK THAT CERTAIN THINGS I WAS LOOKING FOR, LOCAL CONTRACTORS, LOCAL PREFERENCE, OBVIOUSLY, COMMUNITY INPUT, WHETHER OR NOT THE TEAM WOULD BE WILLING TO WORK WITH THE STAKEHOLDERS HERE ON THIS BOARD TO DELIVER A PROJECT THAT WOULD I THINK, BE MUTUALLY AGREEABLE, ARE THE THINGS THAT I WAS LOOKING FOR OUT OF THE THREE OR FOUR OF THEM, AND DIVERSITY.
I WAS INTENTIONALLY OBSERVING JUST WHAT THE DYNAMICS ARE.
I THINK THAT I WOULD BE MOST INCLINED TO ALSO SUPPORT THE LAST PROJECT AS PRESENTED FOR ALL OF THOSE REASONS.
I THINK THEY WERE THE ONLY ONES THAT PRESENTED ALL OF THOSE ELEMENTS FROM MY LENS.
I SAW A VERY DIVERSE TEAM, I SAW LOCAL VENDORS.
I SAW A GROUP THAT WAS WILLING TO WORK AND ENGAGE THE COMMUNITY.
THEY DID PROVIDE FOR AN ELEMENT IN THEIR PRESENTATION TO US THAT SPOKE TO COMMUNITY OUTREACH, AND I THINK OUR RESIDENTS WOULD APPRECIATE THAT.
I THINK THAT THEY LEFT THEIR PROJECT BROAD ENOUGH TO ALLOW FOR ENGAGEMENT FROM THIS COMMISSION AND THE COMMUNITY STAKEHOLDERS.
THEY DIDN'T COME, ALREADY READY WITH A CONCEPT.
THEY CAME WITH THE FRAMEWORK AS REQUESTED BY STAFF AND LEFT ENOUGH ROOM FOR US TO BE ABLE TO GET THERE.
I PERSONALLY DID APPRECIATE THAT, AND IF I WERE TO MAKE A RECOMMENDATION, IT WOULD BE FOR FRANCHISE BUILDERS.
>> DO YOU HAVE A SECOND? OR NOT ONE THAT YOU WISH TO SAY RIGHT NOW?
>> I'VE GOT TWO PEOPLE I'VE SPOKEN TO, AND SOMETIMES I GET TO A TIE.
THAT'S WHY I WAS ASKING. COMMISSIONER BOLTON DOESN'T LOOK LIKE HE'S READY TO SPEAK. COMMISSIONER WRIGHT.
>> THANK YOU, MADAM MAYOR. IN GOING OVER AND LOOKING AT MY NOTES, I JUST SAW THE SHEET, THE BID SHEET THAT YOU GUYS PROVIDED,
[02:15:02]
IT WAS IN MY EMAIL, SO EXCUSE ME.BUT IN TERMS OF MY NOTES, I LIKE RDC.
I SAW THAT THEY HAD A LOT OF EXPERIENCE.
THE DESIGNS WERE VERY WELL THOUGHT OUT.
THEY INVOLVED THE STAKEHOLDERS.
ALSO, THEY WERE VERY FOCUSED ON PROTECTING THE RESIDENTS FROM ARSENIC IN THE SOIL.
AND THEN THAT'S A BIG ISSUE IN THE NEIGHBORING DISTRICT IN DISTRICT TO IN THE WOODLANDS, AND THEY HAD A VERY THOUGHT-OUT PLAN FOR THE SURROUNDING AREAS AS WELL IN TERMS OF MONITORING THE WIND AND THAT TYPE OF STUFF.
THE DRAINAGE ASPECT OF THEIR PRESENTATION WAS VERY DETAILED.
THEY HAD A DESIGN THAT SHOWS A CONCEPT OF WHAT IT LOOKED LIKE.
HOWEVER, WHEN IT CAME TO THE PRICE, IN COMPARING TO OTHER PRICES, IT WAS DOUBLE COMPARED OR FRANCHISE.
FRANCHISE HAD A WELL-ORGANISED TEAM.
THE DESIGN WAS FANTASTIC, AS WELL.
I LIKE THE PROUD OF PARK THAT THEY'RE WORKING ON IN DOWN SOUTH.
THEY'RE ALSO WORKING ON THE FORT LAUDERDALE PARK AT THE STADIUM. I THINK THAT WAS GREAT.
THE DESIGNER IS A LOCAL RESIDENT, SO YOU UNDERSTAND THE LAY OF THE LAND THE COMMUNITY, WHAT PEOPLE LIKE.
I ALSO SAW DIVERSITY WITH THEIR TEAM.
I SAW JAMES ALEXANDER EXPERIENCE WITH MERMEN.
THEY ALSO HAVE A COMMUNITY FOUNDATION WHERE THEY'RE WILLING TO GIVE BACK TO THE COMMUNITY.
SO THEY WANT TO BE STAKEHOLDERS AND PART OF THE COMMUNITY.
THEIR COST, OBVIOUSLY, WAS THE LOWEST AT 8 MILLION.
GOING TO THE OTHER FIRM'S WAYPOINT.
THEY ALSO HAD A GOOD TEAM, NOT AS GOOD AS OTHER PEOPLE.
THEY HAD SUB-CONSULTANTS THAT THEY'VE WORKED WITH BEFORE.
THEIR PRICE WAS A LITTLE HIGHER AT 10 MILLION.
AND THEN THE FIRST PRESENTERS, THEIR PRICE WAS HIGH.
THEY SPOKE ABOUT ARSENIC, NOT AS DETAIL AS RDC.
THEY SAID NO CHANGE ORDERS, AND THEY SAID SOMETHING WORKING ALLOWANCE OR 978 FOR ALLOWANCE.
I DIDN'T REALLY UNDERSTAND WHAT THAT MEANT.
I DON'T KNOW IF THAT WAS LIKE A COMMUNITY BENEFIT OR SOMETHING.
I WASN'T SURE WHAT THAT WAS ABOUT.
>> COMMISSIONER WRIGHT JUST ONE SECOND, EITHER MASA OR STEPH. WE GIVE YOU [OVERLAPPING]
>> I CAN RESPOND BACK TO THAT.
IN THE FIRST RFP PACKAGE THAT WE HAD IN THE PAST BEFORE WE SCRAMBLED THAT PACKAGE, THAT WAS AN ALLOWANCE THERE AND THIS NEW RFP THAT WE PUT OUT DOESN'T HAVE THE ALLOWANCE.
I THINK THE BIDDER DID NOT REALLY READ THE PACKAGE THOROUGHLY ON THE NEW RFP.
SO HE KEPT REFERRING TO THE OLD RFP, AND THAT ONE HAD AN ALLOWANCE.
THIS ONE DIDN'T HAVE AN ALLOWANCE.
>> THANK YOU. GO AHEAD. COMMISSIONER.
>> MY FIRST CHOICE WOULD BE RDC, NOT AT THAT PRICE.
IF THEY'RE WILLING TO COME LOWER, THAT WILL BE MY FIRST CHOICE.
BUT IF NOT, I WOULD GO A FRANCHISE BASED ON PRICING BASED ON DESIGN, BASED ON THE FACT THAT I UNDERSTAND THE COMMUNITY AND THE FACT THAT THEY'VE DONE PARKS AND SIMILAR PARKS OF WHAT WE'RE LOOKING FOR.
SO THAT WOULD BE MY FIRST CHOICE IF RDC CAN'T COME DOWN ON PRICE.
>> THANK YOU VERY MUCH. COMMISSIONER BOLTON.
COMMISSIONER BOLTON, IT'S YOUR DISTRICT.
>> ALL FOUR OF THEM HAD SOMETHING TO OFFER.
BUT I CAN'T, IN GOOD CONSCIENCE, UNDERSTANDING BUDGETS AND WHAT FINANCE DEPARTMENT HAS SAID WE'RE HEADING FOR DISASTER.
I MEAN, COMMISSIONER WRIGHT SAID IT BEST RDC HAD A VERY GOOD PROPOSAL.
BUT 14 MILLION IS JUST A BIG NO.
DE POMPEO, THEY HAD A VERY GOOD PROPOSAL.
ACTUALLY, THE ONE THAT I LIKED THE MOST, AND THAT'S WHERE I WAS HEADED.
HOWEVER, THE GENTLEMAN THAT WAS SPEAKING WAS VERY ARROGANT.
AND THAT CAN'T GET OUT OF MY HEAD.
I THINK THAT IF HE WAS JUST A LITTLE BIT MORE MELLOW AND SOFT, AND JUST PRESENTED THE INFORMATION AND JUST TOLD US WHAT HE'S GOING TO DO, EXCEPT FOR JUST BAD MOUTHING OTHER PEOPLE AND BAD MOUTHING THE PROCESS.
I THINK THAT I'LL BE STICKING OUT FOR THEM.
FOR THAT REASON, IF HE'S LISTENING, HE SHOULD GET A PR PERSON OR A PRESENTER.
[02:20:04]
>> TO THEM, I BELIEVE YOUR PROPOSAL THE POMPEO.
YOUR PROPOSAL, I THINK, WAS THE BEST ONE.
IT LOOKED LIKE SOMETHING THAT I'D WANT IN DISTRICT 1.
YOU KNOW WHAT I'M SAYING? BUT I JUST WISH THAT HE WASN'T.
BUT IN MY MIND, THEY TIED WITH FRANJO.
BOTH OF THOSE IN MY MIND TIED.
IF I WERE TO GO WITH AN ANSWER, IT WOULDN'T BE DI POMPEO. I'M JUST THINKING OUT LOUD.
IT WOULDN'T BE DI POMPEO BASED ON THEIR PRESENTATION.
THEIR PROPOSAL WAS GREAT, BUT NO.
IT WOULDN'T BE RDC BASED ON PRICE.
IT'S BETWEEN FRANJO AND WAYPOINT, AND IT SEEMS LIKE MY COLLEAGUES ARE GOING TOWARD FRANJO.
THAT'S MY PICK, BUT I HAVE A CAVEAT.
THE PRICE STILL BOTHERS ME [LAUGHTER] BECAUSE I'M THINKING EIGHT MILLION, 14 MILLION.
I WANT TO BE FISCALLY RESPONSIBLE, AND I WANT TO SAY, GO WITH THE LOWEST BIDDER BECAUSE OF PRICE, AND I DON'T WANT TO PAY MORE.
[LAUGHTER] LET'S MAKE IT CLEAR.
DON'T BE SAYING, BOLTON WANTS TO SPEND MORE CITY MONEY, NO.
THAT'S NOT WHAT I'M SAYING, IS JUST EIGHT MILLION VERSUS 14 MILLION, OR EIGHT MILLION VERSUS 10 MILLION, OR EIGHT MILLION VERSUS 11 MILLION. THAT'S A BIG DIFFERENCE.
I'M NOT SAYING THAT THE COMPANY SHOULD HAVE BID MORE; I'M JUST SAYING THAT THE PRICE BOTHERS ME.
SO IF FRANJO IS THE ONE THAT WE SELECT, JUST MAKE SURE THAT WE'RE LOOKING CLOSELY AT PRODUCT AND PRICE POINT SO THAT WE ARE NOT GETTING OURSELVES IN SOME ISSUES DOWN THE ROAD.
BECAUSE I'VE BEEN HERE LONG ENOUGH AND I UNDERSTAND NOW CHANGE ORDERS AND ALL THAT STUFF, AND I'M NOT PLAYING THAT GAME THAT OTHER PEOPLE HAVE PLAYED BEFORE.
I CLOCK IT NOW? CLOCK IT, I CLOCK IT NOW.
THEY COME WITH LOW PRICES, AND THEN ALL OF A SUDDEN, IT'S CHANGE ORDERS UP THE GOZO.
[LAUGHTER] I HOPE I'M STILL HERE.
I HOPE THAT'S NOT THE GAMES THAT PEOPLE ARE PLAYING.
IF WE GO WITH FRANJO, WOULD WE BE SELECTING THEM AND THEIR PRICE, OR WOULD WE BE SELECTING THEM AND NEGOTIATE?
>> THE RESOLUTION IS PREPARED TO SELECT AND ALLOW THE CITY MANAGER AND STAFF TO NEGOTIATE.
>> BUT NEGOTIATE EIGHT MILLION DOWNWARDS OR NEGOTIATE EIGHT MILLION UPWARDS.
WE LOOK AT THE PROPOSAL COMPONENTS, AND WE LOOK AT SOME OF THE PREFERENCES AND WE MAY GO UP OR WE MAY GO DOWN.
BUT THE OBVIOUSLY INITIAL EFFORT WOULD BE TO REDUCE THE PROJECT COST AS MUCH AS POSSIBLE WITHOUT COMPROMISING ON THE ELEMENTS IN THE COMPONENTS IN THE QUALITY OF THE PRODUCT.
>> I HEARD THE FIRST ONE, AND I THINK FROM DI POMPEO SAY THAT THEY BID BEFORE AND THEIR PRICE WAS REJECTED.
WHAT WAS THE PRICE THAT WAS REJECTED?
>> COMMISSIONER BOLTON, I THINK WE DON'T NEED TO DISCUSS THAT.
[OVERLAPPING] NO. FROM A LEGAL STANDPOINT.
>> ALL RIGHT. AS A GENERAL QUESTION, WHAT DO YOU THINK THE PRICE SHOULD HAVE BEEN AS YOU HEARD IT TODAY, MUSTAFA?
>> OUR BUDGET IN THE CIP PROGRAM FOR THIS PROJECT WAS WHAT, SEVEN MILLION DOLLARS?
[02:25:02]
>> IN THE FY24, WE HAVE 7.5 AND WE HAVE TWO POINT SOMETHING FROM PREVIOUS FUNDING, SO A TOTAL IS $9.9 MILLION IN OUR BUDGET.
>> EVEN IF WE WANTED TO CHOOSE WAYPOINT OR DI POMPEO, WE STILL DON'T HAVE $10 MILLION.
WE'D HAVE TO COUGH IT UP FROM SOMEWHERE.
>> OBVIOUSLY, COMMISSIONER, WHAT CITY MANAGER HAD MENTIONED, ONCE WE HAVE CONSENSUS FROM YOU ALL TODAY, THE POINT OF THIS PRESENTATION TO SEE WHAT YOUR PREFERENCE FROM THE DESIGN AND LOOKING AT IT.
NOT REALLY FOCUS ON THE PRICE, WHICH ONE IS YOUR PREFERENCE FROM DESIGN, EXPERTISE, AND THE PRODUCTS.
THAT'S WHERE WE WOULD GO AND NEGOTIATE WITH THEM TO MAKE SURE WE FIT WITHIN THE BUDGET.
IF THERE'S SOMETHING THAT WE CAN'T FIT WITHIN THE BUDGET, WE HAVE TO COME BACK AND TALK TO CITY MANAGER AND THE COMMISSION TO SEE IF THERE'S ANY ALTERNATIVES THAT CAN BE DONE.
BUT THAT WAS THE OBJECTIVE OF THIS TO LOOK AT THE DESIGN, THE EXPERTISE, THE TEAM, THE INVOLVEMENT, COMMUNITY OUTREACH, ALL THAT IS ONE BIG PORTION OR ONE BIG SCENARIO IN THIS ASPECT. IS THAT MAKE ANY SENSE?
>> WELL, I HOPE THAT DI POMPEO WILL BID ON SOMETHING ELSE BECAUSE I REALLY LIKE THEIR PROPOSAL, BUT I HOPE THAT WHEN THEY'RE BIDDING ON SOMETHING ELSE, THEY ARE A LITTLE NICER.
>> COMMISSIONER WRIGHT, YOU WISH TO SPEAK?
>> YES, THANK YOU, MADAM MAYOR. MUSTAFA, YOU SAID DESIGN. LOOK AT THE PRICING.
WHEN I LOOK AT RDC'S BREAKDOWN FOR DESIGN IS 1.3, I CAN RUN IT TO 1.4, WHEREAS FRANJO IS 565.
YOU MENTIONED THAT RIGHT NOW, WE'RE IN THE DESIGN PHASE, AND THE COST IS NOT NECESSARILY A MAIN THING IN TERMS OF CONSTRUCTION.
BUT WHEN YOU LOOK AT THE BREAKDOWN OF DESIGN, THEY'RE STILL LIKE THREE TIMES MORE THAT OF FRANJO.
I DO AGREE BASED ON THEIR PRESENTATION, THEIR DESIGN PRESENTATION IS BETTER.
THEY SEEM TO HAVE A BETTER TEAM.
THEIR PROJECTS AND THE AESTHETICS OF THEIR PROJECTS THAT THEY'VE DONE BEFORE SEEM TO BE VERY MODERN-LOOKING, AND IN AFFLUENT COMMUNITIES, I SEE BAY HARBOR AND THOSE PLACES.
I ALSO SEE GOOD PROJECTS WITH FRANJO AS WELL.
BUT ON YOUR POINT, YOU SAID IT'S BOTH DESIGN.
LOOKING AT THE PRICE IN TERMS OF DESIGN OF BOTH COMPANIES, AND ALSO LOOKING AT YOUR SHEET, SCORED 84.
WHY WERE THEY THE HIGHEST? WHY WERE RDC THE WINNER AND NOT FRANJO, OUT OF CURIOSITY? I DON'T LOOK AT THE BREAKDOWN OF THE SCORE.
I GOT THE FINAL POINTS, BUT OUT OF CURIOSITY, WHAT WAS THEIR ADVANTAGE BASED ON YOUR SHEETS?
>> COMMISSIONER, [NOISE] BASICALLY THE COMMITTEE WAS LOOKING AT THE RESPONSES OF EACH BIDDER BASED ON THE CRITERIA THAT WERE MENTIONED IN THE RV PACKAGE, AND THAT'S HOW WE SCORE THEM.
THE COMMITTEE SAW THAT RDC HAVE THE HIGHEST TECHNICAL EXPERTISE; THEIR PROPOSALS, RENDERINGS, AND CONCEPTUAL DRAWINGS WERE WELL THOUGHT THROUGH AND PUT TOGETHER.
THAT'S HOW THEY SCORED HIGH FROM THE TECHNICAL ASPECT OF IT AND FROM THE PRODUCT THEY WE'RE OFFERING.
PRICE-WISE, THE PROCUREMENT DIVISION HANDLED IT AND DID THE MATRIX, THE AVERAGE DOWN, AND HOW MUCH THE SCORE WOULD BE WHEN IT COMES TO PRICING.
THE COMMITTEE ITSELF DID NOT REALLY LOOK AT THE PRICING ITSELF, ALTHOUGH THE PROCUREMENT DEPARTMENT LOOKED AT THE PRICING.
GOING BACK TO MY POINT, I APOLOGIZE IF I MISCOMMUNICATED.
WE ARE OBVIOUSLY LOOKING AT THE PRICING WHEN IT COMES TO ASKING FOR YOUR CONSENSUS AND APPROVAL HERE.
BUT MAIN POINT IS BECAUSE THIS IS A NEGOTIATION PROCESS, THIS IS A DESIGN-BUILD NEGOTIATION PROCESS.
BUT WHAT I WAS TRYING TO EMPHASIZE OR PUT OUT POINT IS, NOT NECESSARILY THE CHEAPEST IS THE BEST.
THAT'S WHERE WE HAVE TO ALIGN ON BASED ON EXPERTISE, THE TEAM, AND WHAT WE'RE PUTTING TOGETHER AND WHAT WE'RE ASKING FOR.
OUR CITY ATTORNEY, MR. HANS, CAN ATTEST TO THE CHEAPEST IS NOT THE BEST FROM HIS EXPERIENCE IN DEALING WITH CONTRACTORS, AND EVERY SINGLE OTHER PERSON WHO HAVE BEEN INVOLVED IN CONSTRUCTION CAN ATTEST TO IT AS WELL.
I'M NOT SAYING NOT TO GO WITH THE CHEAPEST, BUT THE SAME TIME, WE'RE ASKING TO GET YOUR CONSENTS AND GET FEEDBACK FROM YOU FOR WHAT WE HAVE SEEN YOU HAVE HEARD TODAY FROM THE DIFFERENT PROPOSALS.
>> BUT THEY ARE DOUBLE THE PRICE.
IF THERE WERE A NINE OR 10, THEN I WAS LIKE, WE PULL OUT A PREMIUM FOR THEIR DESIGN EXPERTISE AND THE EXPERIENCE.
BUT DOUBLE THE PRICE, I DON'T SEE THAT THE DESIGN AND THE EXPERTISE IS DOUBLE THE PRICE OF FRANJO,
[02:30:04]
WHICH I THINK CAME IN SECOND IN MY BREAKDOWN.MR. PATTERSON, IS THAT TURNED AGAIN? GIVE ME ONE SECOND, THE CITY MANAGER WANTS SAY SOMETHING.
>> MADAM MAYOR, I JUST WANT TO SAY, I DON'T WANT TO PUT IT THIS WAY, BUT I DON'T KNOW HOW ELSE I CAN SAY THIS.
>> THIS IS A PARK. THERE'S SOME ELEMENTS THAT REQUIRE, OBVIOUSLY, SOME SIGNS, SOIL REMEDIATION, AND THE DRAINAGE, AND ALL THAT.
BUT AT THE END OF THE DAY, IT'S NOT THE MOST COMPLICATED PIECE OF WORK IN THE WORLD.
THE BUILDING DESIGN THAT WE'RE TALKING ABOUT IS A RESTROOM FACILITY.
NO MATTER HOW MUCH YOU DRESS IT UP, IT'S A RESTROOM FACILITY WITH SOME ELEMENTS.
WE'RE LOOKING FOR BASIC ELEMENTS HERE, GRASS, TURF, AND PLACEMENT OF THE AMENITIES, THE BASKETBALL COURT, AND THESE ARE THE MOST COMPLICATED CONSTRUCTION PROJECTS IN THE WORLD.
THERE'S A BIG DIFFERENCE, A BIG GAP BETWEEN THIS ONE AND THAT ONE.
>> YEAH, I ACTUALLY APPRECIATE THAT YOU JUST SAID THAT, LEVEN.
I THINK THAT IT'S JUST NOT THAT SERIOUS.
PERSONALLY, WHILE I UNDERSTAND, OBVIOUSLY, THERE WAS ONE PRESENTER THAT HAD A SLEW OF IT COMPONENT AS A PART OF THEIR PROPOSAL.
I THINK THE LANGUAGE THAT WAS USED WAS ENHANCEMENTS AND THINGS THAT WILL DRIVE THE COST.
I THINK THAT IF WE'RE LOOKING FOR ENHANCEMENTS, SURELY, ANY OF THE BUILDERS COULD PROVIDE ADDITIONAL ENHANCEMENTS.
I DON'T THINK THAT WE GET HUNG UP THERE.
IT WAS MY INTENTION TO ASK YOU AND MUSTAFA WHAT WE HAD BUDGETED.
I'M GLAD THE COMMISSIONER ASKED THAT QUESTION, AND I THINK WE'RE WELL WITHIN OUR BUDGET WITH FRANJO BUILDERS.
I THINK IT'S A RESPONSIBLE DECISION.
WE HAVE ROOM, IT SOUNDS LIKE, TO ENHANCE BASED ON WHAT THEY PROVIDED AND WHERE WE ARE IN TERMS OF BUDGET.
THE NEGOTIATION PHASE WILL ALLOW FOR SOME ADDITIONAL OPTIONS IN TERMS OF A PARK.
I LIKE THE FACT THAT, AND I JUST WANT TO EMPHASIZE THAT, WHILE THEY DID NOT LOCK US INTO A DESIGN.
I DON'T WANT TO BE LOCKED INTO ANYTHING.
YOU GUYS KNOW THAT I'M GOING TO RESIST IT EVERY TIME.
I LIKE THE FACT THAT THEY PROVIDED SOME CONCEPTS AND GAVE THIS COMMISSION AND THIS CITY FREEDOM TO BE CREATIVE IN TERMS OF WHAT WE ACTUALLY GET.
I DON'T WANT TO BE LOCKED IN BY ANYBODY AND EVERYTHING ELSE THAT WE GOT WITH THE EXCEPTION OF WHOEVER DIDN'T LEAVE THEIR PROJECT, I DON'T REMEMBER THE PROJECT ANYMORE BECAUSE THEY DIDN'T BRING US ONE, BUT WITH THE EXCEPTION OF THAT ONE, I LIKE THE FACT THAT WE CAN NEGOTIATE THE DESIGN THAT THE DISTRICT COMMISSIONER HAS THE ABILITY TO GO IN, COMMUNITY CAN GO IN AND SAY, HEY, WE WANT THIS HERE.
WE WANT A PICKLEBALL CLEARLY, THEY CAN DELIVER.
THEY DID PROVIDE VARIOUS PROJECTS THAT THEY'VE BEEN A PART OF TO INCLUDE THINGS WE'VE NEVER EVEN SEEN BEFORE HERE IN SOUTH FLORIDA.
I THINK THAT'S EVEN PRETTY COOL.
THAT MEANS THAT WE'RE NOT LIMITED IN SCOPE.
I ALSO LIKE THE FACT THAT THEY HAVEN'T DONE BUSINESS IN OUR CITY BEFORE.
I LIKE THE IDEA THAT WE'RE GIVING SOMEONE NEW AN OPPORTUNITY TO BE A PART OF THIS GREAT CITY.
YOU GUYS KNOW I'M NOT A BIG FAN OF WELL, WE'VE DONE THIS BEFORE, OR WE'VE BEEN HERE BEFORE, AND PEOPLE FEEL ENTITLED.
I DON'T LIKE THE ENTITLEMENT MINDSET.
I THINK IT'S GREAT THAT WE ARE DIVERSIFYING OUR OPPORTUNITIES HERE IN THE CITY TO INCLUDE A GROUP THAT DOES INCORPORATE A RESIDENT, A, B, VENDORS THAT ARE FROM THE LOCAL AREA.
I'M GOING TO CONTINUE TO RE-EMPHASIZE AND REITERATE THAT.
I THINK WE'VE GOT A GREAT OPPORTUNITY IN FRONT OF US WITH THIS GROUP.
I THINK WE ARE BEING FISCALLY RESPONSIBLE BY SELECTING THEM.
THE MAYOR MADE A POINT, AND I NORMALLY DO SAY THE SAME THING.
I NORMALLY MAKE A POINT AND ASK WHAT DOES THE DISTRICT COMMISSIONER WANT, BUT I ASSUMED THAT WE WOULD ALL AGREE THAT THE LOWEST BIDDER WOULD HAVE BEEN THE BEST BIDDER, BUT MAYBE NOT.
HE POINTED OUT THAT THE DISTRICT COMMISSIONER SHOULD HAVE LED.
MAYBE WE SHOULD LET HIMALK TO IT.
>> HE DIDN'T WANT TO. IT'S NOT THAT HE WASN'T GIVEN THE OPPORTUNITY. HE DIDN'T WANT TO.
>> ALL RIGHT. WELL, THOSE ARE JUST MY EXTRA REMARKS. THANKS.
>> BECAUSE I KNOW EVERYBODY WANTS TO GET OUT OF HERE.
I SEE PEOPLE LIKE SHIFTING IN THEIR SEATS.
I'M NOT GOING TO BELABOR IT TOO MUCH.
IT'S EVIDENT THAT THERE HAS BEEN A SELECTION OF PREFERENCE FOR FRANJO,
[02:35:03]
AND I WILL SAY, IN MY OPINION, WHAT WAS PROVIDED TO US IN A LAYOUT WAS WHAT THE CITY PARK AND REC PROGRAM CREATED YEARS AGO.I WAS A LITTLE SURPRISED THAT WE DID NOT HAVE MORE OF A DESIGN.
FOR ME, IT FEELS LIKE WE ARE A LITTLE BIT BACK AT THE BEGINNING VERSUS WHERE WE SHOULD BE AT THIS POINT IN TIME SINCE THIS COMMUNITY WAS PROMISED THIS PARK.
I'M TEMPTED TO SAY ALMOST 10 YEARS AGO NOW.
THAT HAS ME A LITTLE BIT CONCERNED.
I FEEL LIKE WE'RE PLAYING A GAME OF CHUTES AND LADDERS, AND WE'RE NOT AS CLOSE AS WE SHOULD BE BECAUSE WE SHOULD BE AT A PLACE, IN MY OPINION, WHEN THE RFP IS OUT, WE'VE ALREADY HAD THOSE MEETINGS.
WE'RE READY TO GO. HERE'S WHAT YOU GOT.
THERE SHOULDN'T BE TOO MUCH MORE ON THE NEGOTIATIONS, AND FOR ME PERSONALLY, I FEEL WE'RE ALL THE WAY BACK IN THE BEGINNING.
ONE THING, CITY MANAGER, I THINK YOU DID LEAVE OFF WAS AN IMPORTANT THING.
REMEDIATION. THAT IS A BIG THING.
MAJOR THING, MORE THAN WHETHER OR NOT THIS IS A SPLASH PAD OR ANYTHING ELSE.
BUT YOU'RE GOING TO NEGOTIATE WITH FRANJO.
THAT IS THE SELECTION AT THIS TIME.
I'M PRETTY SURE FRANJO IS HEARING THE CONCERNS OF BUDGET.
DO IT RIGHT. I DO BELIEVE SOMETIMES YOU GET WHAT YOU PAY FOR.
I'M NOT SAYING THAT BEING THE CHEAPEST ISN'T A GOOD QUALITY; SOMETIMES THAT DOES HAPPEN.
I DON'T LIKE THAT SOMETIMES WE SAY GO RUN, AND THEN WE NEVER SEE IT AGAIN AND ALL OF A SUDDEN WE ARE GET PLEASE DO AN AMENDMENT TO THE BUDGET BECAUSE THINGS HAVE GONE UP AND WE HAVE NOT SEEN WHY IT'S GONE UP, WHAT HAS BEEN REMOVED FROM A PROJECT, THAT'S HAPPENED ON A FEW THINGS, AND WE HAVE ANTICIPATED THE PROJECT TO BE COMPLETE.
HAVE A LITTLE DISCONCERTION ON THAT.
I AM HAPPY WITH RESIDENT BEING IN HERE.
I AM HAPPY YOU HAVE ONE OF THE BONUS ITEMS HERE.
I'M PRETTY SURE IF YOU GUYS LOOK AT YOUR GROUP OF PEOPLE, YOU HAVE A VETERAN OR TWO IN YOUR MIDST TO SHOW THAT AS WELL AND SOME OTHER PLAYERS IN THERE.
CITY MANAGER, YOU'VE GOT THE CONSENSUS OF THE TEAM.
IS THERE ANYTHING ELSE FROM PROCUREMENT FOR PUBLIC SERVICES THAT WE NEEDED TO DO FOR YOU GUYS TODAY?
>> NO. NOTHING ELSE. THANK YOU, MAYOR.
>> LADIES AND GENTLEMEN. IT IS 3:05 PM.
GET ON SAFELY. GOOD NIGHT.